(3) Following the date on which the initial performance
test is completed or is required to be completed under §113.2079 of this
title, whichever date comes first, the owner or operator shall ensure that
the designated facility does not operate above the maximum charge rate or
below the minimum secondary chamber temperature measured as three-hour rolling
averages (calculated each hour as the average of the previous three operating
hours) at all times except during periods of startup, shutdown, and malfunction.
Operating parameter limits do not apply during performance tests. Operation
above the maximum charge rate or below the minimum secondary chamber temperature
shall constitute a violation of the established operating parameters.
(4) Except as provided in paragraph (5) of this subsection,
operation of the designated facility above the maximum charge rate and below
the minimum secondary chamber temperature on a three-hour rolling average
simultaneously shall constitute a violation of the PM, CO, and dioxin/furan
emission limits.
(5) The owner or operator may conduct a repeat performance
test within 30 days of violation of applicable operating parameters to demonstrate
that the designated facility is not in violation of the applicable emission
limits. Repeat performance tests conducted under this subsection must be conducted
using the identical operating parameters that indicated a violation under
paragraph (4) of this subsection.
(c) Equivalent test methods may be approved by the executive
director or his designated representative.
|