T30S112.14(b)

  SO2 Parts Per Million by Volume (ppmv) Maximum
  Two-Hour Average Three-Hour* Average
(1) Primary Copper Smelter for all purposes other than those listed below:   650
(A) Reverberatory Furnace   6,000
(2) Primary Zinc Smelter 1,000  
(3) Primary Lead Smelter    
(A) Sinter Machine Discharge End (provided gases do not pass through Sinter bed) 2,500  
(B) Sinter Handling Equipment Emission Collecting Systems 2,500  
(C) All Other Processes 650  
(4) Other Primary Smelter 2,500  
(5) Secondary Metal Recovery Facility 3,500  
(6) Sulfuric Acid Plant   650

*The three-hour standards will be based on a six-hour average until September 30, 1994.