Figure: 30 TAC §113.2079(a)(4)
Table 12. Shutdown Extension Requirements.
Analysis of Need | Document the analysis undertaken to support the need for a shutdown extension, including an explanation why one year is insufficient. |
Analysis of Off-site Transport Option | Evaluate the option of temporary or permanent transport of the waste offsite to a commercial medical waste treatment and disposal facility. |
Shutdown Plan Must specify measurable and enforceable incremental steps of progress (dates) toward shutdown. |
Installing Alternative Treatment Technology (ATT) Contract award for ATT vendor. Initiate of on-site construction or installation of ATT. Complete on-site construction or installation of ATT. Shutdown of existing HMIWI unit. Render existing HMIWI unit inoperable |
Contracting With Commercial Waste Treatment & Disposal Company
(WTDC) Obtain price quotes for commercial disposal services. Contract start with WTDC. Shutdown of existing HMIWI unit. Render existing HMIWI unit inoperable. |