TITLE 16ECONOMIC REGULATION
PART 2PUBLIC UTILITY COMMISSION OF TEXAS
CHAPTER 25SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS
SUBCHAPTER SWHOLESALE MARKETS
RULE §25.511Texas Energy Fund Completion Bonus Grant Program

      (iv) the name of each generation resource in the electric generating facility and the name of the electric generating facility on ERCOT's market participant list.

    (I) a statement describing when each generation resource in the electric generating facility met the planning model requirements necessary to be included in an ERCOT capacity, demand, and reserves report with an identification of the first appearance of the electric generating facility, or any generation resource in the electric generating facility, in an ERCOT capacity, demand, and reserves report;

    (J) a statement of whether the applicant applied for a loan under §25.510 of this title (relating to Texas Energy Fund In-ERCOT Generation Loan Program) and the commission's determination on the loan application, if known;

    (K) if applicable, a statement asserting that extenuating circumstances support the extension of any deadline described in subsection (e)(2) of this section, including the facts surrounding those extenuating circumstances;

    (L) documentation that the applicant has registered or will register with the commission as a power generation company, unless the applicant is an MOU, electric cooperative, or river authority;

    (M) documentation that the applicant has registered or will register its generation resources according to ERCOT's registration requirements; and

    (N) a narrative explanation of the applicant's preparations for compliance with §25.55 of this title (relating to Weather Emergency Preparedness).

  (2) The commission will evaluate the information provided in an application to determine whether an applicant is eligible to receive a completion bonus grant award. Determination of eligibility to receive a completion bonus grant award does not entitle an applicant to a grant payment.

    (A) The commission will issue a notice of eligibility for an applicant it determines is eligible to receive a completion bonus grant award. The notice of eligibility will state the completion bonus grant award amount based on the actual or projected capacity of each generation resource in the electric generating facility and its actual or projected interconnection date. The award amount is calculated for each generation resource, and these amounts are added together, if applicable, to reach a total award amount for the electric generating facility. For a project that has not reached its interconnection date at the time the application is submitted, the applicant must subsequently submit to the TEF administrator documentation demonstrating that the interconnection date satisfies the applicable deadline in subsection (e)(2) of this section and demonstrate adherence to the criteria described in subsection (c) of this section. If the actual nameplate capacity or interconnection date differs from estimates, the commission may revise the eligible applicant's completion bonus grant award amount to reflect actual information and amend the notice of eligibility accordingly.

    (B) For the ten successive test periods following a qualifying electric generating facility's interconnection date, an eligible applicant is authorized to receive an annual completion bonus grant payment for each test period in which its generation resource or resources meet the performance standard established in this section.

    (C) An eligible applicant must enter into a grant agreement in the form and manner specified by the commission whereby the eligible applicant commits to adhere to the requirements described in subsection (c) of this section for the duration of any test period for which it may receive a completion bonus grant payment. Failure to enter into a grant agreement or breach of the executed grant agreement will be grounds for the commission to determine that an applicant is ineligible to obtain any future completion bonus grant payment.

  (3) Information submitted to the commission in a completion bonus grant application is confidential and not subject to disclosure under Chapter 552 of the Texas Government Code.

  (4) An applicant must separately file a statement indicating that an application for a completion bonus grant award has been presented to the commission for review with the date of application submission.

(e) Completion bonus grant award amount.

  (1) The amount of a completion bonus grant award is based on program funding availability, and either;

    (A) the combined capacity of each new generation resource and interconnection date of the new electric generating facility; or

    (B) the combined capacity of each new generation resource and interconnection date of the last new generation resource added to an existing electric generating facility.

  (2) Unless the commission determines that extenuating circumstances justify extension of the deadlines under this subsection, the commission may approve a completion bonus grant award for an applicant considered eligible to receive a completion bonus grant award in an amount not to exceed:

    (A) $120,000 per MW of applicable capacity that is interconnected to the ERCOT region before June 1, 2026; or

    (B) $80,000 per MW of applicable capacity that is interconnected to the ERCOT region on or after June 1, 2026, and before June 1, 2029.

  (3) The applicable capacity for use in paragraph (1)(A) and (1)(B) of this subsection is:

    (A) the combined nameplate capacity of all new generation resources, if the newly constructed electric generating facility provides all capacity exclusively to the ERCOT power region;

    (B) the increase in nameplate capacity attributable to the addition of one or more new generation resources at an existing electric generating facility; or

    (C) the net nameplate capacity that exclusively serves the ERCOT region, as determined by the maximum non-coincident peak demand of the industrial load or PUN, if the electric generating facility serves an industrial load or PUN.

(f) Grant payment process.

  (1) For each test period, the TEF administrator will disburse a grant payment to an applicant eligible to receive a completion bonus grant award. A grant payment is one-tenth of an applicant's total completion bonus grant award, subject to the performance standards and discount methodology prescribed under subsections (g) and (h) of this section.

  (2) No later than 45 days following the end of each test period, ERCOT must determine and provide to the TEF administrator the assessed hours, the median and optimal performance levels of the generation resources in the reference group, the PRF and ARF for each generation resource in an electric generating facility under this section, and the amount of payment each eligible applicant is entitled to for that test period, based on the performance of each of its generation resources. The TEF administrator will provide each eligible applicant the assessed hours, the median and optimal performance levels, the eligible applicant's PRF and ARF, and the eligible applicant's calculated completion bonus grant payment amount.

  (3) ERCOT's determination of a generation resource's PRF and ARF and the calculation of the applicant's completion bonus award payment following a test period are subject to review under Section 20 of the ERCOT protocols (alternative dispute resolution procedure) as modified by this subsection. To seek review of ERCOT's determination of PRF, ARF, or payment amount, an eligible applicant must submit a written request for an alternative dispute resolution proceeding to ERCOT no later than 30 days after the date the TEF administrator provides PRF and ARF determinations and payment calculations to the eligible applicant for the test period. The eligible applicant must simultaneously notify the TEF administrator in writing in the manner prescribed by the commission that it has invoked review of ERCOT's determination of PRF or ARF or payment calculations. An eligible applicant may appeal the outcome of the ERCOT review in accordance with §22.251(d) of this title (relating to Review of Electric Reliability Council of Texas (ERCOT) Conduct). The only parties to an appeal of the ERCOT review are the eligible applicant, ERCOT, and commission staff.

  (4) Thirty-five days after the TEF administrator provides the PRF, ARF, and completion bonus grant payment amount to each eligible applicant, the TEF administrator will instruct the Texas Treasury Safekeeping Trust Company to disburse the grant payment to the eligible applicant and notify the eligible applicant of the disbursement, unless the eligible applicant requests review of the determination of PRF or ARF under paragraph (3) of this subsection. Upon resolution of a requested review, the TEF administrator will instruct the Texas Treasury Safekeeping Trust Company to disburse the grant payment, if appropriate.

Cont'd...