RULE §24.163Service Connections

  (2) Developers may be required to provide contributions in aid of construction in amounts sufficient to reimburse the utility for:

    (A) existing uncommitted facilities at their original cost if the utility has not previously been reimbursed. A utility shall not be reimbursed for facilities in excess of the amount the utility paid for the facilities. A utility is not required to allocate existing uncommitted facilities to a developer for projected development beyond a reasonable planning period; or

    (B) additional facilities compliant with the commission's minimum design criteria for facilities used in the production, transmission, pumping, or treatment of water or the commission's minimum design criteria for wastewater collection and treatment facilities and to provide for reasonable local demand requirements. Income tax liabilities which may be incurred due to collection of contributions in aid of construction may be included in extension charges to developers. Additional tax liabilities due to collection of the original tax liability may not be collected unless they can be supported and are specifically noted in the approved extension policy.

  (3) For purposes of this subsection, a developer is one who subdivides or requests more than two water service connections or sewer service connections on a single contiguous tract of land.

(d) Cost utilities and service applicants shall bear.

  (1) Within its certificated area, a utility shall be required to bear the cost of the first 200 feet of any water main or sewer collection line necessary to extend service to an individual residential service applicant within a platted subdivision unless the utility can document:

    (A) that the developer of the subdivision refused to provide facilities compatible with the utility's facilities in accordance with the utility's approved extension policy after receiving a written request from the utility; or

    (B) that the developer of the subdivision defaulted on the terms and conditions of a written agreement or contract existing between the utility and the developer regarding payment for services, extensions, or other requirements; or in the event the developer declared bankruptcy and was therefore unable to meet obligations; and

    (C) that the residential service applicant purchased the property from the developer after the developer was notified of the need to provide facilities to the utility.

  (2) A residential service applicant may be charged the remaining costs of extending service to his property; provided, however, that the residential service applicant may only be required to pay the cost equivalent to the cost of extending the nearest water main or wastewater collection line, whether or not that line has adequate capacity to serve that residential service applicant. The following criteria shall be considered to determine the residential service applicant's cost for extending service:

    (A) The residential service applicant shall not be required to pay for costs of main extensions greater than two inches in diameter for water distribution and pressure wastewater collection lines and six inches in diameter for gravity wastewater lines.

    (B) Exceptions may be granted by the commission if:

      (i) adequate service cannot be provided to the applicant using the maximum line sizes listed due to distance or elevation, in which case, it shall be the utility's burden to justify that a larger diameter pipe is required for adequate service;

      (ii) larger minimum line sizes are required under subdivision platting requirements or building codes of municipalities within whose corporate limits or extraterritorial jurisdiction the point of use is located; or

      (iii) the residential service applicant is located outside the CCN service area.

    (C) If an exception is granted, the utility must establish a proportional cost plan for the specific extension or a rebate plan which may be limited to seven years to return the portion of the applicant's costs for oversizing as new customers are added to ensure that future applicants for service on the line pay at least as much as the initial service applicant.

  (3) The utility shall bear the cost of any oversizing of water distribution lines or wastewater collection lines necessary to serve other potential service applicants or customers in the immediate area or for fire flow requirements unless an exception is granted under paragraph (2)(B) of this subsection.

  (4) For purposes of determining the costs that service applicants shall pay, commercial customers with service demands greater than residential customer demands in the certificated area, industrial, and wholesale customers may be treated as developers. A service applicant requesting a one inch meter for a lawn sprinkler system to service a residential lot is not considered nonstandard service.

(e) Other Fees for Service Applicants. Except for an affected county, utilities shall not charge membership fees or application fees.