TITLE 16ECONOMIC REGULATION
PART 2PUBLIC UTILITY COMMISSION OF TEXAS
CHAPTER 25SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS
SUBCHAPTER ITRANSMISSION AND DISTRIBUTION
DIVISION 2TRANSMISSION AND DISTRIBUTION APPLICABLE TO ALL ELECTRIC UTILITIES
RULE §25.218Middle Mile Broadband Service

    (L) a demonstration that the revenues received from the provision of middle mile broadband service under the plan offset all costs directly attributable to the middle mile broadband service, including but not limited to, construction, maintenance, operations, taxes, other costs, and return;

    (M) testimony, exhibits, and other evidence that demonstrate the project will allow for the provision and maintenance of middle mile broadband service to unserved and underserved areas with a sworn statement attesting compliance with subsection (e) of this section;

    (N) unless otherwise specified, testimony, exhibits, or other evidence that fully support the information required by subparagraphs (A) - (M) of this paragraph; and

    (O) any other information that the applicant considers relevant.

  (2) Notice and intervention deadline. On or before the day after an electric utility files its plan, the electric utility must provide notice in accordance with this paragraph. The notice must include the docket number assigned to the electric utility's filed written plan. Within 10 days of the date service of notice is completed, an electric utility must file, in the docket assigned to its written plan, proof of notice to the persons or entities specified under subparagraphs (A) and (B) of this paragraph and a list of such parties by name specifying whether the person or entity qualifies as an affected property owner under subsection (b)(1) of this section. Failure by an electric utility to provide timely notice, as determined by the presiding officer, will toll the intervention deadline under subparagraph (E) of this paragraph until the date timely notice is issued. Affected property owners automatically qualify as intervenors for proceedings under this section.

    (A) Notice to affected property owners under this section must:

      (i) Be sent by first class mail to the last known address of each affected property owner whose property is listed on the most recent tax roll of each county authorized to levy property taxes against the property and, if available, by electronic service.

      (ii) Conspicuously state in plain language:

        (I) that the electric utility has determined the recipient is an affected property owner as defined under 16 Texas Administrative Code §25.218(b)(1) and that the mailing is a notice of intent to use the utility's easement for middle mile broadband implementation;

        (II) the recipient's status as an affected property owner means the utility's easement or other property right planned by the utility for the provision of third-party middle mile broadband service does not include language permitting middle mile broadband service;

        (III) that under PURA Chapter 43 and 16 Texas Administrative Code §25.218, a utility may implement middle mile broadband service without modifying or expanding the easement if the affected property owner does not submit a timely written protest;

        (IV) that a written protest may be submitted electronically in the docket for the middle mile broadband proceeding using the interchange on the commission's website or mailed with reference to the docket to Commission's Filing Clerk, Public Utility Commission of Texas, 1701 North Congress Avenue, P.O. Box 13326, Austin, Texas 78711-3326;

        (V) the project number for the filing of notice of written plans and the docket number for utility's specific middle mile broadband plan;

        (VI) that a written protest can be filed for any reason;

        (VII) that a written protest is considered timely if submitted not later than the 60th day from the postmarked date of the notice;

        (VIII) that a submitted written protest can be retracted at any time by the recipient through a mailed or electronic filing with the commission in the specified docket, or resolved by written agreement with the electric utility;

        (IX) that other legal authorization could override the written protest;

        (X) an estimated schedule for construction with a statement that the schedule is subject to change;

        (XI) the recipient qualifies as an intervenor and may seek to intervene in the docket, and that intervention is not the same as a written protest;

        (XII) specify the intervention deadline in accordance with subparagraph (E) of this paragraph; and

        (XIII) a link or website address for the commission website for public participation.

      (iii) State whether any new fiber optic cables used for middle mile broadband service will be located above or below ground in the easement or other property right.

    (B) Notice to the following persons or entities must be sent by first class mail to the last known address of the person or entity or by electronic service:

      (i) all parties in the electric utility's last comprehensive base-rate proceeding;

      (ii) property owners whose property is listed on the most recent tax roll of each county authorized to levy property taxes against the property and whose real property is burdened by an existing easement, right-of-way or other property right that permits the provision of third-party middle mile broadband service on an electric utility delivery system;

      (iii) the Office of Public Utility Counsel; and

      (iv) municipalities crossed by or within five miles of the planned project and counties that are crossed by the planned project.

    (C) Notice to the parties described under subparagraph (B) of this paragraph must conspicuously state in plain language:

      (i) that the electric utility has determined the recipient is not an affected property owner as defined under Chapter 16, Texas Administrative Code §25.218(b)(1), that the mailing is a notice of intent to use the utility's easement for implementation of middle mile broadband service, and that the electric utility's determination may be challenged in the docket listed in the notice if the person or entity files a motion to intervene in the proceeding and that motion to intervene is granted by the presiding officer;

      (ii) the intervention deadline in accordance with subparagraph (E) of this paragraph; and

      (iii) a link or website address for the commission website for public participation.

    (D) The electric utility must file a notice of written middle mile broadband plan proceeding and must include in the notice the docket number for the proceeding. The commission will designate a project number for the filing of notice of plans under this section. This filing serves as notice to all other interested parties.

    (E) The intervention deadline is 45 days from the date the utility files its notice of written middle mile broadband plan proceeding in accordance with subparagraph (D) of this paragraph. The lapse of the intervention deadline does not prevent an affected property owner from submitting a written protest under subparagraph (F) of this paragraph.

    (F) Protest by affected property owner.

      (i) Not later than the 60th day after the postmarked date an electric utility mails notice to affected property owners in accordance with subparagraph (A) of this paragraph, an affected property owner may submit to the electric utility a written protest of the intended use of the easement or other property right for middle mile broadband service by filing the protest with the commission in the docket assigned to the middle mile broadband plan proceeding. For purposes of this section, an electric utility is deemed to have received a written protest filed with the commission in the appropriate docket number.

      (ii) If an electric utility receives a written protest directly from an affected property owner, the electric utility must file the protest with the commission within three working days of receipt.

      (iii) An electric utility that receives a timely written protest from an affected property owner must not use the easement or other property right for middle mile broadband service unless that use is authorized by law or the protester later retracts its protest or agrees in writing to that use.

      (iv) An electric utility that receives a timely written protest from an affected property owner regarding the proposed middle mile broadband plan may cancel the project at any time.

      (v) An electric utility that receives any timely written protests must file an update with the commission that any applicable protests have been resolved in accordance with clause (iii) of this subparagraph before implementing its middle mile broadband plan.

      (vi) If an affected property owner fails to submit a timely written protest, an electric utility may proceed with a commission-approved plan to provide middle mile broadband service without modifying or expanding the easement for the property owner.

  (3) Commission processing of electric utility's plan.

Cont'd...