Applicant's Total Housing Development Cost. For Competitive Housing Tax Credit Applications, the Underwriter will adjust an Applicant's cost schedule line item to meet program rules. Underwriter will not make subsequent adjustments to the application to meet feasibility requirements as a result of the initial adjustment required to meet program rules.

  (1) Acquisition Costs.

    (A) Land, Acquisition and Rehabilitation, Reconstruction, and Adaptive Reuse Acquisition.

      (i) For a non-identity of interest acquisition with no building acquisition cost in basis or when the acquisition is not part of the Direct Loan eligible cost and not subject to the appraisal requirements in the Uniform Relocation Assistance and Act of 1970, the underwritten acquisition cost will be the amount(s) reflected in the Site Control document(s) for the Property. At Cost Certification, the acquisition cost used will be the actual amount paid as verified by the settlement statement.

      (ii) For an identity of interest acquisition or when required by the Uniform Relocation Assistance and Acquisition Act of 1970 the underwritten acquisition cost will be the lesser of the amount reflected in the Site Control documents for the property or the appraised value as determined by an appraisal that meets the requirements of §11.304 of this chapter (relating to Appraisal Rules and Guidelines). An appraisal is not required if the land or building are donated to the proposed Development, and no costs of acquisition appear on the Development Cost Schedule. An acquisition will be considered an identity of interest transaction when an Affiliate of the seller is an Affiliate of, or a Related Party to, any Owner at any level of the Development Team or a Related Party lender; and

        (I) is the current owner in whole or in part of the Property as of the first date of the Application Acceptance Period or the Application Acceptance Date for Direct Loans; or

        (II) has or had within the prior 36 months the legal or beneficial ownership of the property or any portion thereof or interest therein regardless of ownership percentage, control or profit participation prior to the first day of the Application Acceptance Period or in the case of a tax-exempt bond or 4% tax credit application the Application Date.

      (iii) For all identity of interest acquisitions, the cost used at cost certification will be limited to the acquisition cost underwritten in the initial Underwriting of the Application.

      (iv) In cases where more land will be acquired (by the Applicant or a Related Party) than will be utilized as the Development Site and the remainder acreage is not accessible for use by tenants or dedicated as permanent and maintained green space, the value ascribed to the proposed Development Site will be prorated based on acreage from the total cost reflected in the Site Control document(s) or the appraisal, if an appraisal is required. An appraisal containing segregated values for the total acreage to be acquired, the acreage for the Development Site and the remainder acreage may be used by the Underwriter in making a proration determination based on relative value. The Underwriter will not utilize a prorated value greater than the total amount in the Site Control document(s).

    (B) USDA Rehabilitation Developments. The underwritten acquisition cost for developments financed by USDA will be the transfer value approved by USDA.

    (C) Eligible Basis on Acquisition of Buildings. Building acquisition cost included in Eligible Basis is limited to the appraised value of the buildings, exclusive of land value, as determined by an appraisal that meets the requirements of §11.304 of this chapter (relating to Appraisal Rules and Guidelines). If the acquisition cost in the Site Control documents is less than the appraised value, Underwriter will utilize the land value from the appraisal and adjust the building acquisition cost accordingly.

  (2) Off-Site Costs. The Underwriter will only consider costs of Off-Site Construction that are well documented and certified to by a Third Party engineer on the required Application forms with supporting documentation.

  (3) Site Work Costs. The Underwriter will only consider costs of Site Work, including site amenities, that are well documented and certified to by a Third Party engineer on the required Application forms with supporting documentation.

  (4) Building Costs.

    (A) New Construction and Reconstruction. The Underwriter will use the Marshall and Swift Residential Cost Handbook, other comparable published Third-Party cost estimating data sources, historical final cost certifications of previous Housing Tax Credit developments and other acceptable cost data available to the Underwriter to estimate Building Cost. Generally, the "Average Quality" multiple, townhouse, or single family costs, as appropriate, from the Marshall and Swift Residential Cost Handbook or other comparable published Third-Party data source, will be used based upon details provided in the Application and particularly building plans and elevations. Costs for multi- level parking structures must be supported by a cost estimate from a Third Party contractor with demonstrated experience in structured parking construction. The Underwriter will consider amenities, specifications and development types not included in the Average Quality standard. The Underwriter may consider a sales tax exemption for nonprofit General Contractors.

    (B) Rehabilitation and Adaptive Reuse.

      (i) The Applicant must provide a scope of work and narrative description of the work to be completed. The narrative should speak to all Off-Site Construction, Site Work, and building components including finishes and equipment, and development amenities. The narrative should be in sufficient detail so that the reader can understand the work and it must generally be arranged consistent with the line- items on the SCR Supplement and must also be consistent with the Development Cost Schedule of the Application.

      (ii) The Underwriter will use cost data provided on the SCR Supplement if adequately described and substantiated in the SCR report as the basis for estimating Total Housing Development Costs.

  (5) Contingency. Total contingency, including any soft cost contingency, will be limited to a maximum of 7% of Building Cost plus Site Work and Off-Site Construction for New Construction and Reconstruction Developments, and 10% of Building Cost plus Site Work and Off-Site Construction for Rehabilitation and Adaptive Reuse Developments. For Housing Tax Credit Developments, the percentage is applied to the sum of the eligible Building Cost, eligible Site Work costs and eligible Off-Site Construction costs in calculating the eligible contingency cost.

  (6) General Contractor Fee. General Contractor fees include general requirements, contractor overhead, and contractor profit. General requirements include, but are not limited to, on-site supervision or construction management, off-site supervision and overhead, jobsite security, equipment rental, storage, temporary utilities, and other indirect costs. General Contractor fees are limited to a total of 14% on Developments with Hard Costs of $3 million or greater, the lesser of $420,000 or 16% on Developments with Hard Costs less than $3 million and greater than $2 million, and the lesser of $320,000 or 18% on Developments with Hard Costs at $2 million or less. Any contractor fees to Affiliates or Related Party subcontractors regardless of the percentage of the contract sum in the construction contract (s) will be treated collectively with the General Contractor Fee limitations. Any General Contractor fees above this limit will be excluded from Total Housing Development Costs. For Housing Tax Credit Developments, the percentages are applied to the sum of the Eligible Hard Costs in calculating the eligible contractor fees. For Developments also receiving financing from USDA, the combination of builder's general requirements, builder's overhead, and builder's profit should not exceed the lower of TDHCA or USDA requirements. Additional fees for ineligible costs will be limited to the same percentage of ineligible Hard Costs but will not be included in Eligible Basis.

  (7) Developer Fee.

    (A) For Housing Tax Credit Developments, the Developer Fee included in Eligible Basis cannot exceed 15% of the project's eligible costs, less Developer Fee, for Developments proposing 50 Units or more and 20% of the project's eligible costs, less Developer Fee, for Developments proposing 49 Units or less. If the Development is an additional phase, proposed by any Principal of the existing tax credit Development, the Developer Fee may not exceed 15%, regardless of the number of Units.

    (B) For Housing Tax Credit Developments, any additional Developer Fee claimed for ineligible costs will be limited to the same percentage but applied only to ineligible Hard Costs. Any Developer Fee above this limit will be excluded from Total Housing Development Costs. All fees to Affiliates or Related Parties for work or guarantees determined by the Underwriter to be typically completed or provided by the Developer or Principal(s) of the Developer will be considered part of Developer Fee. All costs for general and administrative expenses for the Cont'd...