(a) Each rail transit agency shall develop a corrective
action plan for:
(1) results from investigations in which identified
causal and contributing factors are determined by the rail transit
agency or the department to require corrective actions; and
(2) findings from safety reviews performed by the department
that require corrective action.
(b) Each corrective action plan must identify the action
to be taken by the rail transit agency, an implementation schedule,
and the individual or department responsible for implementation of
the plan.
(c) The department will review the corrective action
plan within 30 days after the date of receipt. If a plan is not approved,
the department will work with the rail transit agency to develop appropriate
corrective action plans.
(d) The rail transit agency shall provide the department
with verification that corrective actions have been implemented, as
described in the corrective action plan, or that proposed alternate
actions will be implemented, subject to department review and approval.
(e) If the rail transit agency disputes the department's
decision related to a corrective action plan, the rail transit agency
shall submit an application for administrative review under §7.93
of this subchapter (relating to Administrative Review) not later than
30 days after the date of receipt of the written decision.
(f) Failure to complete a corrective action plan is
a violation under this subchapter.
|