by a technical justification as well as any supporting information for the additional time. The conversion factor and alternate compliance period may be periodically reviewed by the executive director to ensure that material is being removed from the facility.

  (2) Maximum volume of combustible material. A facility shall not store processed or unprocessed combustible material in excess of the maximum volume of material indicated in the current notice of intent to operate the facility submitted to the executive director.

  (3) Time limits for processing. All combustible material stored by a facility to produce mulch or compost must be ground so that 100% has a particle size of six inches or less in at least one dimension and 90% has a particle size of six inches or less in all dimensions no later than 90 days after receipt. Material will not be considered processed until it is ground to the specified dimensions. Under certain circumstances, an owner or operator may request executive director approval for additional time to grind combustible materials up to 180 days after receipt of the material.

  (4) Pile size limits. Each pile of combustible material shall have dimensions not to exceed 25 feet in height. Unprocessed combustible material shall not cover an area greater than 50,000 square feet at the facility, with no single pile exceeding 8,000 square feet. A pile of processed combustible material shall not cover an area greater than 25,000 square feet.

  (5) Number of piles. The number of piles of combustible materials at the facility shall not exceed the maximum number specified in the notice of intent to operate the facility submitted to the executive director.

  (6) Fire lanes between piles. There shall be a minimum separation of 40 feet from piles of unprocessed combustible materials and a minimum separation equal to the pile height between piles of processed combustible materials. An all-weather road shall encircle the area used for processing and storage of combustible material. At a minimum, this all-weather roadway shall have minimum 25-foot turning radii; shall be capable of accommodating firefighting vehicles during wet weather; and shall meet applicable local requirements and specifications. The open space between buildings and piles shall be kept open at all times; and be maintained free of combustible material, rubbish, equipment, or other materials. Upon coordination with the local fire marshal, the distance required may be increased, as necessary, to protect human health and safety.

  (7) Buffer zone. The set back distance from all property boundaries to the edge of the areas receiving, processing, or storing material must be at least 50 feet.

  (8) Recharge Zone or Transition Zone. Notwithstanding the applicability requirements of Chapter 213 of this title (relating to Required Edwards Aquifer Protection Plans, Notifications, and Exemptions), facilities located on a recharge or transition zone shall have a water pollution abatement plan consistent with the requirements of §213.5(b) of this title (relating to Required Edwards Aquifer Protection Plans, Notifications, and Exemptions).

  (9) Notice of intent. By the effective date of this subsection for existing facilities or at least 90 days prior to commencing new operations, the owner or operator must file a notice of intent in accordance with §328.5(b) of this title (relating to Reporting and Recordkeeping Requirements) that also includes provisions to demonstrate compliance with this subsection. A revised notice of intent must be filed with the executive director before revising a volume conversion factor or before a facility exceeds the maximum amount of material to be stored as specified in the current notice of intent.

  (10) Recordkeeping. The owner or operator of a facility subject to the requirements of this subsection must maintain all records necessary to demonstrate compliance with this subsection.

  (11) Compliance. Failure to operate and maintain a facility as proposed in the current notice of intent for the facility is a violation of this chapter.

  (12) Effective date. The requirements of this subsection do not become effective until one year after commission adoption of this subsection.


Source Note: The provisions of this 328.4 adopted to be effective September 12, 2002, 27 TexReg 8561; amended to be effective November 4, 2004, 29 TexReg 10120; amended to be effective September 10, 2009, 33 TexReg 8171