TITLE 16ECONOMIC REGULATION
PART 2PUBLIC UTILITY COMMISSION OF TEXAS
CHAPTER 24SUBSTANTIVE RULES APPLICABLE TO WATER AND SEWER SERVICE PROVIDERS
SUBCHAPTER HCERTIFICATES OF CONVENIENCE AND NECESSITY
RULE §24.233Contents of Certificate of Convenience and Necessity Applications

    (C) the landowner or retail public utility that submitted the formal request has not unreasonably refused to:

      (i) comply with the municipality's service extension and development process; or

      (ii) enter into a contract for retail water or sewer utility service with the municipality.

  (5) If a municipality refuses to provide service in the requested area, as evidenced by a formal vote of the municipality's governing body or an official notification from the municipality, the commission is not required to make the findings otherwise required by this section and may grant the CCN to the retail public utility at any time after the date of the formal vote or receipt of the official notification.

  (6) The commission must include as a condition of a CCN granted under paragraph (4) or (5) of this subsection that all water and sewer facilities be designed and constructed in accordance with the municipality's standards for water and sewer facilities.

  (7) Paragraphs (4) - (6) of this subsection do not apply to Cameron, Hidalgo, or Willacy Counties, or to a county:

    (A) with a population of more than 30,000 and less than 35,000 that borders the Red River;

    (B) with a population of more than 100,000 and less than 200,000 that borders a county described by subparagraph (A) of this paragraph;

    (C) with a population of 130,000 or more that is adjacent to a county with a population of 1.5 million or more that is within 200 miles of an international border; or

    (D) with a population of more than 40,000 and less than 50,000 that contains a portion of the San Antonio river.

    (E) The commission will maintain on its website a list of counties that are presumed to meet the requirements of this paragraph.

  (8) A commitment by a city to provide service must, at a minimum, provide that the construction of service facilities will begin within one year and will be substantially completed within two years after the date the retail public utility's application was filed with the municipality.

  (9) If the commission makes a decision under paragraph (3) of this subsection regarding the granting of a CCN without the consent of the municipality, the municipality or the retail public utility may appeal the decision to the appropriate state district court.

(d) Extension beyond extraterritorial jurisdiction.

  (1) Except as provided by paragraph (2) of this subsection, if a municipality extends its extraterritorial jurisdiction to include an area in the certificated service area of a retail public utility, the retail public utility may continue and extend service in its certificated service area under the rights granted by its CCN and this chapter.

  (2) The commission may not extend a municipality's certificated service area beyond its extraterritorial jurisdiction if an owner of land that is located wholly or partly outside the extraterritorial jurisdiction elects to exclude some or all of the landowner's property within the requested area in accordance with TWC §13.246(h). This subsection does not apply to a sale, transfer, merger, consolidation, acquisition, lease, or rental of a CCN as approved by the commission.

  (3) Paragraph (2) of this subsection does not apply to an extension of extraterritorial jurisdiction in Cameron, Hidalgo, or Willacy Counties, or in a county:

    (A) with a population of more than 30,000 and less than 35,000 that borders the Red River;

    (B) with a population of more than 100,000 and less than 200,000 that borders a county described by subparagraph (A) of this paragraph;

    (C) with a population of 130,000 or more that is adjacent to a county with a population of 1.5 million or more that is within 200 miles of an international border; or

    (D) with a population of more than 40,000 and less than 50,000 that contains a portion of the San Antonio river.

    (E) The commission will maintain on its website a list of counties that are presumed to meet the requirements of this paragraph.

  (4) To the extent of a conflict between this subsection and TWC §13.245, TWC §13.245 prevails.

(e) Area within municipality.

  (1) If an area is within the boundaries of a municipality, any retail public utility holding or entitled to hold a CCN under this chapter to provide retail water and/or sewer utility service or operate facilities in that area may continue and extend service in its certificated service area, unless the municipality exercises its power of eminent domain to acquire the property of the retail public utility under this subsection. Except as provided by TWC §13.255, a municipally owned or operated utility may not provide retail water and sewer utility service within the certificated service area of another retail public utility without first having obtained from the commission a CCN that includes the area to be served.

  (2) This subsection may not be construed as limiting the power of municipalities to incorporate or extend their boundaries by annexation, or as prohibiting any municipality from levying taxes and other special charges for the use of the streets as are authorized by Texas Tax Code §182.025.

  (3) In addition to any other rights provided by law, a municipality with a population of more than 500,000 may exercise the power of eminent domain in the manner provided by Texas Property Code, chapter 21, to acquire a substandard water or sewer system if all the facilities of the system are located entirely within the municipality's boundaries. The municipality shall pay just and adequate compensation for the property. In this subsection, substandard water or sewer system means a system that is not in compliance with the municipality's standards for water and wastewater service.

    (A) A municipality shall notify the commission no later than seven days after filing an eminent domain lawsuit to acquire a substandard water or sewer system and also notify the commission no later than seven days after acquiring the system.

    (B) With the notification of filing its eminent domain lawsuit, the municipality, in its sole discretion, shall either request that the commission cancel the CCN of the acquired system or transfer the certificate to the municipality, and the commission shall take such requested action upon notification of acquisition of the system.


Source Note: The provisions of this §24.233 adopted to be effective October 17, 2018, 43 TexReg 6826