TITLE 16ECONOMIC REGULATION
PART 2PUBLIC UTILITY COMMISSION OF TEXAS
CHAPTER 25SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS
SUBCHAPTER ITRANSMISSION AND DISTRIBUTION
DIVISION 2TRANSMISSION AND DISTRIBUTION APPLICABLE TO ALL ELECTRIC UTILITIES
RULE §25.218Middle Mile Broadband Service

        (XIII) a link or website address for the commission website for public participation.

      (iii) State whether any new fiber optic cables used for middle mile broadband service will be located above or below ground in the easement or other property right.

    (B) Notice to the following persons or entities must be sent by first class mail to the last known address of the person or entity or by electronic service:

      (i) all parties in the electric utility's last comprehensive base-rate proceeding;

      (ii) property owners whose property is listed on the most recent tax roll of each county authorized to levy property taxes against the property and whose real property is burdened by an existing easement, right-of-way or other property right that permits the provision of third-party middle mile broadband service on an electric utility delivery system;

      (iii) the Office of Public Utility Counsel; and

      (iv) municipalities crossed by or within five miles of the planned project and counties that are crossed by the planned project.

    (C) Notice to the parties described under subparagraph (B) of this paragraph must conspicuously state in plain language:

      (i) that the electric utility has determined the recipient is not an affected property owner as defined under Chapter 16, Texas Administrative Code §25.218(b)(1), that the mailing is a notice of intent to use the utility's easement for implementation of middle mile broadband service, and that the electric utility's determination may be challenged in the docket listed in the notice if the person or entity files a motion to intervene in the proceeding and that motion to intervene is granted by the presiding officer;

      (ii) the intervention deadline in accordance with subparagraph (E) of this paragraph; and

      (iii) a link or website address for the commission website for public participation.

    (D) The electric utility must file a notice of written middle mile broadband plan proceeding and must include in the notice the docket number for the proceeding. The commission will designate a project number for the filing of notice of plans under this section. This filing serves as notice to all other interested parties.

    (E) The intervention deadline is 45 days from the date the utility files its notice of written middle mile broadband plan proceeding in accordance with subparagraph (D) of this paragraph. The lapse of the intervention deadline does not prevent an affected property owner from submitting a written protest under subparagraph (F) of this paragraph.

    (F) Protest by affected property owner.

      (i) Not later than the 60th day after the postmarked date an electric utility mails notice to affected property owners in accordance with subparagraph (A) of this paragraph, an affected property owner may submit to the electric utility a written protest of the intended use of the easement or other property right for middle mile broadband service by filing the protest with the commission in the docket assigned to the middle mile broadband plan proceeding. For purposes of this section, an electric utility is deemed to have received a written protest filed with the commission in the appropriate docket number.

      (ii) If an electric utility receives a written protest directly from an affected property owner, the electric utility must file the protest with the commission within three working days of receipt.

      (iii) An electric utility that receives a timely written protest from an affected property owner must not use the easement or other property right for middle mile broadband service unless that use is authorized by law or the protester later retracts its protest or agrees in writing to that use.

      (iv) An electric utility that receives a timely written protest from an affected property owner regarding the proposed middle mile broadband plan may cancel the project at any time.

      (v) An electric utility that receives any timely written protests must file an update with the commission that any applicable protests have been resolved in accordance with clause (iii) of this subparagraph before implementing its middle mile broadband plan.

      (vi) If an affected property owner fails to submit a timely written protest, an electric utility may proceed with a commission-approved plan to provide middle mile broadband service without modifying or expanding the easement for the property owner.

  (3) Commission processing of electric utility's plan.

    (A) The commission must approve, modify, or reject an electric utility's middle mile broadband plan submitted to the commission under this section not later than the 181st day after the date all information necessary for the plan to be deemed materially sufficient was filed.

    (B) Following the filing of a plan by an electric utility under this section, the commission may review the electric utility's plan for middle mile broadband service under subsection (f) of this section or refer the application to the State Office of Administrative Hearings (SOAH). Upon referral to SOAH:

      (i) The commission delegates authority to the presiding officer to deem plans sufficient, approve plans, and modify approved plans filed under this subsection through a notice of approval under §22.35(b)(1) (relating to Informal Disposition) of this title.

      (ii) The presiding officer will review for sufficiency the electric utility's plan for middle mile broadband service under paragraph (1) of this subsection and notice to potential intervenors under paragraph (2) of this subsection.

      (iii) The presiding officer must establish a procedural schedule that will enable the commission to, approve, modify, or reject the plan not later than the 181st day after the date all information necessary for the plan to be deemed materially sufficient was filed.

    (C) A motion to find a plan filing materially deficient must be filed no later than seven days after the intervention deadline. The motion must specify the nature of the deficiency, the relevant portions of the plan, and cite the particular requirement under paragraph (1) of this subsection with which the plan is alleged not to comply. The electric utility's response to a motion to find a plan materially deficient must be filed no later than five working days after such motion is received.

    (D) An approved plan may be updated or amended subject to commission approval in accordance with this subsection.

(g) Cost recovery for deployment of middle mile broadband facilities.

  (1) An electric utility's investment in facilities installed by that electric utility to provide middle mile broadband service under a plan approved by the commission under this section is eligible for inclusion in the electric utility's invested capital.

  (2) In a proceeding under PURA Chapter 36, revenue received by an electric utility from an internet service provider for the use of middle mile broadband service must be applied as a revenue credit to customers in proportion to the customers' funding of the underlying infrastructure. For purposes of this paragraph, the term ‘customers’ refers to ‘rate classes.’

  (3) An electric utility submitting a plan must ensure that revenues received by the electric utility from the provision of middle mile broadband service offset all costs directly attributable to the middle mile broadband service, including but not limited to, construction, maintenance, operations, taxes, other costs, and return.

  (4) If revenues received by an electric utility from an internet service provider for the use of middle mile broadband service are insufficient to offset the costs under paragraph (3) of this subsection, the utility must ensure that its regulated rates prevent ratepayer cross-subsidization.

(h) Reliability of electric systems maintained.

  (1) An electric utility that installs and operates facilities to provide middle mile broadband service must employ all reasonable measures to ensure that the operation of the middle mile broadband service does not interfere with or diminish the reliability of the electric utility's electric delivery system.

  (2) If a disruption in the provision of electric service occurs, the electric utility is governed by the terms and conditions of the retail electric delivery service tariff.

  (3) The electric utility may take all necessary actions regarding its middle mile broadband service and the facilities required in the provision of that service to address circumstances that may pose health, safety, security, or reliability concerns.

  (4) At all times, the provision of broadband service is secondary to the reliable provision of electric delivery services.

  (5) Except as provided by contract or tariff, an electric utility is not liable to any person, including an internet service provider, for any damages, including direct, indirect, physical, economic, exemplary, or consequential damages, including loss of business, loss of profits or revenue, or loss of production capacity caused by a fluctuation, disruption, or interruption of middle mile broadband service that is caused in whole or in part by:

    (A) force majeure; or

    (B) the electric utility's provision of electric delivery services, including actions taken by the electric utility to ensure the reliability and security of the electric delivery system and actions taken in response to address all circumstances that may pose health, safety, security, or reliability concerns.


Source Note: The provisions of this §25.218 adopted to be effective April 21, 2022, 47 TexReg 1993