<<Prev Rule

Texas Administrative Code

Next Rule>>
TITLE 16ECONOMIC REGULATION
PART 2PUBLIC UTILITY COMMISSION OF TEXAS
CHAPTER 24SUBSTANTIVE RULES APPLICABLE TO WATER AND SEWER SERVICE PROVIDERS
SUBCHAPTER BRATES AND TARIFFS
RULE §24.25Form and Filing of Tariffs

      (iii) The minimal level of retail water service requested by the utility must not exceed 3,000 gallons per month per connection. Additional gallons used must be billed at the utility's tariffed rates.

      (iv) For purposes of the provision in this subparagraph, a reduced rate authorized under this section does not:

        (I) Make or grant an unreasonable preference or advantage to any corporation or person;

        (II) Subject a corporation or person to an unreasonable prejudice or disadvantage; or

        (III) Constitute an unreasonable difference as to retail water rates between classes of service.

    (C) If a utility has provided notice as required in subparagraph (F) of this paragraph, the commission may approve a pass-through provision as a minor tariff change, even if the utility has never had an approved pass-through provision in its tariff. A pass-through provision may not be approved for a charge already included in the utility's cost of service used to calculate the rates approved by the commission in the utility's most recently approved rate change under TWC §§13.187, 13.1871, 13.18715, or 13.1872. A pass-through provision may only include passing through of the actual costs charged to the utility. Only the commission staff or the utility may request a hearing on a proposed pass-through provision or a proposed revision or change to a pass-through provision. A pass-through provision may be approved as follows:

      (i) A utility that purchases water or sewage treatment and whose rates are under the original jurisdiction of the commission may include a provision in its tariff to pass through to its customers changes in such costs. The provision must specify how it is calculated.

      (ii) A utility may pass through a temporary water rate provision implemented in response to mandatory reductions in water use imposed by a court, government agency, or other authority. The provision must specify how the temporary water rate provision is calculated.

      (iii) A utility may include the addition of a production fee charged by a groundwater conservation district, including a production fee charged in accordance with a groundwater reduction plan entered in to by a utility in response to a groundwater conservation district production order or rule, as a separate line item in the tariff.

      (iv) A utility may pass through the costs of changing its source of water if the source change is required by a governmental entity. The pass-through provision may not be effective prior to the date the conversion begins. The pass-through provision must be calculated using an annual true-up provision.

      (v) A utility subject to more than one pass-through cost allowable in this section may request approval of an overall combined pass-through provision that includes all allowed pass-through costs to be recovered in one provision under subparagraph (D) of this paragraph. The twelve calendar months (true-up period) for inclusion in the true-up must remain constant, e.g., January through December.

      (vi) A utility that has a combined pass-through provision in its approved tariff may request to amend its tariff to replace the combined pass-through provision with individual pass-through provisions if all revenues and expenses have been properly trued up in a true-up report and all overcollections have been credited back to the customers. A utility that has replaced its previously approved combined pass-through provision with individual provisions may not request another combined pass-through until three years after the replacement has been approved unless good cause is shown.

    (D) A change in the combined pass-through provision may be implemented only once per year. The utility must file a true-up report within one month after the end of the true-up period. The report must reconcile both expenses and revenues related to the combined pass-through charge for the true-up period. If the true-up report reflects an over-collection from customers, the utility must change its combined pass-through rate using the confirmed rate changes to charges being passed through and the over-collection from customers reflected in the true-up report. If the true-up report does not reflect an over-collection from the customers, the implementation of a change to the pass-through rate is optional. The change may be effective in a billing cycle within three months after the end of the true-up period as long as the true-up clearly shows the reconciliation between charges by pass-through entities and collections from the customers, and charges from previous years are reconciled. Only expenses charged by the pass-through provider may be included in the provision. The true-up report must include:

      (i) a list of all entities charging fees included in the combined pass- through provision, specifying any new entities added to the combined pass-through provision;

      (ii) a summary of each charge passed through in the report year, along with documentation verifying the charge assessed and showing the amount the utility paid;

      (iii) a comparison between annual amounts billed by all entities charging fees included in the pass-through provision with amounts billed for the usage by the utility to its customers in the pass-through period;

      (iv) all calculations and supporting documentation;

      (v) a summary report, by year, for the lesser of all years prior or five years prior to the pass-through period showing the same information as in clause (iii) of this subparagraph with a reconciliation to the utility's booked numbers, if there is a difference in any year; and

      (vi) any other documentation or information requested by the commission.

    (E) For any pass-through provision granted under this section, all charges approved for recovery of pass-through costs must be stated separately from all charges by the utility to recover the revenue requirement. Except for a combined pass-through provision, the calculation for a pass-through gallonage rate for a utility with one source of water may be made using the following equation, which is provided as an example: R=G /(1-L), where R is the utility's new proposed pass-through rate, G equals the new gallonage charge by source supplier or conservation district, and L equals the actual line loss reflected as a percentage expressed in decimal format (for example, 8.5% would be expressed as 0.085). Line loss will be considered on a case-by-case basis.

    (F) A utility that requests to revise or implement an approved pass-through provision must take the following actions prior to the beginning of the billing period in which the revision takes effect:

      (i) file a written notice with the commission that must include:

        (I) each affected CCN number;

        (II) a list of each affected subdivision public water system (including name and corresponding number issued by the TCEQ), and water quality system (including name and corresponding number issued by the TCEQ), if applicable;

        (III) a copy of the notice to the customers;

        (IV) documentation supporting the stated amounts of any new or modified pass-through costs;

        (V) historical documentation of line loss for one year;

        (VI) all calculations and assumptions for any true-up of pass-through costs;

        (VII) the calculations and assumptions used to determine the new rates; and

        (VIII) a copy of the pages of the utility's tariff that contain the rates that will change if the utility's application is approved; and

      (ii) e-mail (if the customer has agreed to receive communications electronically), mail, or hand-deliver notice to the utility's customers. Notice may be in the form of a billing insert and must contain:

        (I) the effective date of the change;

        (II) the present calculation of customer billings;

        (III) the new calculation of customer billings;

        (IV) an explanation of any corrections to the pass-through formula, if applicable;

        (V) the change in charges to the utility for purchased water or sewer treatment or ground water reduction fee or subsidence, if applicable; and

        (VI) the following language: "This tariff change is being implemented in accordance with the minor tariff changes allowed by 16 Texas Administrative Code §24.25. The cost to you as a result of this change will not exceed the costs charged to your utility."

    (G) The following provisions apply to surcharges:

      (i) A surcharge is an authorized rate to collect revenues over and above the usual cost of service.

      (ii) If authorized by the commission or the municipality exercising original jurisdiction over the utility, a surcharge to recover the actual increase in costs to the utility may be collected over a specifically authorized time period without being listed on the approved tariff for:

        (I) sampling fees not already recovered by rates;

Cont'd...

Next Page Previous Page

Link to Texas Secretary of State Home Page | link to Texas Register home page | link to Texas Administrative Code home page | link to Open Meetings home page