(a) The department will make a decision on an application
within 60 days of the date of receipt of the application. If the decision
cannot be made within the 60 day period, the department will notify
the applicant of the delay providing the reason for the delay, and
provide an estimate of when the decision will be made.
(b) If the permit application is approved, the department
will issue a permit for the sign by sending a copy of the approved
application to the applicant.
(c) If the permit application is not approved, the
department will send a copy of the denied application and a notice
that states the reason for the denial.
(d) If the permit application is denied, the department
will notify the landowner identified on the permit application of
the denial by written notice. The notice is for informational purposes
only, and does not convey any rights to the landowner. The landowner
may not appeal the denial unless the landowner is also the applicant.
|