Figure: 30 TAC §113.2079(a)(2)
Table 11. Compliance Extension Requirements.
Analysis of Need | Document the analysis undertaken to support the need for a compliance extension, including an explanation why one year is insufficient. |
Analysis of Off-site Transport Option | Evaluate the option of temporary or permanent transport of the waste offsite to a commercial medical waste treatment and disposal facility. |
Control Plan Must specify measurable and enforceable incremental steps of progress (dates) toward compliance for installation of necessary air pollution control equipment. |
Obtain services of architectural and engineering
firm regarding the air pollution control devices (APCD). Obtain design drawings of APCDs. Contract award for control systems or process modifications, or purchase orders for APCDs. Submit petition for site-specific operating parameters under §113.2075(5), as applicable. Obtain major components of APCDs. Initiate of on-site construction or installation of APCDs or process changes. Complete on-site construction or installation of APCDs or process changes. Initial startup of APCDs. Initial compliance test(s) of APCDs. Final compliance. |