(a) Class I units. If you plan to achieve compliance more than 1 year following the effective date of state plan approval and a permit modification is not required, or more than 1 year following the date of issuance of a revised construction or operating permit if a permit modification is required, you must meet five increments of progress: (1) Submit a final control plan. (2) Submit a notification of retrofit contract award. (3) Initiate onsite construction. (4) Complete onsite construction. (5) Achieve final compliance. (b) Class II units. If you plan to achieve compliance more than 1 year following the effective date of state plan approval and a permit modification is not required, or more than 1 year following the date of issuance of a revised construction or operating permit if a permit modification is required, you must meet two increments of progress: (1) Submit a final control plan. (2) Achieve final compliance. |