By the compliance date in §112.108 of this title (relating
to Compliance Schedule), the owner or operator shall comply with the
following:
(1) perform continuous emissions monitoring system
relative accuracy tests for equipment installed to meet the requirements
of §112.103 of this title (relating to Monitoring Requirements)
in accordance with 40 Code of Federal Regulations (CFR) §60.105a(g)(2)
for the FCCU ESP Stack (EPN06ESPPCV) and 40 CFR §60.106a(1)(iii)
for the No. 1 SRU Incinerator Vent (EPN 69TGINC) and No. 2 SRU Incinerator
Vent (EPN 71TGINC);
(2) perform initial and subsequent testing of monitoring
devices required by §112.103 of this title in accordance with
the manufacturer's specifications to ensure that the required monitoring
instrumentation is properly calibrated and functional. Initial testing
must be completed by the applicable compliance date in §112.108
of this title. If a monitoring device was previously tested in accordance
with the manufacturer's specifications and a record is available to
document proper procedures were followed, then an owner or operator
is not required to repeat the initial testing again under these provisions;
and
(3) conduct additional performance testing, if requested
by the executive director, in compliance with 40 CFR §60.104a
to demonstrate compliance with applicable emission limits or standards.
The notification requirements of 40 CFR §60.8(d) apply to each
initial performance test and to each subsequent performance test required
by the executive director, except for performance tests conducted
for the purpose of obtaining supplemental data because of continuous
monitoring system breakdowns, repairs, calibration checks, or zero
and span adjustments. All performance tests must be conducted using
test methods allowed in §112.105 of this title (relating to Approved
Test Methods).
|