RULE §213.5Required Edwards Aquifer Protection Plans, Notification, and Exemptions

      (viii) Pilot-scale field testing (including water quality monitoring) may be required for BMPs that are not contained in technical guidance recognized by, or prepared by, the executive director.

        (I) When pilot-scale field testing of an innovative technology (including water quality monitoring) is required, only one pilot site will be approved.

        (II) No additional approvals will be granted until the pilot study is complete and the applicant demonstrates adequate protection of the Edwards Aquifer.

        (III) If the innovative technology demonstrates adequate protection of the Edwards Aquifer, additional units may be approved for use as permanent pollution abatement measures on the Edwards Aquifer recharge zone.

        (IV) If the innovative technology demonstrates inadequate protection of the Edwards Aquifer, a retrofit of the pollution abatement measure may be required to achieve compliance with requirements under subparagraph (D) of this paragraph and no additional units will be approved for use on the Edwards Aquifer recharge zone.

    (D) Requirements for BMPs and measures.

      (i) Temporary BMPs.

        (I) The technical report must include a description of interim and permanent stabilization practices for the site, including a schedule of when the practices will be implemented. Stabilization practices may include, but are not limited to: establishment of temporary vegetation, establishment of permanent vegetation, mulching, geotextiles, sod stabilization, vegetative buffer strips, protection of trees, preservation of mature vegetation, and other appropriate measures.

          (-a-) The following records shall be maintained and made available to the executive director upon request: the dates when major grading activities occur; the dates when construction activities temporarily or permanently cease on a portion of the site; and the dates when stabilization measures are initiated.

          (-b-) Stabilization measures shall be initiated as soon as practicable in portions of the site where construction activities have temporarily or permanently ceased, but in no case more than 14 days after the construction activity in that portion of the site has temporarily or permanently ceased. Where the initiation of stabilization measures by the 14th day after construction activity temporary or permanently cease is precluded by weather conditions, stabilization measures shall be initiated as soon as practicable. Where construction activity on a portion of the site is temporarily ceased, and earth disturbing activities will be resumed within 21 days, temporary stabilization measures do not have to be initiated on that portion of site. In areas experiencing droughts where the initiation of stabilization measures by the 14th day after construction activity has temporarily or permanently ceased is precluded by seasonal arid conditions, stabilization measures shall be initiated as soon as practicable.

        (II) The technical report must include a description of structural practices to divert flows from exposed soils, store flows, or otherwise limit runoff and the discharge of pollutants from exposed areas of the site to the degree attainable. Structural practices may include, but are not limited to: silt fences, earth dikes, drainage swales, sediment traps, checks dams, subsurface drains, pipe slope drains, level spreaders, storm drain inlet protection, rock outlet protection, reinforced soil retaining systems, gabions, and sediment basins. Placement of structural practices in floodplains should be avoided to the degree attainable.

          (-a-) For common drainage locations that serve an area with ten or more acres disturbed at one time, a sediment basin that provides storage for a calculated volume of runoff from a two-year, 24-hour storm from each disturbed acre drained, or equivalent control measures, shall be provided where attainable until final stabilization of the site. Where no such calculation has been performed, a sediment basin providing 3,600 cubic feet of storage per acre drained, or equivalent control measures, shall be provided where attainable until final stabilization of the site. When computing the number of acres draining into a common location it is not necessary to include flows from off-site areas and flows from on-site areas that are either undisturbed or have undergone final stabilization where such flows are diverted around both the disturbed area and the sediment basin.

          (-b-) In determining whether installing a sediment basin is attainable, the applicant may consider factors such as site soils, slope, and available area on site. For drainage locations which serve ten or more disturbed acres at one time and where a sediment basin or equivalent controls is not attainable, smaller sediment basins and/or sediment traps should be used. Where neither the sediment basin nor equivalent controls are attainable due to site limitations, silt fences, vegetative buffer strips, or equivalent sediment controls are required for all down slope boundaries of the construction area and for those side slope boundaries deemed appropriate as dictated by individual site conditions. The executive director encourages the use of a combination of sediment and erosion control measures in order to achieve maximum pollutant removal.

          (-c-) For drainage locations serving less than ten acres, smaller sediment basins and/or sediment traps should be used. At a minimum, silt fences, vegetative buffer strips, or equivalent sediment controls are required for all down slope boundaries (and for those side slope boundaries deemed appropriate as dictated by individual site conditions) of the construction area unless a sediment basin providing storage for a calculated volume of runoff from a two-year, 24- hour storm or 3,600 cubic feet of storage per acre drained is provided. The executive director encourages the use of a combination of sediment and erosion control measures in order to achieve maximum pollutant removal.

      (ii) Permanent BMPs and measures.

        (I) BMPs and measures must be implemented to control the discharge of pollution from regulated activities after the completion of construction. These practices and measures must be designed, constructed, operated, and maintained to insure that 80% of the incremental increase in the annual mass loading of total suspended solids from the site caused by the regulated activity is removed. These quantities must be calculated in accordance with technical guidance prepared or accepted by the executive director.

        (II) Owners of permanent BMPs and measures must insure that the BMPs and measures are constructed and function as designed. A Texas licensed professional engineer must certify in writing that the permanent BMPs or measures were constructed as designed. The certification letter must be submitted to the appropriate regional office within 30 days of site completion.

        (III) Where a site is used for low density single-family residential development and has 20% or less impervious cover, other permanent BMPs are not required. This exemption from permanent BMPs must be recorded in the county deed records, with a notice that if the percent impervious cover increases above 20% or land use changes, the exemption for the whole site as described in the property boundaries required by §213.4(g) of this title, may no longer apply and the property owner must notify the appropriate regional office of these changes.

        (IV) The executive director may waive the requirement for other permanent BMPs for multi-family residential developments, schools, or small business sites where 20% or less impervious cover is used at the site. This exemption from permanent BMPs must be recorded in the county deed records, with a notice that if the percent impervious cover increases above 20% or land use changes, the exemption for the whole site as described in the property boundaries required by §213.4(g) of this title, may no longer apply and the property owner must notify the appropriate regional office of these changes.

    (E) The technical report must describe measures that will be used to avoid or minimize surface stream contamination and changes in the way in which water enters a stream as a result of the construction and development. The measures should address the following:

      (i) increased stream flashing;

      (ii) the creation of stronger flows and in-stream velocities; or

      (iii) other in-stream effects caused by the regulated activity which increase erosion that results in water quality degradation.

    (F) The technical report must describe the method of wastewater disposal from the site.

      (i) If wastewater is to be disposed of by conveyance to a sewage treatment plant for treatment and disposal, the existing or proposed treatment facility must be identified.

      (ii) If wastewater is to be disposed of by an on-site sewage facility, the application must include a written statement from the appropriate authorized agent, stating that the site is suitable for the use of private sewage facilities and will meet the special requirements for on-site sewage facilities located on the Edwards Aquifer recharge zone as specified under Chapter 285 of this title (relating to On-Site Sewage Facilities), or identifying those areas that are not suitable.

    (G) The technical report must describe the measures that will be used to contain any spill of hydrocarbons or hazardous substances such as on a roadway or from a pipeline or from temporary aboveground storage of 250 gallons or more.

      (i) Temporary storage facilities are those used on site for less than one year.

      (ii) Temporary aboveground storage tank systems of 250 gallons or more cumulative storage capacity must be located a minimum horizontal distance of 150 feet from any domestic, industrial, irrigation, or public water supply well, or other sensitive feature.

  (5) Responsibility for maintenance of permanent BMPs and measures after construction is complete.

    (A) The applicant shall be responsible for maintaining the permanent BMPs after construction until such time as the maintenance obligation is either assumed in writing by another entity having ownership or control of the property (such as without limitation, an owner's association, a new property owner or lessee, a district, or municipality) or the ownership of the property is transferred to the entity. Such entity shall then be responsible for maintenance until another entity assumes such obligations in writing or ownership is transferred.

    (B) A copy of the transfer of responsibility must be filed with the executive director at the appropriate regional office within 30 days of the transfer.

    (C) This paragraph applies to:

      (i) multiple single-family residential developments, multi-family residential; and

      (ii) non-residential developments such as commercial, industrial, institutional, schools, and other sites where regulated activities occur.

(c) Organized sewage collection systems.

  (1) No person may commence rehabilitation or construction related to an existing or new organized sewage collection system on the recharge zone, until final design plans, specifications, and an engineering report, as specified in Chapter 317 of this title (relating to Design Criteria for Sewerage Systems) and appropriate special requirements of this section, have been filed with and approved by the executive director.

  (2) General design of sewage collection systems. Design of new sewage collection systems on the recharge zone must comply with Chapter 317 of this title.

  (3) Special requirements for sewage collection systems. In addition to the requirements in paragraph (2) of this subsection, sewage collection systems on the recharge zone must meet the following special requirements.

    (A) Manhole rehabilitation or construction. All manholes rehabilitated or constructed after March 21, 1990, must be watertight, with watertight rings and covers and must be constructed and tested to meet the requirements of §317.2(c)(5)(H) of this title (relating to Sewage Collection System).

    (B) Piping for gravity and pressurized collection systems. Compliance with the following is required, unless local regulations dictate more stringent standards:

      (i) for gravity collection systems, all PVC pipe must have a Standard Dimension Ratio (SDR) of 35 or less and meet the requirements of §317.2(a) - (c)(4) of this title; and

      (ii) for all pressurized sewer systems, all PVC pipe must have a minimum working pressure rating of 150 pounds per square inch and meet the requirements of §317.2(d)(2) - (4) and §317.3(d)(5) - (7) of this title (relating to Sewage Collection System and Lift Stations).

    (C) Lift station design. Lift stations must be designed and constructed to ensure that bypassing of any sewage does not occur. All lift stations must be designed to meet the requirements of §317.2(d) and §317.3 of this title. A lift station application must include final construction plans and a design report prepared by or under the direct supervision of a Texas licensed professional engineer. All design information must be signed, sealed, and dated by a Texas licensed professional engineer.

    (D) Certification of new sewage collection system lines by a Texas licensed professional engineer. Owners of sewage collection systems must insure that all new gravity sewer system lines having a diameter greater than or equal to six inches and all new force mains are tested for leakage following construction. Such lines must be certified by a Texas licensed professional engineer to meet the appropriate requirements of §317.2 of this title. The engineer must retain copies of all test results which must be made available to the executive director upon request. The engineer must certify in writing that all wastewater lines have passed all required testing to the Cont'd...

Next Page Previous Page

Link to Texas Secretary of State Home Page | link to Texas Register home page | link to Texas Administrative Code home page | link to Open Meetings home page