RULE §25.195Terms and Conditions for Transmission Service

    (E) After the completion and energization of the initial interconnection, the responsibility for costs incurred by a TSP for new or upgraded interconnection facilities due to modifications or expansions made by the interconnected transmission-level generator will be borne in accordance with this subparagraph.

      (i) For the ten calendar years following the date of energization for the initial interconnection of the transmission-level generator, and to the extent that the costs of the new or upgraded interconnection facilities needed due to modifications made by the transmission-level generator exceed the remainder of the allowance calculated under paragraph (3) of this subsection, the current owner of the transmission-level generator that is listed in the new or amended SGIA is responsible for the interconnection costs incurred by the TSP, where:

        (I) the allowance is the amount that was in effect on the date the notice to proceed with the initial interconnection was issued in accordance with paragraph (3) of this subsection and the executed SGIA; and

        (II) the remainder is the difference between the allowance described under subclause (I) of this clause and the actual costs that a TSP incurred to construct, design, and upgrade interconnection facilities to initially interconnect the transmission-level generator. The remainder will be adjusted by the TSP in accordance with the methodology in subparagraph (A)(ii) of this paragraph.

      (ii) After ten calendar years from the date of energization for the initial interconnection, the transmission-level generator is eligible for a new allowance determined in accordance with paragraph (3)(A) of this subsection for the costs of new or upgraded interconnection facilities necessary to accommodate modifications made by the transmission-level generator at the same point of interconnection.

    (F) Beginning on or around May 1, 2029, and at least every five calendar years thereafter, the commission will open a project and request comments on whether the allowance or annual allowance adjustment methodology described in paragraph (3)(A) of this subsection should be modified. If the commission determines the allowance or the annual allowance adjustment methodology should be adjusted, the commission will initiate a rulemaking proceeding.

(g) Curtailment of service. In an emergency situation, as determined by ERCOT and at its direction, a TSP may interrupt transmission service on a non-discriminatory basis, if necessary, to preserve the stability of the transmission network and service to customers. Such curtailments must be carried out in accordance with §25.200 of this title (relating to Load Shedding, Curtailments, and Redispatch) and in accordance with ERCOT protocols.

(h) Filing of contracts. An electric utility must file with the commission each new, and all amendments to, interconnection agreements within 30 days of execution, including a cover letter explaining any deviations from the commission-approved SGIA. An interconnection agreement is subject to commission review and approval upon request by any party to the agreement. Appropriate portions of the filings may be filed confidentially and be subject to provisions of confidentiality to protect competitively sensitive commercial or financial information.

(i) Transmission-level generator interconnection costs report. ERCOT must, in consultation with commission staff, include as part of the ERCOT Generation Interconnection Status report or any successor report the generation interconnection costs for each new transmission-level generator interconnected in each calendar month based on date of energization, including the total cost of the interconnection, any CIAC paid by the transmission-level generator, and any above-allowance costs incurred by the transmission-level generator.

  (1) Beginning in January 2026, within 90 calendar days from the end of each calendar month the TSP must provide to ERCOT the information described in this subsection for each new transmission-level generator interconnection to the TSP's system in that calendar month.

  (2) Beginning in April 2027 and every calendar year thereafter, ERCOT will publish the information described in this subsection in a separate report for each new transmission-level generator interconnection to the ERCOT transmission system in the prior calendar year. ERCOT will, at a minimum, provide the information described in this subsection and total amounts for the prior calendar year.


Source Note: The provisions of this §25.195 adopted to be effective April 13, 1999, 24 TexReg 2874; amended to be effective June 20, 2001, 26 TexReg 4440; amended to be effective March 6, 2024, 49 TexReg 1262