RULE §133.162New Construction Requirements

        (III) Monolithic ceilings. Ceilings which are monolithic from wall to wall (painted solid gypsum wallboard), smooth and without fissures, open joints, or crevices and with a washable and moisture impervious finish.

      (vii) Special construction. Special conditions may require special wall and ceiling construction for security in areas such as storage of controlled substances and areas where patients are likely to attempt suicide or escape.

      (viii) Flammable anesthetizing locations. Flammable anesthetic locations in which flammable anesthetic agents are stored or administered shall comply with Annex E of the National Fire Protection Association 99, Standard for Health Care Facilities, 2002 edition (NFPA 99).

      (ix) Materials finishes. Materials known to produce noxious gases when burned shall not be used for mattresses, upholstery, and wall finishes.

      (x) Signage. A sign shall be posted at the entrance to each toilet/restroom to identify the facility for public, staff or patient use. Signs are not required for patient room bathrooms.

  (3) General mechanical requirements. This paragraph contains common requirements for mechanical systems; steam and hot and cold water systems; air conditioning, heating and ventilating systems; plumbing fixtures; piping systems; and thermal and acoustical insulation. The hospital shall comply with the requirements of this paragraph and any specific mechanical requirements for the particular unit of the hospital in accordance with §133.163 of this title.

    (A) Equipment location. When mechanical equipment is exposed to weather, it shall be protected by weatherproof construction or weather protected.

    (B) Vibration isolation. Mechanical equipment shall be mounted on vibration isolators as required to prevent unacceptable structure-borne vibration. Ducts, pipes, etc. connected to mechanical equipment which is a source of vibration shall be isolated from the equipment with vibration isolators.

    (C) Performance and acceptance. Prior to completion and acceptance of the facility, all mechanical systems shall be tested, balanced, and operated to demonstrate to the design engineer or his representative that the installation and performance of these systems conform to the requirements of the plans and specifications.

      (i) Material lists. Upon completion of the contract, the owner shall be provided with parts lists and procurement information with numbers and description for each piece of equipment.

      (ii) Instructions. Upon completion of the contract, the owner shall be provided with instructions in the operational use of systems and equipment as required.

    (D) Heating, ventilating and air conditioning (HVAC) systems. All HVAC systems shall comply with and shall be installed in accordance with the requirements of National Fire Protection Association 90A, Standard for the Installation of Air Conditioning and Ventilating Systems, 2002 edition, (NFPA 90A), NFPA 99, Chapter 6, the requirements contained in this subparagraph, and the specific requirements for a particular unit in accordance with §133.163 of this title.

      (i) General ventilation requirements. All rooms and areas in the hospital listed in Table 3 of §133.169(c) of this title shall have provision for positive ventilation. Fans serving exhaust systems shall be located at the discharge end and shall be conveniently accessible for service. Exhaust systems may be combined, unless otherwise noted, for efficient use of recovery devices required for energy conservation. The ventilation rates shown in Table 3 of §133.169(c) of this title shall be used only as minimum requirements since they do not preclude the use of higher rates that may be appropriate. Supply air to the building and exhaust air from the building shall be regulated to provide a positive pressure within the building with respect to the exterior.

        (I) Cost reduction methods. To reduce utility costs, facility design may utilize energy conserving procedures including recovery devices, variable air volume, load shedding, systems shutdown or reduction of ventilation rates (when specifically permitted) in certain areas when unoccupied. In no case shall patient care be jeopardized.

        (II) Economizer cycle. Mechanical systems shall be arranged to take advantage of outside air conditions by using an economizer cycle when appropriate to reduce heating and cooling systems loads. Innovative design that provides for additional energy conservation while meeting the intent of this section for acceptable patient care may be presented to the department for consideration.

        (III) Outside air intake locations. Outside air intakes shall be located at least 25 feet from exhaust outlets of ventilating systems, combustion equipment stacks, medical-surgical vacuum systems, plumbing vents, or areas which may collect vehicular exhaust or other noxious fumes. (Prevailing winds and proximity to other structures may require more stringent requirements). Plumbing and vacuum vents that terminate five feet above the level of the top of the air intake may be located as close as 10 feet.

        (IV) Low air intake location limit. The bottom of outside air intakes serving central systems shall be located as high as practical but at least six feet above ground level, or if installed above the roof, three feet above the roof level.

        (V) Contaminated air exhaust outlets. Exhaust outlets from areas (kitchen hoods, etc.) that exhaust contaminated air shall be above the roof and be arranged to exhaust upward unless the air has been treated by an appropriate means where sidewall exhaust will be allowed. Ethylene oxide sterilizers shall be terminated above the roof and be arranged to exhaust upward.

        (VI) Directional air flow. Ventilation systems shall be designed and balanced to provide directional flow as shown in Table 3 of §133.169(c) of this title. For reductions and shutdown of ventilation systems when a room is unoccupied, the provisions in Note 4 of Table 3 of §133.169(c) of this title shall be followed.

        (VII) Areas requiring fully ducted systems. Fully ducted supply, return and exhaust air for HVAC systems shall be provided for all critical care areas, sensitive care areas, all patient care areas, all areas requiring a sterile regimen, storage rooms, food preparation areas, and where required for fire safety purposes. Combination systems, utilizing both ducts and plenums for movement of air in these areas shall not be permitted.

        (VIII) Ventilation start-up requirements. Air handling systems shall not be started or operated without the filters installed in place. This includes the 90% and 99.97% efficiency filters where required. Ducts shall be cleaned thoroughly and throughout by a certified air duct cleaning contractor when the air handling systems have been operating without the required filters in place. When ducts are determined to be dirty or dusty, the department will require a written report assuring cleanliness of duct and clean air quality.

        (IX) Humidifier location. When duct humidifiers are located upstream of the final filters, they shall be located at least 15 feet from the filters. Ductwork with duct-mounted humidifiers shall be provided with a means of removing water accumulation. An adjustable high-limit humidistat shall be located downstream of the humidifier to reduce the potential of condensation inside the duct. All duct take-offs should be sufficiently downstream of the humidifier to ensure complete moisture absorption. Reservoir-type water spray or evaporative pan humidifiers shall not be used.

      (ii) Filtration requirements. All central air handling systems serving patient care areas, including nursing unit corridors, shall be equipped with filters having efficiencies equal to, or greater than, those specified in Table 4 of §133.169(d) of this title. Filter efficiencies shall be average efficiencies tested in accordance with American Society of Heating, Refrigerating, and Air-Conditioning Engineers (ASHRAE), Inc., Standard 52.2, 1999 edition, Method of Testing General Ventilation Air-Cleaning Devices for Removal Efficiency by Particle Size. All joints between filter segments, and between filter segments and the enclosing ductwork, shall have gaskets and seals to provide a positive seal against air leakage. Air handlers serving more than one room shall be considered as central air handlers. All documents published by ASHRAE as referenced in this section may be obtained by writing or calling the ASHRAE, Inc. at the following address or telephone number: ASHRAE, Inc., 1791 Tullie Circle, N. E., Atlanta, GA 30329; telephone (404) 636-8400.

        (I) Filtration requirements for air handling units serving single rooms requiring asepsis control. Dedicated air handlers serving only one room where asepsis control is required, such as, but not limited to, operating rooms, delivery rooms, special procedure rooms, and nurseries shall be equipped with filters having efficiencies equal to, or greater than, those specified for patient care areas in Table 4 of §133.169(d) of this title.

        (II) Filtration requirements for air handling units serving other single rooms. Dedicated air handlers serving all other single rooms shall be equipped with nominal filters installed at the return air system.

Cont'd...