RULE §24.245Revocation of a Certificate of Convenience and Necessity or Amendment of a Certificate of Convenience and Necessity by Decertification, Expedited Release, or Streamlined Expedited Release

      (i) has refused to provide service;

      (ii) cannot provide service as identified in the request for service provided under paragraph (5) of this subsection on a continuous and adequate basis; or

      (iii) conditions the provision of service on the payment of costs not properly allocable directly to the landowner's service request, as determined by the commission.

  (2) An owner of a tract of land may not file a petition under paragraph (1) of this subsection if the landowner's property is located in the boundaries of any municipality or the extraterritorial jurisdiction of a municipality with a population of more than 500,000 and the municipality or retail public utility owned by the municipality is the current CCN holder.

  (3) The landowner's desired alternate retail public utility must be:

    (A) an existing retail public utility; or

    (B) a district proposed to be created under article 16, §59 or article 3, §52 of the Texas Constitution.

  (4) The fact that a current CCN holder is a borrower under a federal loan program does not prohibit the filing of a petition under this subsection or authorizing an alternate retail public utility to provide service to the removed area.

  (5) The landowner must submit to the current CCN holder a written request for service. The request must be sent by certified mail, return receipt requested, or by hand delivery with written acknowledgement of receipt. For a request other than for standard residential or commercial service, the written request must identify the following:

    (A) the tract of land or portion of the tract of land for which service is sought;

    (B) the time frame within which service is needed for current and projected service demands in the tract of land;

    (C) the reasonable level and manner of service needed for current and projected service demands in the area;

    (D) the approximate cost for the alternate retail public utility to provide service at the same level, and in the same manner, that is requested from the current CCN holder;

    (E) the flow and pressure requirements and specific infrastructure needs, including line size and system capacity for the required level of fire protection requested, if any; and

    (F) any additional information requested by the current CCN holder that is reasonably related to determining the capacity or cost of providing service at the level, in the manner, and in the time frame, requested.

  (6) The landowner's petition for expedited release under this subsection must be verified by a notarized affidavit and demonstrate that the circumstances identified in paragraph (1) of this subsection exist. The petition must include the following:

    (A) the name of the alternate retail public utility;

    (B) a copy of the request for service submitted as required by paragraph (5) of this subsection;

    (C) a copy of the current CCN holder's response to the request for service, if any;

    (D) copies of deeds demonstrating ownership of the tract of land by the landowner; and

    (E) the mapping information described in subsection (k) of this section.

  (7) The landowner must mail a copy of the petition to the current CCN holder and the alternate retail public utility via certified mail on the day that the landowner files the petition with the commission.

  (8) The presiding officer will determine whether the petition is administratively complete. If the petition is determined not to be administratively complete, the presiding officer will issue an order describing the deficiencies in the petition and setting a deadline for the petitioner to address the deficiencies. When the petition is determined to be administratively complete, the presiding officer will establish a procedural schedule that is consistent with paragraphs (9) and (10) of this subsection. The presiding officer may recommend dismissal of the petition under §22.181(d) of this title if the petitioner fails to supplement or amend the petition within the required timeframe after the presiding officer has determined that the petition is not administratively complete.

  (9) The current CCN holder may file a response to the petition within a timeframe specified by the presiding officer, not to exceed 20 days from the date the petition is determined to be administratively complete. The response must be verified by a notarized affidavit.

  (10) The commission will grant the petition within 60 calendar days from the date the petition was found to be administratively complete unless the commission makes an express finding that the landowner failed to satisfy all of the requirements of this subsection and makes separate findings of fact and conclusions of law for each requirement based solely on the information provided by the landowner and the current CCN holder. The commission may condition the granting or denial of a petition on terms and conditions specifically related to the landowner's service request and all relevant information submitted by the landowner, the current CCN holder, and commission staff.

  (11) The commission will base its decision on the filings submitted by the current CCN holder, the landowner, and commission staff. Chapter 2001 of the Texas Government Code does not apply to any petition filed under this subsection. The current CCN holder or landowner may file a motion for rehearing of the commission's decision on the same timeline that applies to other final orders of the commission. The commission's order ruling on the petition may not be appealed.

  (12) If the current CCN holder has never made service available through planning, design, construction of facilities, or contractual obligations to provide service to the tract of land, the commission is not required to find that the alternate retail public utility can provide better service than the current CCN holder, but only that the alternate retail public utility can provide the requested service. This paragraph does not apply to Cameron, Willacy, and Hidalgo Counties or to a county that meets any of the following criteria:

    (A) the county has a population of more than 30,000 and less than 35,000 and borders the Red River;

    (B) the county has a population of more than 100,000 and less than 200,000 and borders a county described by subparagraph (A) of this paragraph;

    (C) the county has a population of 130,000 or more and is adjacent to a county with a population of 1.5 million or more that is within 200 miles of an international border; or

    (D) the county has a population of more than 40,000 and less than 50,000 and contains a portion of the San Antonio River.

  (13) If the alternate retail public utility is a proposed district, then the commission will condition the release of the tract of land and required CCN amendment or revocation on the final and unappealable creation of the district. The district must file a written notice with the commission when the creation is complete and provide a copy of the final order, judgment, or other document creating the district.

  (14) The commission may require an award of compensation to the former CCN holder under subsection (g) of this section. The determination of the amount of compensation, if any, will be made according to the procedures in subsection (g) of this section.

(g) Determination of compensation to former CCN holder after revocation, decertification amendment or expedited release. The determination of the monetary amount of compensation to be paid to the former CCN holder, if any, will be determined at the time another retail public utility seeks to provide service in the removed area and before service is actually provided. This subsection does not apply to revocations or decertification amendments under paragraph (d)(2) of this section or to streamlined expedited release under subsection (h) of this section.

  (1) After the commission has issued its order granting revocation, decertification, or expedited release, the prospective retail public utility must file a notice of intent to provide service. A notice of intent filed before the commission issues its order under subsection (d) or (f) of this section is deemed to be filed on the date the commission's order is signed.

  (2) The notice of intent must include the following information:

    (A) a statement that the filing is a notice of intent to provide service to an area that has been removed from a CCN under subsection (d) or (f) of this section;

    (B) the name and CCN number of the former CCN holder; and

Cont'd...