        (IV) Hot water distribution systems. Hot water distribution systems for patient care areas shall be under constant recirculation to provide continuous hot water at each hot water outlet. Nonrecirculated fixtures branch piping shall not exceed 25 feet in length. Water temperature is measured at the point of use or inlet to the equipment. Tankless water system may be used at point of use.

        (V) Domestic hot water system. The domestic hot water system shall make provisions to limit the amount of Legionella bacteria and opportunistic waterborne pathogens.

      (viii) Drainage systems.

        (I) Above ground piping. Soil stacks, drains, vents, waste lines, and leaders installed above ground within buildings shall be drain-waste-vent (DWV) weight or heavier and shall be: copper pipe, copper tube, cast iron pipe, or galvanized iron pipe.

        (II) Underground piping. All underground building drains shall be: cast iron soil pipe, hard temper copper tube (DWV or heavier), acrylonitrile-butodiene-styrene (ABS) plastic pipe (DWV Schedule 40 or heavier), polyvinyl chloride (PVC) plastic pipe (DWV Schedule 40 or heavier), or extra strength vitrified clay pipe (VCP) with compression joints or couplings with at least 12 inches of earth cover.

        (III) Drains for chemical wastes. Separate drainage systems for chemical wastes (acids and other corrosive materials) shall be provided. Materials acceptable for chemical waste drainage systems shall include chemically resistant glass pipe, high silicone content cast iron pipe, VCP, plastic pipe, or plastic lined pipe.

      (ix) Thermal insulation for piping systems and equipment. Insulation shall be provided for the following:

        (I) boilers, smoke breeching, and stacks;

        (II) steam supply and condensate return piping;

        (III) hot water piping and all hot water heaters, generators, converters, and storage tanks;

        (IV) chilled water, refrigerant, other process piping, equipment operating with fluid temperatures below ambient dew point, and water supply and drainage piping on which condensation may occur. Insulation on cold surfaces shall include an exterior vapor barrier;

        (V) other piping, ducts, and equipment as necessary to maintain the efficiency of the system.

      (x) Pipe and equipment insulation rating. Flame spread shall not exceed 25 and smoke development rating shall not exceed 150 for pipe insulation as determined by an independent testing laboratory in accordance with National Fire Protection Association 255, Standard Method of Test of Surface Burning Characteristics of Building Materials, 2000 edition. Smoke development rating for pipe insulation located in environmental air areas shall not exceed 50.

      (xi) Asbestos insulation. Asbestos insulation shall not be used.

    (B) Plumbing fixtures. Plumbing fixtures shall be made of nonabsorptive acid-resistant materials and shall comply with the recommendations of the National Standard Plumbing Code and this paragraph.

      (i) Sink and lavatory controls. All fixtures used by medical and nursing staff and all lavatories used by patients and food handlers shall be trimmed with valves which can be operated without the use of hands. Blade handles used for this purpose shall not be less than four inches in length. Single lever or wrist blade devices may be used.

      (ii) Clinical sink traps. Clinical sinks shall have an integral trap in which the upper portion of a visible trap seal provides a water surface.

      (iii) Sinks for disposal of plaster of paris. Sinks used for the disposal of plaster of paris shall have a plaster trap.

      (iv) Back-flow or siphoning. All plumbing fixtures and equipment shall be designed and installed to prevent the back-flow or back-siphonage of any material into the water supply. The over-the-rim type water inlet shall be used wherever possible. Vacuum-breaking devices shall be properly installed when an over-the-rim type water inlet cannot be utilized.

      (v) Drinking fountain. Each drinking fountain shall be designed so that the water issues at an angle from the vertical, the end of the water orifice is above the rim of the bowl, and a guard is located over the orifice to protect it from lip contamination.

      (vi) Sterilizing equipment. All sterilizing equipment shall be designed and installed to prevent not only the contamination of the water supply but also the entrance of contaminating materials into the sterilizing units.

      (vii) Hose attachment. No hose shall be affixed to any faucet if the end of the hose can become submerged in contaminated liquid unless the faucet is equipped with an approved, properly installed vacuum breaker.

      (viii) Bedpan washers and sterilizers. Bedpan washers and sterilizers shall be designed and installed so that both hot and cold water inlets shall be protected against back-siphonage at maximum water level.

      (ix) Flood level rim clearance. The water supply spout for lavatories and sinks required in patient care areas shall be mounted so that its discharge point is a minimum of five inches above the rim of the fixture.

      (x) Scrub sink controls. Scrub sinks and lavatories used for scrubbing in procedure rooms shall be trimmed with foot, knee, or ultrasonic controls. Single lever wrist blades are not acceptable at scrub sinks.

      (xi) Floor drains or floor sinks. Where floor drains or floor sinks are installed, they shall be of a type that can be easily cleaned by removal of the cover. Removable stainless steel mesh shall be provided in addition to grilled drain cover to prevent entry of large particles of waste which might cause stoppages.

      (xii) Under-counter piping. Under-counter piping and above floor drains shall be arranged (raised) so as not to interfere with cleaning of floor below the equipment.

      (xiii) Ice machines. All ice-making machines used for human consumption shall be of the self-dispensing type. Copper tubing shall be provided for supply connections to ice machines.

      (xiv) Food disposal units. A food disposal unit shall only be permitted in the dietary department (§133.163(e) of this title).

  (5) General electrical requirements. This paragraph contains common electrical requirements. The hospital shall comply with the requirements of this paragraph and with any specific electrical requirements for the particular unit of the hospital in accordance with §133.163 of this title.

    (A) Electrical installations. All new electrical material and equipment, including conductors, controls, and signaling devices, shall be installed in compliance with applicable sections of the National Fire Protection Association 70, National Electrical Code, 1999 edition (NFPA 70), and NFPA 99 and as necessary to provide a complete electrical system. Electrical systems and components shall be listed by nationally recognized listing agencies as complying with available standards and shall be installed in accordance with the listings and manufacturers' instructions.

      (i) All fixtures, switches, sockets, and other pieces of apparatus shall be maintained in a safe and working condition.

      (ii) Extension cords and cables shall not be used for permanent wiring.

      (iii) All electrical heating devices shall be equipped with a pilot light to indicate when the device is in service, unless equipped with a temperature limiting device integral with the heater.

      (iv) All equipment, fixtures, and appliances shall be properly grounded in accordance with NFPA 70.

      (v) Under-counter receptacles and conduits shall be arranged (raised) to not interfere with cleaning of floor below the equipment.

    (B) Installation testing and certification.

      (i) Installation testing. The electrical installations, including alarm, nurses calling system and communication systems, shall be tested to demonstrate that equipment installation and operation is appropriate and functional.

      (ii) Grounding system testing. The grounding system shall be tested as described in NFPA 99, 4.3.3, for patient care areas in new or renovated work. The testing shall be performed by a qualified electrician or their qualified electrical testing agent. The electrical contractor shall provide a letter stating that the grounding system has been tested in accordance with NFPA 99, the testing device use complies with NFPA 99, and whether the grounding system passed the test. The letter shall be signed by the qualified electrical contractor, or their designated qualified electrical testing agent, certifying that the system has been tested and the results of the test are indicated.

    (C) Electrical safeguards. Shielded isolation transformers, voltage regulators, filters, surge suppressors, and other safeguards shall be provided as required where power line disturbances are likely to affect fire alarm components, data processing, equipment used for treatment, and automated laboratory diagnostic equipment.