RULE §25.55Weather Emergency Preparedness

      (i) Identifies each transmission substation or switchyard maintained by the TSP for which the declaration is being submitted;

      (ii) Summarizes all activities engaged in by the TSP to complete the requirements of paragraph (1) of this subsection for the upcoming winter season,

      (iii) Provides the minimum ambient temperature at which each transmission facility has experienced sustained operations, as measured at the substation or switchyard or the weather station nearest to the substation or switchyard;

      (iv) Includes any additional information required by the ERCOT protocols in effect as of October 1 of the year in which the declaration is submitted; and

      (v) Includes a notarized attestation sworn to by the TSP's highest-ranking representative, official, or officer with binding authority over the TSP, attesting to the completion of all activities described in paragraph (1) of this subsection, except activities required to be completed after December 1, and to the accuracy and veracity of the information described in subparagraph (A) of this paragraph.

    (B) No earlier than May 1 and no later than June 1 of each year, a TSP must submit a declaration of summer weather preparedness for the upcoming summer season that at a minimum:

      (i) Identifies each transmission substation or switchyard maintained by the TSP for which the declaration is being submitted;

      (ii) Summarizes all activities engaged in by the TSP to complete the requirements of paragraph (2) of this subsection;

      (iii) Provides maximum ambient temperature at which each transmission facility has experienced sustained operations, as measured at the substation or switchyard or the weather station nearest to the substation or switchyard;

      (iv) Includes any additional information required by the ERCOT protocols in effect as of April 1 of the year in which the declaration is submitted; and

      (v) Includes a notarized attestation sworn to by the TSP's highest-ranking representative, official, or officer with binding authority over the TSP attesting to the completion of all activities described in paragraph (2) of this subsection, except activities required to be completed after June 1, and to the accuracy and veracity of the information described in subparagraph (B) of this paragraph.

  (4) No later than December 20 of each year, ERCOT must file with the commission a compliance report that addresses whether each TSP has submitted the declaration of winter weather preparedness required by paragraph (3)(A) of this subsection for each transmission substation or switchyard maintained by the TSP.

  (5) No later than June 20 of each year, ERCOT must file with the commission a compliance report that addresses whether each TSP has submitted the declaration of summer weather preparedness required by paragraph (3)(B) of this subsection for each transmission substation or switchyard maintained by the TSP.

  (6) ERCOT will treat declarations of preparedness and associated information submitted by a TSP as Protected Information as defined by the ERCOT protocols.

(g) ERCOT inspections of transmission facilities.

  (1) ERCOT must conduct inspections of transmission facilities and may prioritize inspections based on factors such as the length of time since the transmission facility was last inspected; whether a transmission facility is critical for electric grid reliability; has experienced a forced outage or other failure related to weather emergency conditions; or has other vulnerabilities related to weather emergency conditions. ERCOT must determine, in consultation with commission staff, the number, extent, and content of inspections, as well as develop a risk-based methodology for selecting at least ten percent of substations or switchyards providing transmission service to be inspected at least once every three years. ERCOT must develop, in consultation with commission staff, a winter weather inspection checklist and a summer weather inspection checklist for use during facility inspections. Inspections may be conducted by ERCOT's employees or contractors.

    (A) ERCOT must provide each TSP at least 72 hours' written notice of an inspection unless otherwise agreed by the TSP and ERCOT. The written notice must identify each ERCOT employee, commission staff member, or designated contractor participating in the inspection. Within 24 hours of receiving notice of inspection, a TSP must provide ERCOT, commission staff, and designated contractors all TSP requirements for facility access. Upon provision of the required written notice, a TSP must grant access to its facility to ERCOT and commission staff, including an employee of a contractor designated by ERCOT or the commission to conduct, oversee, or observe the inspection.

    (B) During the inspection, a TSP must provide ERCOT, commission staff, and designated contractors access to any part of the facility upon request. ERCOT, commission staff, and designated contractors must comply with all applicable safety and security regulations, including those maintained by the TSP, during the inspection. A TSP must provide access to inspection, maintenance, and other records associated with weather preparation measures, and must make the TSP's staff available to answer questions. A TSP may escort ERCOT, commission staff, and designated contractors at all times during an inspection. During the inspection, ERCOT, commission staff, and designated contractors may take photographs and video recordings of any part of the facility except control rooms and may conduct interviews of facility personnel designated by the TSP. Documents, photographs, and video recordings collected or generated by ERCOT, commission staff, or designated contractors during or related to the inspection will be treated as confidential information under applicable state or federal laws and regulations.

  (2) ERCOT inspection report.

    (A) ERCOT must provide a written report on its inspection of a transmission system or facility to the TSP. The written inspection report must address whether the TSP has complied with the requirements in subsection(f)(1) or (2) of this section.

    (B) If the TSP has not complied with a requirement in subsection (f)(1) or (2) of this section, ERCOT must provide the TSP a reasonable period to cure the identified deficiencies.

      (i) The cure period determined by ERCOT must consider what weather emergency preparation measures the TSP may be reasonably expected to have taken before ERCOT's inspection, the reliability risk of the TSP's noncompliance, and the complexity of the measures needed to cure the deficiency.

      (ii) The TSP may request ERCOT provide a longer period to cure the identified deficiencies. The request must be accompanied by documentation that supports the request.

      (iii) ERCOT, in consultation with commission staff, will determine the revised cure period after considering a request for a longer period to cure the identified deficiencies.

    (C) ERCOT must report to commission staff any TSP that does not remedy the deficiencies identified under subparagraph (A) of this paragraph within the cure period determined by ERCOT under subparagraph (B) of this paragraph.

    (D) A TSP reported by ERCOT to commission staff under subparagraph (C) of this paragraph will be subject to enforcement investigation under §22.246 of this title. A violation of this section is a Class A violation under §25.8(b)(3)(A) of this title and may be subject to a penalty not to exceed $1,000,000 per violation per day.

(h) Weather-related failures by a TSP to provide service. ERCOT must notify a TSP and commission staff of the TSP's repeated or major-weather related forced interruption of service. Upon notification from ERCOT, the TSP must contract with a qualified professional engineer to assess its weather emergency preparation measures, plans, procedures, and operations. The qualified professional engineer must not be an employee of the TSP or its affiliate. The qualified professional engineer must not have participated in previous assessments for this facility for at least five years, unless the TSP provides documentation that no other qualified professional engineers are reasonably available for engagement. The qualified professional engineer must conduct a root cause analysis of the failure and develop a corrective action plan to address any weather-related causes of the failure. The TSP must submit the qualified professional engineer's assessment to the commission and ERCOT within 15 calendar days of receiving the assessment. A TSP to which this subsection applies may be subject to additional inspections by ERCOT. ERCOT must refer to commission staff for investigation any TSP that violates this subsection.

(i) ERCOT historical weather study. ERCOT must study historical weather data across each weather zone classified in the ERCOT protocols. ERCOT must file with the commission a report summarizing the results of the study at least once every five years, beginning no later than November 1, 2026.

  (1) At a minimum, ERCOT must calculate the 90th, 95th, and 99th percentiles of:

    (A) the daily minimum temperature in each weather zone;

    (B) the daily maximum temperature in each weather zone;

    (C) the maximum sustained wind speed in each weather zone;

    (D) the minimum average 72-hour temperature in each weather zone;

    (E) the maximum average 72-hour temperature in each weather zone; and

    (F) the minimum average wind chill in each weather zone.

  (2) ERCOT may add additional parameters to the historical weather study.

  (3) ERCOT must take into consideration weather predictions produced by the office of the state climatologist when preparing the historical weather study.


Source Note: The provisions of this §25.55 adopted to be effective October 20, 2022, 47 TexReg 6826