TITLE 30ENVIRONMENTAL QUALITY
PART 1TEXAS COMMISSION ON ENVIRONMENTAL QUALITY
CHAPTER 331UNDERGROUND INJECTION CONTROL
SUBCHAPTER DSTANDARDS FOR CLASS I WELLS OTHER THAN SALT CAVERN DISPOSAL WELLS
RULE §331.64Monitoring and Testing Requirements

  (2) When the executive director determines that an injection well lacks mechanical integrity pursuant to paragraph (4) of this subsection, the executive director shall give written notice of his determination to the owner or operator. Unless the executive director requires immediate cessation, the owner or operator shall cease injection into the well within 48 hours of receipt of the executive director's determination. The executive director may allow plugging of the well in accordance with the requirements of §331.46 of this title (relating to Closure Standards) or require the owner or operator to perform such additional construction, operation, monitoring, reporting and corrective action as is necessary to prevent the movement of fluid into or between USDWs caused by the lack of mechanical integrity. The owner or operator may resume injection upon receipt of written notification from the executive director that the owner or operator has demonstrated mechanical integrity under paragraph (4) of this subsection.

  (3) The executive director may allow the owner or operator of a well which lacks mechanical integrity under paragraph (4) of this subsection to continue or resume injection if the owner or operator has made a satisfactory demonstration that there is no movement of fluid into or between USDWs.

  (4) Mechanical Integrity Testing. An injection well has mechanical integrity if:

    (A) There is no significant leak in the casing, tubing or packer; and

    (B) There is no significant fluid movement into an USDW through vertical channels adjacent to the injection well bore.

  (5) One of the following methods shall be used to evaluate the absence of significant leaks under paragraph (4)(A) of this subsection:

    (A) Following an initial pressure test, monitoring of the tubing-casing annulus pressure with sufficient frequency to be representative, as determined by the executive director, while maintaining an annulus pressure different from atmospheric pressure measured at the surface; or

    (B) Pressure test with liquid or gas.

  (6) The results of a temperature or noise log must be used to determine the absence of significant fluid movement under paragraph (4)(B) of this subsection.

  (7) The executive director may allow the use of a test to demonstrate mechanical integrity other than those listed in paragraph (5)(A) and (B) of this subsection with the written approval of the executive director. To obtain approval, the permittee shall submit a written request to the executive director, which shall set forth the proposed test and all technical data supporting its use. The executive director shall approve the request if it will reliably demonstrate the mechanical integrity of wells for which its use is proposed.

  (8) In conducting and evaluating the tests enumerated in this section or others to be allowed by the executive director, the owner or operator and the executive director shall apply methods and standards generally accepted in the industry. When the owner or operator reports the results of mechanical integrity tests to the executive director, he shall include a description of the test(s) and the method(s) used. In making his evaluation, the executive director shall review monitoring and other test data submitted since the previous evaluation.

  (9) The executive director may require additional or alternative tests if the results presented by the owner or operator under §331.64(k)(5) of this title (relating to Monitoring and Testing Requirements) are not satisfactory to the executive director to demonstrate that there is no movement of fluid into or between USDWs resulting from the injection activity.

  (10) Ambient monitoring.

    (A) Based on a site-specific assessment of the potential for fluid movement from the well or injection zone and on the potential value of monitoring wells to detect such movement, the executive director shall require the owner or operator to develop a monitoring program. At a minimum, the executive director shall require monitoring of the pressure buildup in the injection zone annually, including a shut down of the well for a time sufficient to conduct a valid observation of the pressure fall-off curve.

    (B) When prescribing a monitoring system the executive director may also require:

      (i) Continuous monitoring for pressure changes in the first aquifer overlying the confining zone. When such a well is installed, the owner or operator shall, on a quarterly basis, sample the aquifer and analyze for constituents specified by the executive director;

      (ii) The use of indirect, geophysical techniques to determine the position of the waste front, the water quality in a formation designated by the executive director, or to provide other site-specific data;

      (iii) Periodic monitoring of the ground water quality in the first aquifer overlying the injection zone;

      (iv) Periodic monitoring of the ground water quality in the lowermost USDW; and

      (v) Any additional monitoring necessary to determine whether fluids are moving into or between USDWs.


Source Note: The provisions of this §331.64 adopted to be effective May 13, 1986, 11 TexReg 1983; amended to be effective July 5, 1989, 14 TexReg 3047; amended to be effective January 2, 1995, 19 TexReg 10099; amended to be effective April 28, 1997, 22 TexReg 3526; amended to be effective July 10, 2008, 33 TexReg 5342; amended to be effective January 7, 2021, 46 TexReg 191

Previous Page

Link to Texas Secretary of State Home Page | link to Texas Register home page | link to Texas Administrative Code home page | link to Open Meetings home page