RULE §299.24Construction Progress Reports

(a) The owner shall have a professional engineer provide the following information to the executive director in writing within ten working days after construction on the dam commences:

  (1) the actual start date;

  (2) the contractor's name and address; and

  (3) the name and telephone number of the professional engineer or inspector that will be on site during construction.

(b) The owner shall have a professional engineer submit monthly reports of progress on high- and significant-hazard dams to the executive director during construction. The report must include:

  (1) the work accomplished during the month;

  (2) the percent of the contract time used;

  (3) the percentage of completion of the project on the date of the report;

  (4) a description of problem areas encountered during construction;

  (5) the dates of the reporting period; and

  (6) any changes in the contact information.


Source Note: The provisions of this §299.24 adopted to be effective January 1, 2009, 33 TexReg 10465