(a) The commission, by written order, will select projects
for funding under the TAP based on:
(1) recommendations from the director of the division
responsible for administering the TAP;
(2) the potential benefit to the state of the project;
and
(3) whether the project enhances the surface transportation
system.
(b) The commission is not bound by project selection
recommendations provided by the department.
(c) The department will notify the project sponsor
of the selection.
(d) The commission will specify a fixed amount of TAP
funds for each project. Project costs in excess of this amount are
the responsibility of the project sponsor. The project sponsor may
seek additional funds through the TAP in subsequent program calls.
(e) A project that is not selected must be resubmitted
to receive consideration during subsequent program calls.
|