(a) The director may approve a grant recipient's written
request for a no cost time extension of the termination date of the
grant agreement to permit the grant recipient additional time to complete
the work of the grant project if the grant recipient is in good fiscal
and programmatic standing.
(b) A written request for a no cost time extension
must include:
(1) a timeline of events beginning on the date of grant
award;
(2) a detailed explanation why the grant project is
not expected to be completed within the grant term; and
(3) if applicable, supporting documentation demonstrating
extenuating circumstances.
(c) The director may approve one or more no cost time
extensions. The duration of each no cost time extension may be no
longer than six months from the termination date of the grant agreement,
unless the director finds that special circumstances justify authorizing
additional time to complete the work of the grant project.
(d) Approval of a no cost time extension request must
be supported by a finding of good cause and the grant agreement shall
be amended to reflect the change.
(e) The director's decision to grant or deny a no cost
time extension request is final and is not subject to appeal.
|