(a) Reimbursement of funds will be made in accordance
with the terms of the contract.
(b) After completion of the project, the awardee will
provide the following milestones and updates as required by the contract.
(c) Throughout the project period, the awardee must
provide copies of all reports required by federal agencies pursuant
to the terms of individual federal grants received, within 30 days
of their submission to the granting agencies.
(d) The awardee must provide all reports to the Commission
as required by the terms of the grant contract, including, but not
limited to, reports on any performance measures, milestone reports,
and project completion reports.
(e) Failure to submit reports in a timely and satisfactory
manner may result in the withholding of funds due or requested by
the awardee. Failure to document post-completion requirements may
result in the return of funds to the Commission as set forth in the
contract.
|
Source Note: The provisions of this §4.40 adopted to be effective November 25, 2009, 34 TexReg 8311; amended to be effective January 28, 2016, 41 TexReg 681; amended to be effective April 22, 2020, 45 TexReg 2539 |