RULE §331.182 | Area of Review |
The area of review for an aquifer storage and recovery (ASR) project is the area determined by a radius of 1/2 mile from the proposed ASR injection well. For an ASR project that includes more than one proposed injection well, the area of review is the area determined by a radius of 1/2 mile from the centroid of the injection well field. If the extent of the underground stored water of the ASR project will exceed the area determined by the 1/2 mile radius as described in this section, the area of review is the area determined by the projected extent of the underground stored water as calculated by using site-specific hydrogeologic information. In the application for authorization, the applicant shall provide information on the activities within the area of review including the following factors and their adverse impacts, if any, on the injection operation: |
Source Note: The provisions of this §331.182 adopted to be effective June 28, 1996, 21 TexReg 5443; amended to be effective January 10, 1997, 22 TexReg 58; amended to be effective November 23, 2000, 25 TexReg 11433; amended to be effective May 19, 2016, 41 TexReg 3513 |