(a) The owner or operator of utility boilers listed
in §117.1300 of this title (relating to Applicability) at a major
source of nitrogen oxides (NOX ) shall
submit to the Office of Compliance and Enforcement, the appropriate
regional office, and the Office of Air, a final control report to
show compliance with the requirements of §117.1310 of this title
(relating to Emission Specifications for Eight-Hour Attainment Demonstration).
The report must include:
(1) the methods of NOX control
for each utility boiler;
(2) the emissions measured by testing required in §117.1335
of this title (relating to Initial Demonstration of Compliance);
(3) the submittal date, and whether sent to the central
or the regional office (or both), of any compliance stack test report
or monitor certification report required by §117.1335 of this
title that is not being submitted concurrently with the final compliance
report; and
(4) the specific rule citation for any utility boiler
with a claimed exemption from the emission specification of §117.1310
of this title.
(b) The report must be submitted by the applicable
date specified for final control plans in §117.9130 of this title
(relating to Compliance Schedule Dallas-Fort Worth Eight-Hour Ozone
Nonattainment Area Utility Electric Generation Sources).
|