RULE §9.2Contract Claim Procedure

hearing provided in subparagraph (D)(ii) of this paragraph.

    (D) The committee chairman shall give written notice of the committee's decision on the claim to the department and prime contractor. The department and prime contractor are presumed to receive the decision three days after it is sent by United States mail.

      (i) If the prime contractor does not object to the committee's decision, the prime contractor shall file a written statement with the committee's chairman stating that the prime contractor does not object. The prime contractor shall file the statement no later than 20 days after receipt of the committee's decision. The chairman shall then prepare a document showing the settlement of the claim including, when required, payment to the prime contractor, and the prime contractor's release of all claims under the contract. The prime contractor shall sign it. The executive director may approve the settlement, or may request the commission to approve the settlement by issuance of an order. The executive director shall then implement the resolution of the claim. If contemplated in the committee's decision, the executive director shall expend funds as specified in the decision. If contemplated in the committee's decision, the executive director shall order the prime contractor to make payment to the department.

      (ii) If the prime contractor objects to the committee's decision the prime contractor shall file a petition with the executive director no later than 20 days after receipt of the committee's decision requesting an administrative hearing to litigate the claim under the provisions of §§1.21 et seq. of this title (relating to Procedures in Contested Cases).

      (iii) If the prime contractor fails to file a written petition under clause (ii) of this subparagraph within 20 days of receipt of the committee's decision, the prime contractor waives his right to a contested case hearing. All further litigation of claims on the project or contract by the prime contractor shall be barred by the doctrines of issue and claim preclusion. The chairman shall then prepare an order implementing the resolution of the claim under the committee's decision, and stating that further litigation on the claim is prohibited. The executive director shall then issue the order and implement the resolution of the claim. If contemplated in the committee's decision, the executive director shall expend funds as specified in the decision. If contemplated in the committee's decision, the executive director shall order the prime contractor to make payment to the department.

  (4) Decision after contested case hearing. This paragraph applies if a contested case hearing has been held on a claim. The administrative law judge's proposal for decision shall be submitted to the executive director for adoption. The executive director may change a finding of fact or conclusion of law made by the administrative law judge or may vacate or modify an order issued by the administrative law judge. The executive director shall provide a written statement containing the reason and legal basis for any change.

  (5) This section does not abrogate the department's authority to enforce in a court of competent jurisdiction a final department order issued under the section.

(h) Claim forfeiture. A claim against the department shall be forfeited to the department by any person who corruptly practices or attempts to practice any fraud against the department in the proof, statement, establishment, or allowance thereof. In such cases the department shall specifically find such fraud or attempt and render judgment of forfeiture. This subsection applies only if there is clear and convincing evidence that a person knowingly presented a false claim for the purpose of getting paid for the claim.

(i) Relation of contract claim proceeding and sanction proceeding.

  (1) Except as provided in paragraphs (2) and (3) of this subsection, the processing of a contract claim under this section is a separate proceeding.

  (2) If a contested issue arises that is relevant both to a contract claim proceeding and a sanction proceeding concerning the same contract, the issue shall be resolved in the proceeding that the executive director refers first for a contested case hearing under Chapter 1, Subchapter E of this title (relating to Procedures in Contested Cases). If the issue is decided in the first proceeding that decision shall apply to and be binding in all subsequent department proceedings.

  (3) This paragraph applies to a contract under which the parties agreed to submit questions which may arise to the decision of a department engineer. If a dispute under the contract leads to a contract claim proceeding or sanction proceeding, the engineer's decision shall be upheld unless it was based on fraud, misconduct, or such gross mistake as would imply bad faith or failure to exercise an honest judgment.


Source Note: The provisions of this §9.2 adopted to be effective December 7, 2006, 31 TexReg 9749; amended to be effective July 19, 2007, 32 TexReg 4448; amended to be effective September 20, 2012, 37 TexReg 7299; amended to be effective September 19, 2018, 43 TexReg 5996