(a) In addition to other contract provisions, each
highway improvement contract must provide notice to the contractor
of the evaluation of contract performance under §9.23 of this
subchapter (relating to Evaluation and monitoring of contract performance)
and the range of contract remedies applicable for substandard performance
under the contract, including:
(1) the possible establishment of a project recovery
plan or corrective action plan under §9.23 of this subchapter
to correct significant deficiencies in contract performance;
(2) liquidated damages applicable to the contract under §9.22
of this subchapter (relating to Liquidated Damages);
(3) reduction in the contractor's bidding capacity
under §9.24 of this subchapter;
(4) the prohibition or suspension of bidding on new
projects under §9.24 of this subchapter; and
(5) prohibition from participating in an awarded contract
under §9.24 of this subchapter.
(b) In addition to other contract provisions, each
materials contract must provide notice to the contractor of the range
of contract remedies applicable for substandard performance under
the contract, including applicable actions that may be taken under §9.24
of this subchapter.
|