<<Prev Rule

Texas Administrative Code

Next Rule>>
TITLE 16ECONOMIC REGULATION
PART 1RAILROAD COMMISSION OF TEXAS
CHAPTER 8PIPELINE SAFETY REGULATIONS
SUBCHAPTER CREQUIREMENTS FOR GAS PIPELINES ONLY
RULE §8.209Distribution Facilities Replacements

(a) This section applies to each operator of a gas distribution system that is subject to the requirements of 49 CFR Part 192. This section prescribes the minimum requirements by which all operators will develop and implement a risk-based program for the removal or replacement of distribution facilities, including steel service lines, in such gas distribution systems. The risk-based program will work in conjunction with the Distribution Integrity Management Program (DIMP) using scheduled replacements to manage identified risks associated with the integrity of distribution facilities.

(b) Each operator must make joints on below-ground piping that meets the following requirements:

  (1) Joints on steel pipe must be welded or designed and installed to resist longitudinal pullout or thrust forces per 49 CFR §192.273.

  (2) Joints on plastic pipe must be fused or designed and installed to resist longitudinal pullout or thrust forces per ASTM D2513-Category 1.

(c) Each operator must establish written procedures for implementing the requirements of this section. Each operator must develop a risk-based program to determine the relative risks and their associated consequences within each pipeline system or segment. Each operator that determines that steel service lines are the greatest risk must conduct the steel service line leak repair analysis set forth in subsection (d) of this section and use the prescriptive model in subsection (f) of this section for the replacement of those steel service lines.

(d) In developing its risk-based program, each operator must develop a risk analysis using data collected under its DIMP and the data submitted on the PS-95 to determine the risks associated with each of the operator's distribution systems and establish its own risk ranking for pipeline segments and facilities to determine a prioritized schedule for service line or facility replacement. The operator must support the analysis with data, collected to validate system integrity, that allow for the identification of segments or facilities within the system that have the highest relative risk ranking or consequence in the event of a failure. The operator must identify in its risk-based program the distribution piping, by segment, that poses the greatest risk to the operation of the system. In addition, each operator that determines that steel service lines are the greatest risk must conduct a steel service line leak repair analysis to determine the leak repair rate for steel service lines. The leak repair rate for below-ground steel service lines is determined by dividing the annualized number of below-ground leaks repaired on steel service lines (excluding third-party leaks and leaks on steel service lines removed or replaced under this section) by the total number of steel service lines as reported on PHMSA Form F 7100.1-1, the Gas Distribution System Annual Report. Each operator that determines that steel service lines are the greatest risk must conduct the steel service line leak repair analysis using the most recent three calendar years of data reported to the Commission on Form PS-95.

(e) Each operator must create a risk model that will identify by segment those lines that pose the highest risk ranking or consequence of failure. The determination of risk is based on the degree of hazard associated with the risk factors assigned to the pipeline segments or facilities within each of the operator's distribution systems. The priority of service line or facility replacement is determined by classifying each pipeline segment or facility based on its degree of hazard associated with each risk factor. Each operator must establish its own risk ranking for pipeline segments or facilities to determine the priority for necessary service line or facility replacements. Each operator should include the following factors in developing its risk analysis:

  (1) pipe location, including proximity to buildings or other structures and the type and use of the buildings and proximity to areas of concentrations of people;

  (2) composition and nature of the piping system, including the age of the pipe, materials, type of facilities, operating pressures, leak history records, prior leak grade repairs, and other studies;

  (3) corrosion history of the pipeline, including known areas of significant corrosion or areas where corrosive environments are known to exist, cased crossings of roads, highways, railroads, or other similar locations where there is susceptibility to unique corrosive conditions;

  (4) environmental factors that affect gas migration, including conditions that could increase the potential for leakage or cause leaking gas to migrate to an area where it could create a hazard, such as extreme weather conditions or events (significant amounts or extended periods of rainfall, extended periods of drought, unusual or prolonged freezing weather, hurricanes, etc.); particular soil conditions; unstable soil; or areas subject to earth movement, subsidence, or extensive growth of tree roots around pipeline facilities that can exert substantial longitudinal force on the pipe and nearby joints; and

  (5) any other condition known to the operator that has significant potential to initiate a leak or to permit leaking gas to migrate to an area where it could result in a hazard, including construction activity near the pipeline, wall-to-wall pavement, trenchless excavation activities (e.g., boring), blasting, large earth-moving equipment, heavy traffic, increase in operating pressure, and other similar activities or conditions.

(f) This subsection applies to operators that determine under subsection (c) of this section that steel service lines are the greatest risk. Based on the results of the steel service line leak repair analysis under subsection (d) of this section, each operator must categorize each segment and complete the removal and replacement of steel service lines by segment according to the risk ranking established pursuant to subsection (e) of this section as follows:

  (1) a segment with an annualized steel service line leak rate of 5% or greater but less than 7.5% is a Priority 1 segment and an operator must remove or replace no less than 10% of the original inventory per year; and

  (2) a segment with an annualized steel service line leak rate of less than 5% is a Priority 2 segment. An operator is not required to remove or replace any Priority 2 segments; however, upon discovery of a leak on a Priority 2 segment, the operator must remove or replace rather than repair those lines except as outlined in subsection (g) of this section.

(g) For those steel service lines that must remain in service because of specific operational conditions or requirements, each operator must determine if an integrity risk exists on the segment, and if so, must replace the segment with steel as part of the integrity management plan.

(h) All replacement programs require a minimum annual replacement of 8% of the pipeline segments or facilities posing the greatest risk in the system and identified for replacement pursuant to this section. Each operator with steel service lines subject to subsection (f) of this section must establish a schedule for the replacement of steel service lines or other distribution facilities according to the risk ranking established as part of the operator's risk-based program and must submit the schedule to the Division for review and approval or amendment under subsection (c) of this section.

(i) In conjunction with the filing of the pipeline safety and regulatory program fee pursuant to §8.201 of this title (relating to Pipeline Safety and Regulatory Program Fees) and no later than March 15 of each year, each operator must file with the Division:

  (1) by System ID, a list of the steel service line or other distribution facilities replaced during the prior calendar year; and

  (2) the operator's proposed work plan for removal or replacement for the current calendar year, the implementation of which is subject to review and amendment by the Division. Each operator must notify the Division of any revisions to the proposed work plan and, if requested, provide justification for such revision. Within 45 days after receipt of an operator's proposed revisions to its risk-based plan and work plan, the Division will notify the operator either of the acceptance of the risk-based program and work plan or of the necessary modifications to the risk-based program and work plan.

(j) Each operator of a gas distribution system that is subject to the requirements of §7.310 of this title (relating to System of Accounts) may use the provisions of this subsection to account for the investment and expense incurred by the operator to comply with the requirements of this section.

  (1) The operator may:

    (A) establish one or more designated regulatory asset accounts in which to record any expenses incurred by the operator in connection with acquisition, installation, or operation (including related depreciation) of facilities that are subject to the requirements of this section;

Cont'd...

Next Page

Link to Texas Secretary of State Home Page | link to Texas Register home page | link to Texas Administrative Code home page | link to Open Meetings home page