      (iv) schedules of doors, windows, and finishes;

      (v) elevations of each facade;

      (vi) sections through building; and

      (vii) scaled details as necessary.

    (B) Fire safety plans. These drawings shall be provided for all newly constructed buildings, conversions of existing buildings for facilities, additions to existing licensed facilities, and remodeled portions of existing buildings containing licensed facilities. Fire safety plans shall be of a sufficiently large-scale to clearly illustrate the proposed design but not less than one-sixteenth inch equals one foot and shall include the following information:

      (i) separate fire safety plans (preferably one floor plan per sheet) shall indicate location of fire protection rated walls and partitions, location and fire resistance rating of each fire damper, and the required means of egress (corridors, stairs, exits, exit passageways);

        (I) when a new building is to contain a proposed facility, when an existing building is converted to a facility, or when an addition is made to an existing facility building, plans of each floor and roof shall be provided;

        (II) when a portion of a building is remodeled or when a new service is added, only the plan of the floor where the remodeling will take place or new service will be introduced, and the plan of the floor of discharge shall be provided;

      (ii) designated smoke compartments with floor areas of each compartment, location, and fire resistance rating (one or two hour) of each smoke partition, location, type, and fire resistance rating of each smoke damper;

      (iii) location of all required fire alarm devices, including all fire alarm control panels, manual pull stations, audible and visual fire alarm signaling devices, smoke detectors (ceiling and duct-mounted), fire alarm annunciators, fire alarm transmission devices, fire sprinkler flow switches, and control valve supervisory switches on each of the floor plans; and

      (iv) areas protected with fire sprinkler systems (pendant, sidewall or upright, normal or quick response, and temperature rating shall be indicated), stand pipe system risers and sizes with valves and inside and outside fire department connections, fire sprinkler risers and sizes, location and type of portable fire extinguishers.

    (C) Equipment drawings. Equipment drawings shall include the following:

      (i) all equipment necessary for the operation of the facility as planned. The design shall indicate provisions for the installation of large and special items of equipment and for service accessibility;

      (ii) fixed equipment (equipment which is permanently affixed to the building or which must be permanently connected to a service distribution system designed and installed during construction for the specific use of the equipment). The term "fixed equipment" includes items such as laundry extractors, walk-in refrigerators, communication systems, and built-in casework (cabinets);

      (iii) movable equipment (equipment not described in clause (ii) of this subparagraph as fixed). The term "moveable equipment" includes wheeled equipment, plug-in type monitoring equipment, and relocatable items; and

      (iv) equipment which is not included in the construction contract but which requires mechanical or electrical service connections or construction modifications. The equipment described in this clause shall be identified on the drawings to ensure its coordination with the architectural, mechanical, and electrical phases of construction.

    (D) Structural drawings. Structural drawings shall include:

      (i) plans for foundations, floors, roofs, and all intermediate levels;

      (ii) a complete design with sizes, sections, and the relative location of the various members;

      (iii) a schedule of beams, girders, and columns;

      (iv) dimensioned floor levels, column centers, and offsets;

      (v) details of all special connections, assemblies, and expansion joints; and

      (vi) special openings and pipe sleeves dimensioned or otherwise noted for easy reference.

    (E) Mechanical drawings. Mechanical drawings shall include:

      (i) complete ventilation systems (supply, return, exhaust), all fire and smoke partitions, locations of all dampers, registers, and grilles, air volume flow at each device, and identification of all spaces (e.g., corridor, patient room, operating room);

      (ii) boilers, chillers, heating and cooling piping systems (steam piping, hot water, chilled water), and associated pumps;

      (iii) cold and warm water supply systems, water heaters, storage tanks, circulating pumps, plumbing fixtures, emergency water storage tank(s) (if provided), and special piping systems such as for deionized water;

      (iv) nonflammable medical gas piping (oxygen, compressed medical air, vacuum systems, nitrous oxide), emergency shutoff valves, pressure gages, alarm modules, gas outlets;

      (v) drain piping systems (waste and soiled piping systems, laboratory drain systems, roof drain systems);

      (vi) fire protection piping systems (sprinkler piping systems, fire standpipe systems, water or chemical extinguisher piping system for cooking equipment);

      (vii) piping riser diagrams, equipment schedules, control diagrams or narrative description of controls, filters, and location of all duct-mounted smoke detectors; and

      (viii) laboratory exhaust and safety cabinets.

    (F) Electrical drawings. Electrical drawings shall include:

      (i) electrical service entrance with service switches, service feeders to the public service feeders, and characteristics of the light and power current including transformers and their connections;

      (ii) location of all normal electrical system and essential electrical system conduits, wiring, receptacles, light fixtures, switches, and equipment which require permanent electrical connections, on plans of each building level:

        (I) light fixtures marked distinctly to indicate connection to critical or life safety branch circuits or to normal lighting circuits; and

        (II) outlets marked distinctly to indicate connection to critical, life safety, or normal power circuits;

      (iii) telephone and communication, fixed computers, terminals, connections, outlets, and equipment;

      (iv) nurses calling system showing all stations, signals, and annunciators on the plans;

      (v) in addition to electrical plans, single line diagrams prepared for:

        (I) complete electrical system consisting of the normal electrical system and the essential electrical system including the on-site generator(s), transfer switch(es), emergency system (life safety branch and critical branch), equipment system, panels, subpanels, transformers, conduit, wire sizes, main switchboard, power panels, light panels, and equipment for additions to existing buildings, proposed new facilities, and remodeled portions of existing facilities. Feeder and conduit sizes shall be shown with schedule of feeder breakers or switches;

        (II) complete nurses calling system with all stations, signals, annunciators, etc. with room number noted by each device and indicating the type of system (nurses regular calling system, nurses emergency calling system, or staff emergency assistance calling system);

        (III) a single line diagram of the complete fire alarm system showing all control panels, signaling and detection devices and the room number where each device is located; and

      (vi) schedules of all panels indicating connection to life safety branch, critical branch, equipment system or normal system, and connected load at each panel.

  (3) Construction document changes. Any changes to the final construction documents which affect or change the function, design, or designated use of an area shall be submitted to the department for approval prior to authorization of the modifications.

(g) Special submittals.

  (1) Self-certification.

    (A) In an effort to shorten the plan review and approval process, the ASC owner/operator or representative may request approval of final construction documents under the self-certification review process.

      (i) The owner/operator shall submit the items in subsection (b)(1)(A) - (C) of this section and a completed self-certification form, signed by the ASC owner/operator, architect of record, and engineer(s) of record attesting that the plans and specifications are based upon and comply with the requirements of this chapter.

      (ii) By signing and submitting the self-certification form, the ASC owner/operator accepts the following conditions.

        (I) The department retains the right to review the final construction documents, conduct inspections of the project, and withdraw its approval.