(a) The responsible party for an aggregate production
operation, in operation on or before September 1, 2012, shall register
each aggregate production operation with the commission within the
60-day period beginning September 1, 2012.
(b) The responsible party for an aggregate production
operation that begins extraction activities after September 1, 2012
shall register each aggregate production operation with the commission
not later than the 10th business day before the beginning date of
extraction activities.
(c) An aggregate processing plant that has the same
responsible party and is located at the same site from which aggregates
are being or have been removed or extracted from the earth is not
required to obtain a separate registration.
(d) The responsible party for an aggregate production
operation shall renew the registration annually as extraction activities
continue.
(e) The requirements of this chapter are not applicable
to aggregate production operations where:
(1) extraction activities have ceased; and
(2) the responsible party has submitted a registration
cancellation request to the commission or allowed the existing registration
to expire.
(f) Applications for registration or cancellation of
a registration shall be made on forms prescribed by the executive
director.
|