RULE §25.62Transmission and Distribution System Resiliency Plans

(a) Purpose and applicability. This section allows an electric utility that owns and operates a transmission or distribution system to file a resiliency plan to enhance the resiliency of the electric utility's transmission and distribution system. The requirements of this section will be construed, to the extent practicable, to reflect the following:

  (1) Each transmission and distribution system has different system characteristics and faces different resiliency events and resiliency-related risks. The ability to precisely define, measure, and address these events and risks varies. Terms such as "event," "risk," "criteria," and "metric" will be construed pragmatically to provide each utility with the flexibility to develop a well-tailored and systematic approach to improving the resiliency of its system.

  (2) A utility seeking approval of a resiliency plan bears the burden of proof on each aspect of its resiliency plan. Nothing in this section categorically limits the type of evidence that a utility may use to meet this burden. The weight given to each piece of evidence will be determined by the commission on a case-by-case basis based on the relevant facts and circumstances. Provisions contained in this section addressing the weight of certain types of evidence are advisory only.

(b) Definitions. The following terms, when used in this section, have the following meanings unless the context indicates otherwise.

  (1) Distribution invested capital -- The parts of the electric utility's invested capital that are categorized or properly functionalized as distribution plant and, once they are placed into service, are properly recorded in Federal Energy Regulatory Commission (FERC) Uniform System of Accounts 303, 352, 353, 360 through 374, 391, and 397. Distribution invested capital includes only costs: for plant that has been placed into service or will be placed into service prior to rates going into effect; that comply with PURA, including §36.053 and §36.058; and that are prudent, reasonable, and necessary. Distribution invested capital does not include: generation-related costs; transmission-related costs, including costs recovered through rates set pursuant to §25.192 of this title (relating to Transmission Service Rates), §25.193 of this title (relating to Distribution Service Provider Transmission Cost Recovery Factors (TCRF)), or §25.239 of this title (relating to Transmission Cost Recovery Factor for Certain Electric Utilities); indirect corporate costs; capitalized operations and maintenance expenses; and distribution invested capital recovered through a separate rate, including a surcharge, tracker, rider, or other mechanism.

  (2) Resiliency cost recovery rider (RCRR) billing determinant -- Each rate class's annual billing determinant (kilowatt-hour, kilowatt, or kilovolt-ampere) for the most recent 12 months ending no earlier than 90 days prior to an application for a Resiliency Cost Recovery Rider, weather-normalized and adjusted to reflect the number of customers at the end of the period.

  (3) Resiliency event -- an event involving extreme weather conditions, wildfires, cybersecurity threats, or physical security threats that poses a material risk to the safe and reliable operation of an electric utility's transmission and distribution systems. A resiliency event is not primarily associated with resource adequacy or an electric utility's ability to deliver power to load under normal operating conditions.

  (4) Resiliency-related distribution invested capital -- Distribution invested capital associated with a resiliency plan approved under this section that will be placed into service before or at the time the associated rates become effective under this section, and that are not otherwise included in a utility's rates.

  (5) Resiliency-related net distribution invested capital -- Resiliency-related distribution invested capital that is:

    (A) adjusted for accumulated depreciation and any changes in accumulated deferred federal income taxes, including changes to excess accumulated deferred federal income taxes, associated with all resiliency-related distribution invested capital included in the electric utility's RCRR;

    (B) reduced by the amount of net plant investment associated with any distribution invested capital included in a utility's rates that is retired or replaced, at the time the associated rates become effective under this section, by resiliency-related distribution invested capital; and

    (C) further adjusted to remove accumulated depreciation and accumulated deferred federal income taxes associated with distribution invested capital included in a utility's rates that is retired or replaced, at the time the associated rates become effective under this section, by resiliency-related distribution invested capital.

  (6) Weather-normalized -- Adjusted for normal weather using weather data for the most recent ten-year period prior to the year from which the RCRR billing determinants are derived.

(c) Resiliency Plan. An electric utility may file a plan to prevent, withstand, mitigate, or more promptly recover from the risks posed by resiliency events to its transmission and distributions systems. A resiliency plan may be updated, but the updated plan must not take effect earlier than three years from the date of approval of the electric utility's most recently approved resiliency plan.

  (1) Resiliency measures. A resiliency plan is comprised of one or more measures designed to prevent, withstand, mitigate, or more promptly recover from the risks posed to the electric utility's transmission and distribution systems by resiliency events, as described in subsection (d) of this section. Each measure must utilize one or more of the following methods:

    (A) hardening electric transmission and distribution facilities;

    (B) modernizing electric transmission and distribution facilities;

    (C) undergrounding certain electric distribution lines;

    (D) lightning mitigation measures;

    (E) flood mitigation measures;

    (F) information technology;

    (G) cybersecurity measures;

    (H) physical security measures;

    (I) vegetation management; or

    (J) wildfire mitigation and response.

  (2) Contents of the resiliency plan. The resiliency plan must be organized by measure, including a description of any activities, actions, standards, services, procedures, practices, structures, or equipment associated with each measure.

    (A) The resiliency plan must identify, for each measure, one or more risks posed by resiliency events that the measure is intended to prevent, withstand, mitigate, or more promptly recover from.

      (i) The resiliency plan must explain the electric utility's prioritization of the identified resiliency event and, if applicable, the prioritization of the particular geographic area, system, or facilities where the measure will be implemented.

      (ii) The resiliency plan must include evidence of the effectiveness of the measure in preventing, withstanding, mitigating, or more promptly recovering from the risks posed by the identified resiliency event. The commission will give greater weight to evidence that is quantitative, performance-based, or provided by an independent entity with relevant expertise.

      (iii) A resiliency plan must explain the expected benefits of the resiliency measures including, as applicable, reduced system restoration costs, reduction in the frequency or duration of outages for customers. and any improvement in the overall service reliability for customers, including the classes of customers served and any critical load designations.

      (iv) The electric utility must identify if a resiliency measure is a coordinated effort with federal, state, or local government programs or may benefit from any federal, state, or local government funding opportunities.

      (v) The resiliency plan must explain the selection of each measure over any reasonable and readily-identifiable alternatives. The resiliency plan must contain sufficient analysis and evidence, such as cost or performance comparisons, to support the selection of each measure. In selecting between measures, whether a measure would support the plan's systematic approach may be considered.

      (vi) The resiliency plan must identify any measures that may require a transmission system outage to implement. The electric utility must coordinate with its independent system operator before implementing these measures. Upon request, the electric utility must provide its independent system operator, using mutually-agreed to transfer and data security procedures, a complete copy of its resiliency plan.

    (B) Resiliency events.