Figure: 30 TAC §113.2074(a)

Table 3. Initial and Annual Inspection Requirements.

Items to be Inspected Requirements
Burners, pilot assemblies, and pilot sensing devices Inspect for proper operation; clean pilot flame sensor, as necessary.
Combustion air Ensure proper adjustment of primary and secondary chamber combustion air, and adjust as necessary.
Hinges and door latches Inspect and lubricate as necessary.
Dampers, fans, and blowers Inspect for proper operation.
Incinerator door and door gaskets Inspect for proper sealing.
Motors Inspect for proper operation.
Primary chamber refractory lining Inspect lining; clean and repair/replace as necessary.
Incinerator shell Inspect for corrosion and/or hot spots.
Secondary/tertiary chamber and stack Inspect and clean as necessary.
Mechanical loader, including limit switches Inspect for proper operation, if applicable.
Waste bed (grates) visually inspect and repair/seal, as appropriate.
Air pollution control device(s) Inspect device(s) for proper operation, if applicable.
Waste heat boiler systems Inspect to ensure proper operation, if applicable.
Bypass stack components Inspect components.
Thermocouples, sorbent feed systems, and any other monitoring equipment Ensure proper calibration of equipment.
General equipment Generally observe that the equipment is maintained in good operating condition.
Incinerator operation For the burn cycle that follows the inspection, document that the incinerator is operating properly and make any necessary adjustments.