      (viii) a distinct marking to identify an estimated bill.

    (C) Where there is good reason for doing so, estimated bills may be submitted, provided that an actual meter reading is taken at least every six months. For the second consecutive month in which the meter reader is unable to gain access to the premises to read the meter on regular meter reading trips, or in months where meters are not read otherwise, the utility must provide the customer with a postcard and request that the customer read the meter and return the card to the utility if the meter is of a type that can be read by the customer without significant inconvenience or special tools or equipment. If such a postcard is not received by the utility in time for billing, the utility may estimate the meter reading and render the bill accordingly.

    (D) Disputed bills.

      (i) In the event of a dispute between the customer and the utility regarding the bill, the utility must forthwith make such investigation as is required by the particular case and report the results thereof to the customer. If the customer wishes to obtain the benefits of clause (ii) of this subparagraph, notification of the dispute must be given to the utility prior to the date the bill becomes delinquent. In the event the dispute is not resolved, the utility shall inform the customer of the complaint procedures of the appropriate regulatory authority.

      (ii) Notwithstanding any other subsection of this section, the customer shall not be required to pay the disputed portion of the bill which exceeds the amount of that customer's average usage for the billing period at current rates until the earlier of the following: resolution of the dispute or the expiration of the 60-day period beginning on the day the disputed bill is issued. For purposes of this section only, the customer's average usage for the billing period shall be the average of the customer's usage for the same billing period during the preceding two years. Where no previous usage history exists, the average usage shall be estimated on the basis of usage levels of similar customers and under similar conditions.

  (7) Meters.

    (A) Meter requirements.

      (i) Use of meter. All gas sold by a utility must be charged for by meter measurements, except where otherwise provided for by applicable law, regulation of the regulatory authority, or tariff.

      (ii) Installation by utility. Unless otherwise authorized by the regulatory authority, each utility must provide and install and will continue to own and maintain all meters necessary for measurement of gas delivered to its customers.

      (iii) Standard type. No utility may furnish, set up, or put in use any meter which is not reliable and of a standard type which meets generally accepted industry standards; provided, however, special meters not necessarily conforming to such standard types may be used for investigation, testing, or experimental purposes.

    (B) Meter records. Each utility must keep the following records:

      (i) Meter equipment records. Each utility must keep a record of all its meters, showing the customer's address and date of the last test.

      (ii) Records of meter tests. All meter tests must be properly referenced to the meter record provided for therein. The record of each test made on request of a customer must show the identifying number and constants of the meter, the standard meter and other measuring devices used, the date and kind of test made, by whom made, the error (or percentage of accuracy) at each load tested, and sufficient data to permit verification of all calculations.

      (iii) Meter readings--meter unit location. In general, each meter must indicate clearly the units of service for which charge is made to the customer.

      (iv) Meter tests on request of customer.

        (I) Each utility must, upon request of a customer, make a test of the accuracy of the meter serving that customer. The utility must inform the customer of the time and place of the test and permit the customer or his authorized representative to be present if the customer so desires. If no such test has been performed within the previous four years for the same customer at the same location, the test is to be performed without charge. If such a test has been performed for the same customer at the same location within the previous four years, the utility is entitled to charge a fee for the test not to exceed $15 or such other fee for the testing of meters as may be set forth in the utility's tariff properly on file with the regulatory authority. The customer must be properly informed of the result of any test on a meter that serves him.

        (II) Notwithstanding subclause (I) of this clause, if the meter is found to be more than nominally defective, to either the customer's or the utility's disadvantage, any fee charged for a meter test must be refunded to the customer. More than nominally defective means a deviation of more than 2.0% from accurate registration.

      (v) Bill adjustments due to meter error.

        (I) If any meter test reveals a meter to be more than nominally defective, the utility must correct previous readings consistent with the inaccuracy found in the meter for the period of either:

          (-a-) the last six months; or

          (-b-) the last test of the meter, whichever is shorter. Any resulting underbillings or overbillings are to be corrected in subsequent bills, unless service is terminated, in which event a monetary adjustment is to be made. This requirement for a correction may be foregone by the utility if the error is to the utility's disadvantage.

        (II) If a meter is found not to register for any period of time, the utility may make a charge for units used but not metered for a period not to exceed three months previous to the time the meter is found not to be registering. The determination of amounts used but not metered is to be based on consumption during other like periods by the same customer at the same location, when available, and on consumption under similar conditions at the same location or of other similarly situated customers, when not available.

  (8) New construction.

    (A) Standards of construction. Each utility is to construct, install, operate, and maintain its plant, structures, equipment, and lines in accordance with the provisions of such codes and standards as are generally accepted by the industry, as modified by rule or regulation of the regulatory authority or otherwise by law, and in such manner to best accommodate the public and to prevent interference with service furnished by other public utilities insofar as practical.

    (B) Line extension and construction charges. Every utility must file its extension policy. The policy must be consistent, nondiscriminatory, and is subject to the approval of the regulatory authority. No contribution in aid of construction may be required of any customer except as provided for in extension policy.

    (C) Response to request for service. Every gas utility must serve each qualified applicant for service within its service area as rapidly as practical. As a general policy, those applications not involving line extensions or new facilities should be filled within seven working days. Those applications for individual residential service requiring line extensions should be filled within 90 days unless unavailability of materials or other causes beyond the control of the utility result in unavoidable delays. In the event that residential service is delayed in excess of 90 days after an applicant has met credit requirements and made satisfactory arrangements for payment of any required construction charges, a report must be made to the regulatory authority listing the name of the applicant, location, and cause for delay. Unless such delays are due to causes which are reasonably beyond the control of the utility, a delay in excess of 90 days may be found to constitute a refusal to serve.


Source Note: The provisions of this §7.45 adopted to be effective June 26, 1977, 2 TexReg 2371; amended to be effective March 30, 1983, 8 TexReg 887; amended to be effective September 25, 1987, 12 TexReg 3040; amended to be effective September 21, 1998, 23 TexReg 9543; amended to be effective November 10, 2003, 28 TexReg 9826; amended to be effective July 12, 2004, 29 TexReg 6635