      (ii) Boiler accessories including feed pumps, heat-circulating pumps, condensate return pumps, fuel oil pumps, and waste heat boilers shall be connected and installed to provide both normal and standby service.

    (F) Ground fault circuit interrupters (GFCI) receptacles shall be provided for all general use receptacles located within three feet of a wash basin or sink. When GFCI receptacles are used, they shall be connected to not affect other devices connected to the circuit in the event of a trip. Receptacles connected to the critical branch that may be used for equipment that should not be interrupted do not have to be GFCI protected. Receptacles in wet locations, as defined by NFPA 70, §517.20 and §517.21, shall be GFCI protected regardless of the branch of the electrical system serving the receptacle.

  (9) A nurses emergency calling system shall be installed in the patient waiting area, all individual treatment rooms, exam rooms, isolation rooms, hepatitis B rooms, and toilet rooms used by patients to summon nursing staff in an emergency. Activation of the system shall sound a repeating (every 5 seconds or less) distinct audible signal at the nurse station, indicate type and location of call on the system monitor, and activate a distinct visible signal in all areas. The visible and audible signals shall be cancelable only at the patient calling station. A nurses emergency call system shall be accessible to a collapsed patient lying on the floor. Inclusion of a pull cord extending to within 6 inches of the floor will satisfy this requirement.

  (10) The ESRD facility shall provide, at submission of construction documents/plans a letter on facility letterhead indicating the method the ESRD facility has chosen for implementation of the emergency contingency plan for the continuity of emergency essential building systems (emergency generator). The contingency plan shall consist of one of the three options as described as follows.

    (A) An onsite emergency generator shall be provided with a Type II essential electrical distribution system in accordance with requirements of NFPA 99, §4.5, and National Fire Protection Association 110, Standard for Emergency and Standby Power Systems, 2002 Edition.

      (i) An emergency generator standby power system(s) shall require an onsite fuel source and enough fuel capacity in the tank for a period of twenty-four hours or more. When a vapor liquefied petroleum gas (LPG) (natural gas) system is used, the twenty-four hour fuel capacity on site is not required. The vapor withdrawal LPG system shall require a dedicated fuel supply.

      (ii) The emergency generator shall be installed, tested and maintained in accordance with the National Fire Protection Association 99, §4.5.4, and National Fire Protection Association 110, Standard for Emergency and Standby Power Systems, 2002 Edition.

      (iii) When the emergency generator(s) and electrical transformer(s) are located within the same area, they shall be located at least 10 feet apart.

      (iv) Sufficient quantity of potable water supply shall be on site for the operation of the water treatment system for at least twenty-four hours. A water valve connection shall be provided to allow hook-up for potable water from an outside vendor to supply the water treatment system.

    (B) A executed contract with an outside supplier/vendor(s) that will provide a portable emergency generator(s) and potable water on demand.

      (i) An electrical transfer switch with plug-in device sized to provide emergency power for the patient care areas and the provisions in NFPA 99, §4.5.2.2.2.

      (ii) A water valve connection to allow hook-up for potable water from an outside vendor to supply the water treatment system.

      (iii) An alternate source of power (battery power lighting) shall be provided separate and independent from the normal electrical power source that will be effective for a minimum of 1-1/2 hours after loss of the electrical power. The emergency lighting system shall be capable of providing sufficient illumination to allow safe evacuation from the building. The battery pack systems shall be maintained and tested quarterly.

      (iv) The facility shall implement the emergency contingency plan upon the loss of electrical power following a natural weather or man-made event when the electrical power may not be restored within 24 hours. The facility shall exercise the contract(s) with the supplier/vendor(s) in order to have portable emergency generator(s) and potable water available within 36 hours after the loss of electrical power.

    (C) An executed contract with another licensed ESRD facility within a 100 mile radius to provide emergency contingency care for the patients.

      (i) The accepting licensed ESRD facility shall meet the requirements of paragraph (1) of this subsection.

      (ii) An alternate source of power shall be provided separate and independent from the normal electrical power source that will be effective for a minimum of 1-1/2 hours after loss of the electrical power. The emergency lighting system shall be capable of providing sufficient illumination to allow safe evacuation from the building. The battery pack systems shall be maintained and tested quarterly.

  (11) A fire alarm system, which complies with NFPA 101, §18.3.4, and with NFPA 72, Chapter 6 requirements, shall be provided in each facility. The required fire alarm system components are as follows:

    (A) A fire alarm control panel (FACP) shall be installed at a visible central location.

    (B) Manual fire alarm pull stations shall be installed in accordance with NFPA 101, §18.3.4.

    (C) Smoke detectors for door release service shall be installed on the ceiling at each door opening in the smoke partition in accordance with NFPA 72, §6.15.6, where the doors are held open with electromagnetic devices conforming with NFPA 101, §18.2.2.6.

    (D) Smoke detectors shall be installed in air ducts in accordance with NFPA 72, §5.14.4.2 and §5.14.5 and NFPA 90A, §6.4.2.

    (E) Smoke detectors shall be installed in return air ducts in accordance with requirements of NFPA 72 §5.14.4.2.2 and §5.14.5 and NFPA 90A, §6.4.2.2.

    (F) Fire sprinkler system water flow switches shall be installed in accordance with requirements of NFPA 101, §9.6.2; NFPA 13, §6.9; and NFPA 72, §8.5.3.3.3.4.

    (G) Sprinkler system valve supervisory switches shall be installed in accordance with the requirements of NFPA 72, §6.8.5.5.

    (H) Audible alarm indicating devices shall be installed in accordance with the requirements of NFPA 101, §18.3.4, and NFPA 72, §7.4.

    (I) Visual fire alarm indicating devices, which comply with the requirements of NFPA 72, §7.5, shall be provided.

    (J) Devices for transmitting alarm for alerting the local fire brigade or municipal fire department of fire or other emergency shall be provided. The devices shall be listed for the fire alarm service by a nationally recognized laboratory, and be installed in accordance with such listing and the requirements of NFPA 72.

    (K) A fire alarm signal notification, which complies with NFPA 101, §9.6.3, shall be provided to alert occupants of fire or other emergency.

    (L) Wiring for fire alarm detection circuits and fire alarm notification circuits shall comply with requirements of NFPA 70, Article 760.

    (M) Smoke detector(s) for shutdown of air handling units shall be provided. The detectors shall be installed in accordance with NFPA 90A, §6.4.3.

    (N) Telecommunications and information systems central equipment shall be installed in a separate location designed for the intended purpose. Special air conditioning and voltage regulation shall be provided as recommended by the manufacturer.

    (O) When installed, lightning protection systems shall comply with National Fire Protection Association 780, Standard for the Installation of Lightning Protection Systems, 2000 Edition.


Source Note: The provisions of this §117.102 adopted to be effective July 6, 2010, 35 TexReg 5835