RULE §9.152General Rules for Design-Build Contracts

(n) Additional matters. Any matter not specifically addressed in this subchapter that pertains to the construction, expansion, extension, related maintenance, rehabilitation, alteration, or repair of a highway project pursuant to this subchapter, shall be deemed to be within the primary purview of the commission, and all decisions pertaining thereto, whether or not addressed in this subchapter, shall be as determined by the commission, subject to the provisions of applicable law.

(o) Performance and payment security. The department shall require a private entity entering into a design-build contract to provide a performance and payment bond or an alternative form of security, or a combination of bonds and other forms of security, in an amount equal to the cost of constructing the project, unless the department determines that it is impracticable for a private entity to provide security in that amount, in which case the department will set the amount of security. The security will be in the amount that, in the department's sole determination, is sufficient to ensure the proper performance of the agreement, and to protect the department and payment bond beneficiaries supplying labor or materials to the private entity or a subcontractor of the private entity. Bonds and alternate forms of security shall be in the form and contain the provisions required in the request for proposals or the design-build contract, with such changes or modifications as the department determines to be in the best interest of the state. In addition to, or in lieu of, performance and payment bonds, the department may require:

  (1) a cashier's check drawn on a federally insured financial institution, and drawn to the order of the department;

  (2) United States bonds or notes, accompanied by a duly executed power of attorney and agreement authorizing the collection or sale of the bonds or notes in the event of the default of the private entity or a subcontractor of the private entity, or such other act or event that, under the terms of the design-build contract, would allow the department to draw upon or access that security;

  (3) an irrevocable letter of credit issued or confirmed by a financial institution to the benefit of the department, meeting the credit rating and other requirements prescribed by the department, and providing coverage for a period of at least one year following final acceptance of the project or, if there is a warranty period, at least one year following completion of the warranty period;

  (4) an irrevocable letter signed by a guarantor meeting the net worth or other financial requirements prescribed in the request for proposals or design-build contract, and which guarantees, to the extent required under the request for proposals or design-build contract, the full and prompt payment and performance when due of the private entity's obligations under the design-build contract; or

  (5) any other form of security deemed suitable by the department.

(p) Performance evaluations. The department will evaluate the performance of a private entity that enters into a design-build contract, and will evaluate the performance of the private entity's major team members, consultants, and subcontractors, in accordance with the requirements of this subsection. Evaluations will be conducted annually at twelve month intervals during the term of the design-build contract, upon termination of the design-build contract, and when the department determines that work is materially behind schedule or not being performed according to the requirements of the design-build contract. Optional evaluations may be conducted as provided in the design-build contract. Acts or omissions that are the subject of a good faith dispute will not be considered. After a performance evaluation is conducted, and for at least 30 days before the evaluation becomes final and is used by the department, the department will provide for review and comment a copy of the performance evaluation report to the entity being evaluated and, if that entity is a consultant or subcontractor, to the entity that entered into the design-build contract. The department will consider and take into account any submitted comments before the department finalizes the performance evaluation report. The results of performance evaluations will be provided to the entity that was evaluated and may be used in the evaluation of qualifications submittals and proposals submitted under §9.153 of this subchapter and §27.4 of this title (relating to Solicited Proposals) by proposers that include the major team members, consultants, and subcontractors evaluated.


Source Note: The provisions of this §9.152 adopted to be effective March 15, 2012, 37 TexReg 1780; amended to be effective July 19, 2012, 37 TexReg 5334; amended to be effective September 14, 2016, 41 TexReg 7134