RULE §24.25Form and Filing of Tariffs

the need for the temporary rate. A request for a temporary water rate provision for mandatory water use reduction under this paragraph is not considered a statement of intent to increase rates subject to the 12-month limitation in §24.29 of this title (relating to Time Between Filings).

    (B) The utility must establish that the projected revenues that will be generated by the temporary water rate provision are required by the utility to pay reasonable and necessary expenses that will be incurred by the utility during the time mandatory water use reductions are in effect.

  (4) A utility may request a temporary water rate provision for mandatory water use reduction using the formula in paragraph (3) of this subsection or any other method acceptable to the regulatory authority to recover up to 100% of the revenues that would otherwise have been lost due to mandatory water use reductions.

    (A) If the utility requests authorization to recover more than 50% of lost revenues, the utility must submit financial data to support its existing rates as well as the temporary water rate provision for mandatory water use reduction even if no other rates are proposed to be changed. The utility's existing rates are subject to review in addition to the temporary water rate provision for mandatory water use reduction.

    (B) The utility must establish that the projected revenues that will be generated by the temporary water rate provision for mandatory water use reduction are required by the utility to pay reasonable and necessary expenses that will be incurred by the utility during the time mandatory water use reductions are in effect; that the rate of return granted by the regulatory authority in the utility's last rate case does not adequately compensate the utility for the foreseeable risk that mandatory water use reductions will be ordered; and that revenues generated by existing rates do not exceed reasonable cost of service.

  (5) The utility may place the temporary water rate provision into effect only after:

    (A) it has been approved by the regulatory authority and included in the utility's approved tariff in a prior rate proceeding;

    (B) there is an action by a court, government agency, or other authority requiring mandatory water use reduction measures that affect the utility's customers' use of utility services; and

    (C) issuing notice as required by paragraph (7) of this subsection.

  (6) The utility may readjust its temporary water rate provision to respond to modifications or changes to the original required water use reductions by reissuing notice as required by paragraph (7) of this subsection. If the commission is the regulatory authority, only the commission or the utility may request a hearing on the proposed implementation.

  (7) A utility implementing a temporary water rate for mandatory water use reduction must take the following actions prior to the beginning of the billing period in which the temporary water rate provision takes effect:

    (A) submit a written notice, including a copy of the notice received from the court, government agency, or other authority requiring the reduction in water use, to the regulatory authority; and

    (B) e-mail, if the customer has agreed to receive communications electronically, or mail notice to the utility's customers. Notice may be in the form of a billing insert and must contain the effective date of the implementation and the new rate the customers will pay after the temporary water rate provision is implemented. If the commission is the regulatory authority, the notice must include the following language: "This rate change is being implemented in accordance with the temporary water rate provision approved by the Public Utility Commission of Texas to recognize the loss of revenues due to mandatory water use reduction ordered by (name of entity issuing order). The new rates will be effective on (date) and will remain in effect until the mandatory water use reductions are lifted or expired. The purpose of the rate is to ensure the financial integrity of the utility. The utility will recover through the rate (the percentage authorized by the temporary rate) % of the revenues the utility would otherwise have lost due to mandatory water use reduction by increasing the volume charge from ($ per 1,000 gallons to $ per 1,000 gallons)."

  (8) A utility must stop charging a temporary water rate provision as soon as is practicable after the order that required mandatory water use reduction is ended, but in no case later than the end of the billing period that was in effect when the order was ended. The utility must notify its customers of the date that the temporary water rate provision ends and that its rates will return to the level authorized before the temporary water rate provision was implemented. The notice provided to customers regarding the end of the temporary water rate provision must be filed with the commission.

  (9) If the regulatory authority initiates an inquiry into the appropriateness or the continuation of a temporary water rate provision, it may establish the effective date of its decision on or after the date the inquiry is filed.

(k) Multiple system consolidation. Except as otherwise provided in subsection (m) of this section, a utility may consolidate its tariff and rate design for more than one system if:

  (1) the systems included in the tariff are substantially similar in terms of facilities, quality of service, and cost of service; and

  (2) the tariff provides for rates that promote water conservation for single-family residences and landscape irrigation.

(l) Regional rates. The regulatory authority, where practicable, will consolidate the rates by region for applications submitted by a Class A, B, or C utility, or a Class D utility filing under TWC §13.1872(c)(2), with a consolidated tariff and rate design for more than one system.

(m) Exemption. Subsection (k) of this section does not apply to a utility that provided service in only 24 counties on January 1, 2003.

(n) Energy cost adjustment clause.

  (1) A utility that purchases energy (electricity or natural gas) that is necessary for the provision of retail water or sewer service may request the inclusion of an energy cost adjustment clause in its tariff to allow the utility to adjust its rates to reflect increases and decreases in documented energy costs.

  (2) A utility that requests the inclusion of an energy cost adjustment clause in its tariff must file a request with the commission. The utility must also give notice of the proposed energy cost adjustment clause by mail, either separately or accompanying customer billings, by e-mail, or by hand delivery to all affected utility customers at least 60 days prior to the proposed effective date. Proof of notice in the form of an affidavit stating that proper notice was delivered to affected customers and stating the date of such delivery must be filed with the commission by the utility as part of the request. Notice must be provided on a form prescribed by the commission and must contain the following information:

    (A) the utility name and address, a description of how the increase or decrease in energy costs will be calculated, the effective date of the proposed change, and the classes of utility customers affected. The effective date of the proposed energy cost adjustment clause must be the first day of a billing period, which should correspond to the day of the month when meters are typically read, and the clause may not apply to service received before the effective date of the clause;

    (B) information on how to submit comments regarding the energy cost adjustment clause, the address of the commission, and the time frame for comments; and

    (C) any other information that is required by the commission.

  (3) The commission's review of the utility's request is not subject to a contested case hearing. However, the commission will hold a public meeting if requested by a member of the legislature who represents an area served by the utility or if the commission determines that there is substantial public interest in the matter.

  (4) Once an energy cost adjustment clause has been approved, documented changes in energy costs must be passed through to the utility's customers within a reasonable time. The pass-through, whether an increase or decrease, must be implemented on at least an annual basis, unless the commission determines otherwise. Before making a change to the energy cost adjustment clause, notice must be provided as required by paragraph (5) of this subsection. Copies of notices to customers must be filed with the commission.

  (5) Before a utility implements a change in its energy cost adjustment clause as required by paragraph (4) of this subsection, the utility must take the following actions prior to the beginning of the billing period in which the implementation takes effect: