Figure: 30 TAC §113.2079(a)(2)

Table 11. Compliance Extension Requirements.

Analysis of Need • Document the analysis undertaken to support the need for a compliance extension, including an explanation why one year is insufficient.
Analysis of Off-site Transport Option • Evaluate the option of temporary or permanent transport of the waste offsite to a commercial medical waste treatment and disposal facility.
Control Plan

Must specify measurable and enforceable incremental steps of progress (dates) toward compliance for installation of necessary air pollution control equipment.

• Obtain services of architectural and engineering firm regarding the air pollution control devices (APCD).

• Obtain design drawings of APCDs.

• Contract award for control systems or process modifications, or purchase orders for APCDs.

• Submit petition for site-specific operating parameters under §113.2075(5), as applicable.

• Obtain major components of APCDs.

• Initiate of on-site construction or installation of APCDs or process changes.

• Complete on-site construction or installation of APCDs or process changes.

• Initial startup of APCDs.

• Initial compliance test(s) of APCDs.

• Final compliance.