<<Prev Rule

Texas Administrative Code

Next Rule>>
TITLE 43TRANSPORTATION
PART 1TEXAS DEPARTMENT OF TRANSPORTATION
CHAPTER 21RIGHT OF WAY
SUBCHAPTER CUTILITY ACCOMMODATION
RULE §21.40Underground Utilities

    (J) When trenching longitudinally, backfill or stabilized sand shall be compacted to densities equal to that of the surrounding soil. Compaction must meet all requirements listed in Item 400, relating to excavation and backfill structures, of the department's publication, Standard Specification for Construction and Maintenance of Highways, Streets, and Bridges.

    (K) Longitudinal installations shall be in uniform alignment with the department's right of way and as near as practical to the edge of the department's right of way line. Consideration shall be given to allow safe clearance from adjacent installations.

    (L) An additional 12 inches of depth are required for installations within 50 feet of waterways, ditches, channels, creeks, or culverts.

    (M) As assigned corridors within the department's right of way are finite at particular depths, the district may require the placement of a utility facility below other facilities at necessary clearances. The district may require encasements to allow the repair or replacement of the utility facility without disturbing adjacent utility facilities.

  (5) Nonmetallic pipe detection. Where nonmetallic pipe is installed, whether longitudinally or at a crossing, a durable metal wire or other district-approved means of detection shall be concurrently installed.

  (6) Unsuitable conditions. The following conditions are generally unsuitable or undesirable for pipeline crossings and shall be avoided:

    (A) deep cuts;

    (B) locations near footings or bridges and retaining walls;

    (C) crossing intersections at-grade or ramp terminals;

    (D) locations at cross-drains where the flow of water may be obstructed;

    (E) locations within basins or underpasses drained by pump if the pipeline carries a liquid or liquefied gas; or

    (F) terrain where minimum depth of cover would be difficult to attain.

  (7) Clearances. Except as specified in this subchapter, there shall be a minimum of 12 inches vertical and horizontal clearance between a new utility facility and an existing utility facility, unless a greater clearance is required by the district. However, if an installation of another utility facility or highway feature cannot take place without disturbing an existing utility facility, the district may require a minimum clearance of 24 inches.

  (8) Drainage easements. Where it is necessary for pipelines to cross department drainage easements outside of the right of way, the depth of cover shall be as specified for each type of utility facility. In cases where soil conditions are such that erosion might occur, or where it is not feasible to obtain specified depth, it shall be the responsibility of the utility to install retards, energy dissipators, encasement, or concrete or equivalent slabs/caps over the pipe, as approved by the department. Where grades on the pipelines must be maintained, such as gravity flow sewer lines, each case will be reviewed on an individual basis. The main purpose of the department's drainage easement is to carry drainage water and the drainage may not be obstructed. The utility is responsible for obtaining any other approvals or rights required to occupy the drainage easement.

  (9) Existing installations in a highway or transportation project. At the district's discretion, existing longitudinal utility facilities in a highway or transportation project that otherwise meet the requirements of this subchapter may remain in place if the utility facilities:

    (A) can be maintained in accordance with §21.37(b)(2) of this subchapter (relating to Design); and

    (B) are not located under the pavement structure or shoulder of any proposed or existing highway.

  (10) Markers. If a high pressure pipeline crosses a highway, the utility shall place a readily identifiable, durable, and weatherproof marker over the centerline of the pipe at each right of way line. Readily identifiable, durable, and weatherproof markers shall be placed at a minimum distance of 500 feet apart or line of sight at the right of way line for pipelines installed longitudinally within the right of way. All markers shall indicate the name, address, emergency telephone number of the utility, and offset from the right of way line for longitudinal placement. For gas, petroleum, or saltwater pipelines, the pipeline product, operating pressure, and depth of pipe below grade shall also be indicated on the markers. At locations where underground utility facilities have been allowed to cross at an angle other than 90 degrees to centerline, the district may require additional markers in the medians and outer separations of the highway.

(b) Gas and liquid petroleum pipelines and saltwater pipelines.

  (1) Low-pressure pipelines.

    (A) Depth of cover for crossings. Depth of cover is the depth to the top of the encasement, or the carrier pipe if encasement is not used. Where materials and other conditions justify, such as on existing pipelines remaining in place, the district may require a minimum depth of cover under the pavement structure of 12 inches or one-half the diameter of the pipe, whichever is greater.

      (i) For encased low-pressure gas pipelines, the minimum depth of cover is:

        (I) 60 inches or one-half the diameter of the pipe, whichever is greater, below the lowest point of the crossed grade; or

        (II) 48 inches if the pipeline is outside of the pavement structure or 60 inches under ditches (original unsilted flowline).

      (ii) For unencased low-pressure gas pipelines, the minimum depth of cover is:

        (I) 60 inches under the lowest point of the crossed grade;

        (II) 48 inches if the pipeline is outside of paved areas; or

        (III) a lesser depth than applicable under subclause (I) or (II) of this clause if the lesser depth is authorized by the district where a reinforced concrete slab is used to protect the pipeline.

    (B) Depth of cover for longitudinal placement. The minimum depth of cover for longitudinal installations is 48 inches.

    (C) Encasement. Low-pressure gas pipelines crossing the pavement shall be placed in a high-density polyethylene (HDPE) or equivalent encasement. The district may waive this encasement requirement if:

      (i) the pipeline is:

        (I) of welded steel construction; and

        (II) is protected from corrosion by cathodic protective measures or cold tar epoxy wrapping; and

      (ii) the utility signs a written agreement that the pavement will not be cut for pipeline repairs at any time in the future.

    (D) Vents. One or more vents shall be provided for each encasement or series of encasements. For encasements longer than 150 feet, vents shall be provided at both ends. On shorter encasements, a vent shall be located at the high end with a marker placed at the low end. Vents shall be placed at the right of way line immediately above the pipeline, situated so as not to interfere with highway maintenance or be concealed by vegetation, and may not be greater than six inches in diameter. The utility's name, address, and emergency telephone number shall be shown on each vent.

    (E) Aboveground appurtenances. Except for vents, pipeline markers, and gas rectifiers, aboveground utility appurtenances for gas lines are prohibited within department's right of way.

  (2) High-pressure pipelines and saltwater pipelines.

    (A) Depth of cover for crossings.

      (i) Depth of cover is the depth to the top of the encasement or carrier pipe if an encasement is not used. Where materials and other conditions justify, such as on existing lines remaining in place, the district may approve a minimum depth of cover under the pavement structure of 48 inches or one-half the diameter of the pipe, whichever is greater. For encased high-pressure pipeline, the minimum depth of cover is:

        (I) 60 inches or one-half the diameter of the pipe, whichever is greater, below the lowest point of the crossed grade unless a greater depth is required by the district; or

        (II) 48 inches if the pipeline is outside of the pavement structure, or 60 inches if under a ditch, below the lowest point of grade.

      (ii) Where a reinforced concrete slab is used to protect the pipeline, the district may authorize a reduction in the depths specified in this subparagraph.

      (iii) For unencased high-pressure pipelines, the minimum depth of cover is as follows:

        (I) 60 inches under the lowest point of the crossed grade, subject to subparagraph (D) of this paragraph; or

        (II) 60 inches under the lowest point of grade if the pipeline is placed outside the pavement structure or under a ditch.

    (B) Depth of cover for longitudinal placement. The minimum depth of cover is 48 inches.

    (C) Encasement. The encasement must be a vented steel pipe.

Cont'd...

Next Page Previous Page

Link to Texas Secretary of State Home Page | link to Texas Register home page | link to Texas Administrative Code home page | link to Open Meetings home page