TITLE 10COMMUNITY DEVELOPMENT
PART 1TEXAS DEPARTMENT OF HOUSING AND COMMUNITY AFFAIRS
CHAPTER 13MULTIFAMILY DIRECT LOAN RULE
RULE §13.11Post-Award Requirements

(a) Direct Loan awardees must satisfactorily complete the Post-Award Requirements identified in this section after the Board approval date.

(b) If a Direct Loan award is declined by the Direct Loan awardee and returned after Board approval, or if the Direct Loan awardee or Affiliates fail to timely enter into the Contract, close the loan, begin and complete construction, or leave a portion of the Direct Loan award unexpended, penalties may apply under 10 TAC §11.9(f) (relating to Competitive HTC Selection Criteria), and/or the Department may prohibit the Applicant and all Affiliates from applying for MFDL funds for a period of two years.

(c) Benchmarks. Extensions to the benchmarks in paragraphs (1) - (8) of this subsection may only be approved by the Executive Director or authorized designee in accordance with §13.12 or §13.13 of this chapter (relating to Pre-Closing and Post-Closing Amendments), as applicable.

  (1) Environmental Clearance. In order to obtain environmental clearance required by the National Environmental Policy Act (NEPA) and other related Federal and state environmental laws (if applicable), Direct Loan Applicants, including those previously awarded HTC, must submit a fully completed environmental review, including any applicable reports to the Department within 90 days of the Application Acceptance Date.

  (2) Contract Execution. After a Development receives environmental clearance (if applicable), the Department will draft a Contract to be emailed to the Direct Loan awardee. Direct Loan awardees must execute and return a Contract to the Department within 30 calendar days after receipt of the Contract.

  (3) Loan Closing and Construction Commencement. Loan closing must occur and construction must begin on or before the dates described in the Contract. If construction has not commenced within 12 months of the Contract Effective Date, the award may be terminated.

  (4) Loan Closing. In preparation for closing any Direct Loan, the Development Owner must submit the items described in subparagraphs (A) - (F) of this paragraph. Providing incomplete documents, or not responding timely to subsequent Department requests for materials needed to facilitate closing, may significantly delay closing. Any request to change the financing structure of the Development, or the ownership structure, will in most cases extend the amount of time it will take for the Department to meet closing timelines, and may move prioritization of the closing below that of other Developments.

    (A) Documentation of the prior closing or concurrent closing with all sources of funds necessary for the long-term financial feasibility of the Development.

    (B) Due diligence items determined by the Department to be prudent and necessary to meet the Department's rules and to secure the interests of the Department, as requested by Staff.

    (C) When Department funds have a first lien position during the construction term, or if the Development is a public work under state law, assurance of completion of the Development in the form of payment and performance bonds in the full amount of the construction contract or equivalent guarantee as allowable under state law in the sole determination of the Department is required. Development Owners utilizing the USDA §515 program for a Development that is not a public work are exempt from this requirement, but must meet the alternative requirements set forth by USDA.

    (D) Documentation required for preparation of closing loan documents includes, but is not limited to:

      (i) Substantially final information necessary for REA staff to reevaluate the transaction prior to loan closing, including but not limited to a substantially final development cost schedule, sources and uses, operating pro forma, annual operating expenses, rent schedule, updated written financial commitments or term sheets, and any additional financing exhibits that have changed since the time of Application;

      (ii) Substantially final Draft Owner/General Contractor agreement and draft Owner/Architect agreement prior to closing with final executed copies required by the day of closing;

      (iii) Survey of the Property that includes a certification to the Department, Development Owner, Title Company, and other lenders;

      (iv) Plans and specifications for review by the Department's inspection staff. Inspection staff will issue a plan review letter that is intended to assist in identifying early concerns associated with the Department's final construction requirements; and

      (v) If layered with Housing Tax Credits, a substantially final draft limited partnership agreement between the General Partner and the tax credit investor entity.

    (E) If required by the fund source, prior to Contract Execution unless an earlier period is described in Chapters 10, 11, or 12 of this title, the Development Owner must provide verification of:

      (i) Environmental clearance from the Department or HUD, as applicable;

      (ii) Site and Neighborhood clearance from the Department;

      (iii) Documentation necessary to show compliance with the Uniform Relocation Assistance and Property Act and any other relocation requirements that may apply;

      (iv) Title Insurance Commitment or Policy showing the Department as Lender, with copies of all Schedule B documents; and

      (v) Any other documentation that is necessary or prudent to meet program requirements or state or federal law in the sole determination of the Department.

    (F) The Direct Loan Contract as executed, which will be drafted by the Department's counsel or its designee for the Department. No changes proposed by the Developer or Developer's counsel will be accepted unless approved by the Department's Legal Division or its designee.

  (6) Loan Documents. The Development Owner is required to execute all loan closing documents required by and in the form and substance acceptable to the Department's Legal Division.

    (A) Loan closing documents include but are not limited to a promissory note, deed of trust, construction loan agreement (if the proceeds of the loan are to be used for construction), LURA, Architect and/or licensed engineer certification of understanding to complete environmental mitigation if such mitigation is identified in HUD's environmental clearance or the Underwriting Report and assignment and security instruments whereby the Developer, the Development Owner, and/or any Affiliates (if applicable) grants the Department their respective right, title, and interest in and to other collateral, including without limitation the Owner/Architect agreement and the Owner/General Contractor agreement, to secure the payment and performance of the Development Owner's obligations under the loan documents. Additional loan terms and conditions may be imposed by the loan closing documents.

    (B) Loan terms and conditions may vary based on the type of Development, Real Estate Analysis Underwriting Report, and the Set-Aside under which the award was made.

  (7) Quarterly Construction Status Reports. The Development Owner is required to submit quarterly Construction Status Reports to the Asset Management Division as described and by the deadlines specified in 10 TAC §10.401(e) of this title (relating to Construction Status Report).

  (8) Mid-Construction Development Inspection Letter. In addition to any other obligations required as the result of any other Department funding sources, the Development Owner must submit a Mid-Construction Development Inspection Request once the Development has met at least 25% construction completion as indicated on the G703 Continuation Sheet or HUD equivalent form. Department inspection staff will issue a Mid-Construction Development Inspection Letter that confirms work is being done in accordance with the applicable codes, the construction contract, and construction documents.

  (9) Construction Completion. Construction must be completed, as reflected by the Development's certificate(s) of occupancy (if new construction and/or reconstruction) and Certificate of Substantial Completion (AIA Form G704) or Form HUD-92485 for instances in which a federally insured HUD loan is being utilized, within the construction term of any superior construction loan(s) or up to 36 months of the actual loan closing date if no superior construction loan(s) exists, unless a shorter timeline is necessitated by the federal funding source.

  (10) Closed Final Development Inspection Letter. The Closed Final Development Inspection Letter must be issued by the Department within 36 months of loan closing. This letter will verify committed amenities have been provided and confirm compliance with all applicable accessibility requirements; this letter may include deficiencies that require resolution. The Closed Final Development Inspection may be conducted concurrently with a NSPIRE inspection. However, any letters associated with a NSPIRE inspection will not satisfy the Closed Final Development Inspection Letter required by this subsection.