RULE §293.44Special Considerations

    (B) Districts may fund the costs of bridge and culvert crossings needed to accommodate the development's road system that are larger than those specified in subparagraph (A) of this paragraph, which cross channels other than natural waterways with defined bed and banks and are necessary as a result of required channel improvements subject to the following limitations:

      (i) the drainage channel construction or renovation must benefit property within the district's boundaries;

      (ii) the costs shall not exceed a pro rata share based on the percent of total drainage area of the channel crossed, measured at the point of crossing, calculated by taking the total cost of such bridge or culvert crossing multiplied by a fraction, the numerator of which is the total drainage area located within the district upstream of the crossing, and the denominator of which is the total drainage area upstream of the crossing; and

      (iii) the district shall be responsible for not more than 50% of the pro rata share as calculated under this subsection, subject to the developer's 30% contribution as may be required by §293.47 of this title.

    (C) The cost of replacement of existing bridges and culverts not constructed or installed by the developer, or the cost of new bridges and culverts across existing roads not financed or constructed by the developer, may be financed by the district, except that any costs of increasing the traffic-carrying capacity of bridges or culverts shall not be financed by the district.

  (14) In evaluating district construction projects, including those described in paragraphs (1) - (12) of this subsection, primary consideration shall be given to engineering feasibility and whether the project has been designed in accordance with good engineering practices, regardless of other acceptable or less costly engineering alternatives that may exist.

  (15) Bond issue proceeds will not be used to pay or reimburse consultant fees for the following:

    (A) special or investigative reports for projects which, for any reason, have not been constructed and, in all probability, will not be constructed;

    (B) fees for bond issue reports for bond issues consisting primarily of developer reimbursables and approved by the commission but which are no longer proposed to be issued;

    (C) fees for completed projects which are not and will not be of benefit to the district; or

    (D) provided, however, that the limitations shall not apply to regional projects or special or investigative reports necessary to properly evaluate the feasibility of alternative district projects.

  (16) Bond funds may be used to finance costs and expenses necessarily incurred in the creation and organization of the district and the operation of the district as follows.

    (A) Creation and organization expenses were incurred or projected to incur during the creation and organization period. Operational expenses were incurred or projected to incur during construction periods which include periods during which the district is constructing its facilities or there is construction by third parties of aboveground improvements within the district.

    (B) Creation and organization expenses are expenses incurred through the date of the canvassing of the confirmation election.

    (C) Construction periods do not need to be continuous; however, once reimbursement for a specific time period has occurred, operational expenses for a prior time period are no longer eligible. Payment of operational expenses during construction periods is limited to five years in any single bond issue.

    (D) Any reimbursement to a developer of operational expenses with bond funds is restricted to actual operational expenses paid by the district during the same five-year period for which application is made in accordance with this subsection.

    (E) The district may pay interest on the expenses under this paragraph. Section 293.50 of this title (relating to Developer Interest Reimbursement) applies to interest payments for a developer and such payments are subject to a developer reimbursement audit.

  (17) In instances where creation costs to be paid from bond proceeds are determined to be excessive, the executive director may request that the developer submit invoices and cancelled checks to determine whether such creation costs were reasonable, customary, and necessary for district creation purposes. Such creation costs shall not include planning, platting, zoning, other costs prohibited by paragraphs (10) and (14) of this subsection, and other matters not directly related to the district's water, wastewater, and drainage system, even if required for city consent.

  (18) The district shall not purchase, pay for, or reimburse the cost of facilities, either completed or incomplete, from which it has not and will not receive benefit, even though such facilities may have been at one time required by a city or other entity having jurisdiction.

  (19) The district shall not enter into any binding contracts with a developer that compel the district to become liable for costs above those approved by the commission.

  (20) A district shall not purchase more water supply or wastewater treatment capacity than is needed to meet the foreseeable capacity demands of the district, except in circumstances where:

    (A) lease payments or capital contributions are required to be made to entities owning or constructing regional water supply or wastewater treatment facilities to serve the district and others;

    (B) such purchases or leases are necessary to meet minimum regulatory standards; or

    (C) such purchases or leases are justified by considerations of economic or engineering feasibility.

  (21) The district may finance those costs, including mitigation, associated with flood plain regulation and wetlands regulation, attributable to the development of water plants, wastewater treatment plants, pump and lift stations, detention/retention facilities, drainage channels, and levees. The district's share shall not be subject to the developer's 30% contribution as may be required by §293.47 of this title.

  (22) The district may finance those costs associated with endangered species permits. Such costs shall be shared between the district and the developer with the district's share not to exceed 70% of the total costs, unless unusual circumstances are present as determined by the commission. The district's share shall not be subject to the developer's 30% contribution under §293.47 of this title. For purposes of this paragraph, "endangered species permit" means a permit or other authorization issued under §7 or §10(a) of the federal Endangered Species Act of 1973, 16 United States Code, §1536 and §1539(a).

  (23) The district may finance 100% of those costs associated with federal storm water permits. The district's share shall be subject to the developer's 30% contribution as may be required by §293.47 of this title. For purposes of this paragraph, "federal storm water permit" means a permit for storm water discharges issued under the federal Clean Water Act, including National Pollutant Discharge Elimination System permits issued by the United States Environmental Protection Agency and Texas Pollutant Discharge Elimination System permits issued by the commission.

  (24) The district may finance the portion of an amenity lake project that is considered a recreational facility.

    (A) The portion considered a recreational facility must be accessible to all persons within the district and is determined as:

      (i) the percentage of shoreline with at least a 30-foot wide buffer between the shoreline and private property; or

      (ii) the percentage of the perimeter of a high bank of a combination detention facility and lake with at least a 30-foot wide buffer between the high bank and private property.

    (B) The district's share of costs for the portion of an amenity lake project that is considered a recreational facility is not subject to the developer's 30% contribution under §293.47 of this title.

    (C) The authority for districts to fund recreational amenity lake costs in accordance with this paragraph does not apply retroactively to projects included in bond issues submitted to the commission prior to the effective date of this paragraph.

(b) All projects.

  (1) The purchase price for existing facilities not covered by a preconstruction agreement or otherwise not constructed by a developer in contemplation of resale to the district, or if constructed by a developer in contemplation of resale to the district and the cost of the facilities is not available after demonstrating a good faith effort to locate the cost records should be established by an independent appraisal by a licensed professional engineer hired by the district. The appraised value should reflect the cost of replacement of the facility, less repairs and depreciation, taking into account the age and useful life of the facility and Cont'd...