  (7) Materials finishes. Materials known to produce noxious gases when burned shall not be used for mattresses, upholstery, and wall finishes.

(g) General mechanical requirements. This subsection contains requirements for mechanical systems; air conditioning, heating and ventilating systems; steam and hot and cold water systems; and thermal and acoustical insulation.

  (1) Cost. All mechanical systems shall be designed for overall efficiency and life cycle costing, including operational costs. Recognized engineering practices shall be followed to achieve the most economical and effective results except that in no case shall patient care or safety be sacrificed for conservation.

  (2) Equipment location. Mechanical equipment may be located indoors or outdoors (when in a weatherproof enclosure), or in a separate building(s).

  (3) Vibration isolation. Mechanical equipment shall be mounted on vibration isolators as required to prevent unacceptable structure-borne vibration. Ducts, pipes, etc. connected to mechanical equipment which is a source of vibration shall be isolated from the equipment with vibration isolators.

  (4) Performance and acceptance. Prior to completion and acceptance of the facility, all mechanical systems shall be tested, balanced, and operated to demonstrate to the design engineer or his representative that the installation and performance of these systems conform to the requirements of the plans and specifications.

    (A) Material lists. Upon completion of the contract, the owner shall obtain from the construction contractor parts lists and procurement information with numbers and descriptions for each piece of equipment.

    (B) Instructions. Upon completion of the contract, the owner shall obtain from the construction contractor instructions in the operational use and maintenance of systems and equipment as required.

  (5) Heating, ventilating, and air conditioning (HVAC) systems.

    (A) All central HVAC systems shall comply with and shall be installed in accordance with the requirements of NFPA 90A, Standard for the Installation of Air Conditioning and Ventilating Systems, 2002 Edition, or NFPA 90B, Standard for the Installation of Warm Air Heating and Air-Conditioning Systems, 2002 Edition, as applicable and the requirements contained in this paragraph. Air handling units serving two or more rooms are considered to be central units.

    (B) Noncentral air handling systems, i.e., individual room units that are used for heating and cooling purposes (e.g., fan-coil units, heat pump units, and packaged terminal air conditioning units) shall be equipped with permanent (cleanable) or replaceable filters. The filters shall have an average efficiency of 25 - 30% and an average arrestance of 85% based on American Society of Heating, Refrigerating, and Air-Conditioning Engineers (ASHRAE), Inc., Standard 52.2, 1999 edition, Method of Testing General Ventilation Air Cleaning Devices for Removal Efficiency by Particle Size. These units shall be used as air recirculating units only. All outdoor air requirements shall be met by a separate central air handling system with the proper filtration, as required in Table 1 of §135.56(a) of this title.

    (C) General ventilation requirements. All rooms and areas in the ASC shall have provision for positive ventilation. Fans serving exhaust systems shall be located at the discharge end and shall be conveniently accessible for service. Exhaust systems may be combined, unless otherwise noted, for efficient use of recovery devices required for energy conservation. The ventilation rates shown in Table 1 of §135.56(a) of this title shall be used only as minimum requirements, since they do not preclude the use of higher rates that may be appropriate.

      (i) Cost reduction methods. To reduce utility costs, facility design may utilize energy conserving procedures including recovery devices, variable air volume, load shedding, systems shutdown, or reduction of ventilation rates (when specifically permitted) in certain areas when unoccupied. In no case shall patient care be jeopardized.

      (ii) Economizer cycle. Mechanical systems shall be arranged to take advantage of outside air conditions by using an economizer cycle when appropriate to reduce heating and cooling systems loads. Innovative design that provides for additional energy conservation while meeting the intent of this section for acceptable patient care may be presented to the department for consideration.

      (iii) Areas requiring fully ducted systems. Fully ducted supply, return and exhaust air for HVAC systems shall be provided for all critical care areas, sensitive care areas, all patient care areas, all areas requiring a sterile regimen, clean storage rooms, and where required for fire safety purposes. Combination systems, utilizing both ducts and plenums for movement of air in these areas, shall not be permitted. Ductwork access panels shall be labeled.

      (iv) Temperatures and humidities. The designed capacity of the systems shall be capable of providing the ranges of temperatures and humidities as shown in Table 1 of §135.56(a) of this title.

      (v) Thermometers and humidity gauges. Each operating room, special procedure room, and postoperative recovery suite shall have temperature and humidity indicating devices mounted at eye level.

      (vi) Outside air intake locations.

        (I) Outside air intakes shall be located at least 25 feet from exhaust outlets of ventilating systems, combustion equipment stacks, medical-surgical vacuum system outlets, plumbing vents, or areas which may collect vehicular exhaust or other noxious fumes. (Prevailing winds and proximity to other structures may require other arrangements).

        (II) Plumbing and vacuum vents that terminate five feet above the level of the top of the air intake may be located as close as 10 feet to the air intake.

        (III) The bottom of outside air intakes serving central systems shall be located as high as practical but at least six feet above ground level, or if installed above the roof, three feet above the roof level.

      (vii) Contaminated air exhaust outlets. Exhaust outlets from areas (laboratory hoods, etc.) that exhaust contaminated air shall be above the roof and be arranged to exhaust upward unless the air has been treated by an appropriate means where sidewall exhaust will be allowed. Exhaust outlets from areas containing ethylene oxide sterilizers and other contaminants, e.g., glutaraldehyde, shall terminate not less than eight feet above the roof level (or be appropriately labeled as "hazardous exhaust") and arranged to exhaust upward.

      (viii) Directional air flow. Ventilation systems shall be designed and balanced to provide pressure relationships contained in Table 1 of §135.56(a) of this title. For reductions and shut down of ventilation systems when a room is unoccupied, the provisions in Note 4 of Table 1 of §135.56(a) of this title shall be followed.

      (ix) Air distribution devices. Design shall consider turbulence and other factors of air movement to minimize airborne particulate matter. Where extraordinary procedures require special designs, the installation shall be reviewed on a case-by-case basis.

        (I) All supply diffusers grilles shall be located on the ceiling or on a wall near the ceiling.

        (II) Air supply for the operating rooms and special procedure rooms shall be from ceiling outlets near the center of the work area to efficiently control air movement.

        (III) A minimum of two return air inlets located diagonally opposite from one another and near floor level shall be provided. Bottoms of return air grilles in operating rooms and other anesthetizing locations shall be located not more than 12 inches above the finished floor nor less than six inches above the finished floor.

      (x) Ventilation start-up requirements. Air handling systems shall not be started or operated without the filters installed in place. This includes the 90% and 99.97% efficiency filters where required. This includes during construction operations. Ducts shall be cleaned thoroughly and throughout by a National Air Duct Cleaners Association (NADCA) certified air duct cleaning contractor when the air handling systems have been operating without the required filters in place. When ducts are determined to be dirty or dusty, the department shall require a written report assuring cleanliness of duct and clean air quality.

      (xi) Humidifier location. When duct humidifiers are located upstream of the final filters, they shall be located at least 15 feet from the filters. Duct work with duct-mounted humidifiers shall be provided with a means of removing water accumulation. An adjustable high-limit humidistat shall be located downstream of the humidifier to reduce the potential of condensation inside the duct. All duct takeoffs shall be sufficiently downstream of the humidifier to ensure complete moisture absorption. Reservoir-type water spray or evaporative pan humidifiers shall not be used.