(a) An owner shall perform a job safety analysis to
identify potentially hazardous situations for a new or altered wastewater
treatment unit or collection system unit before construction begins.
(b) For those identified potentially hazardous tasks,
a list must be prepared for each task that identifies the necessary:
(1) tools, equipment, and supplies;
(2) fixed and portable lifting equipment;
(3) fixed and portable monitoring equipment;
(4) personal protective equipment and clothing;
(5) warning signs and guards; and
(6) first-aid supplies.
(c) The tools at a wastewater treatment facility must
be sufficient to:
(1) allow workers to safely and properly operate equipment;
(2) perform required preventive maintenance, in compliance
with the manufacturers' minimum requirements;
(3) make repairs; and
(4) maintain processes, pumps, motors, blowers, compressors,
laboratory instrumentation, and other equipment.
|