<<Prev Rule

Texas Administrative Code

Next Rule>>
TITLE 16ECONOMIC REGULATION
PART 2PUBLIC UTILITY COMMISSION OF TEXAS
CHAPTER 25SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS
SUBCHAPTER SWHOLESALE MARKETS
RULE §25.511Texas Energy Fund Completion Bonus Grant Program

(a) Purpose. The purpose of this section is to implement Public Utility Regulatory Act (PURA) §34.0105 and §34.0106 and establish:

  (1) Procedures for submitting an application to be eligible for a completion bonus grant award;

  (2) The process by which an applicant may receive an annual grant payment; and

  (3) Performance standards for electric generating facilities for which an applicant seeks a completion bonus grant payment.

(b) Definitions. The following words and terms, when used in this section, have the following meanings unless the context indicates otherwise.

  (1) Assessed hours--the 100 hours during the test period with the least quantity of operating reserves, as determined by the highest values of peak net load, where peak net load is calculated as gross load minus wind, solar, and storage injection.

  (2) Availability reliability factor (ARF)--a metric calculated with ERCOT data for each generation resource for which the commission awards a completion bonus grant under this section. The ARF is computed as the proportion of time that each generation resource was available (i.e., not in a planned outage) during the assessed hours. The ARF is calculated as follows: "Total evaluated period intervals" is equal to the total number of intervals during the assessed hours, excluding any that occurred during an approved planned outage of the generation resource. "Total period intervals" is equal to the total number of intervals during the assessed hours.

Attached Graphic

  (3) Interconnection date -- the resource commissioning date, as defined in the ERCOT protocols, for the last generation resource in an electric generating facility for which an applicant seeks a completion bonus grant award. The new electric generating facility or new generation resources at an existing electric generating facility must meet the eligibility criteria described in subsection (c) of this section.

  (4) Performance reliability factor (PRF) -- a metric calculated with ERCOT availability and real time (RT) telemetered data for each generation resource for which the commission awards a completion bonus grant under this section. The PRF is computed as the average ratio of each generation resource's RT high sustainable limit (HSL) and its obligated capacity over the assessed hours. Intervals that occurred during an approved planned outage of a generation resource are excluded. The PRF is calculated as follows: "RT Telemetered HSL" is the HSL telemetered by the generation resource in real time. "Available Flag" is a binary flag that is equal to the minimum of a current operating plan (COP) available flag and a RT available flag. "COP available flag" is a binary flag that equals one if each hourly check of the generation resource's COP for the hour that includes the interval in question indicates that the generation resource will be available in that interval (i.e., any status other than OUT or EMRSWGR), with such hourly checks starting at 14:30 on the day before the relevant interval; otherwise, the flag equals zero. "RT available flag" is a binary flag that equals one if the RT telemetered resource status code indicates the generation resource is available (i.e., any status other than OUT or EMRSWGR); otherwise, the flag equals zero. For a generation resource that provides capacity to an industrial load or private use network (PUN), obligated capacity is equal to the net capacity that is dedicated to ERCOT, as of the interconnection date. For all other generation resources, obligated capacity is equal to the adjusted seasonal net max sustainable rating (defined as the registered ERCOT Seasonal Net Max Sustainable Rating adjusted for planned derates). "Total evaluated period intervals" is equal to the total number of intervals during the assessed hours, excluding any that occurred during an approved planned outage of the generation resource.

Attached Graphic

  (5) Test period -- the one-year period starting on June 1 of one year and ending on May 31 of the following year.

(c) Eligibility. To be eligible for a completion bonus grant award under this section, an applicant must construct at least 100 MW of new nameplate capacity, either as new generation resources in a new electric generating facility, or new generation resources at an existing electric generating facility, and the generation resources for which a completion bonus grant is sought must also:

  (1) interconnect to and provide power for the ERCOT region;

  (2) be dispatchable with an output that can be controlled primarily by forces under human control;

  (3) not be an electric energy storage facility;

  (4) participate in the ERCOT wholesale market;

  (5) consist of one or more generation resources physically capable of interconnecting to the ERCOT region through a single point of interconnection;

  (6) be eligible to interconnect to the ERCOT region based on the attributes of the owners of the electric generating facility, according to the requirements in the Lone Star Infrastructure Protection Act (codified at Texas Business and Commerce Code §117.002);

  (7) not meet the planning model requirements necessary to be included in an ERCOT capacity, demand, and reserves report for the ERCOT region before June 1, 2023 for the construction or addition of any generation resource;

  (8) operate in such a manner that the electric generating facility that is serving an industrial load or PUN must meet the following conditions: the portion of nameplate capacity that will serve the maximum non-coincident peak demand of the industrial load or PUN must be less than 50 percent of the facility's total nameplate capacity, and the remaining capacity serving the ERCOT market must be greater than 100 MW; and

  (9) meet the interconnection deadlines described in subsection (e)(2) of this section.

(d) Determination of eligibility for completion bonus grant award.

  (1) Eligibility application. No earlier than January 1, 2025, and no later than 180 days after the interconnection date of the electric generating facility for which an applicant requests a completion bonus grant award, an applicant must submit an electronic application in the form and manner prescribed by the commission. The application must include:

    (A) the applicant's legal name and the proposed name of each generation resource in the electric generating facility for which it seeks a completion bonus grant award. A corporate sponsor or parent may submit the application on behalf of its subsidiary applicant;

    (B) information describing the applicant's quality of services and management;

    (C) information describing the applicant's efficiency of operations;

    (D) a record of the applicant's history of electric generation operations in this state and this country, including information demonstrating the applicant's experience operating and maintaining dispatchable electric generating facilities;

    (E) a description of the operational attributes of the electric generating facility; if any generation resource in the electric generating facility will serve an industrial load or PUN, a description of the manner in which it will serve the industrial load or PUN, how the electric generating facility will primarily serve and benefit the ERCOT bulk power system given its relationship to a PUN or industrial load, the total nameplate capacity of the electric generating facility, the anticipated or actual maximum non-coincident peak demand of the associated industrial load or PUN, whether the electric generating facility's generation capacity would be available to the ERCOT bulk power system during any Energy Emergency Alert, and a copy of any information submitted to ERCOT regarding PUN net generation capacity availability;

    (F) a description of the electric generating facility's ability to address regional and reliability needs;

    (G) for electric generating facilities not yet interconnected to the ERCOT region:

      (i) a proposed project schedule with anticipated dates for completion of construction, submission of registration documents with ERCOT and the commission, and anticipated interconnection date;

      (ii) the anticipated nameplate capacity of the electric generating facility when commercial operations begin; and

      (iii) the estimated construction costs of the electric generating facility.

    (H) for electric generating facilities already interconnected to the ERCOT region:

      (i) the actual construction costs of the electric generating facility, listed by generation resource;

      (ii) the interconnection date of the newly constructed electric generating facility or of the last new generation resource added to an existing electric generating facility;

      (iii) the total nameplate capacity of each generation resource in the electric generating facility that meets the eligibility requirement described in subsection (c)(7) of this section; and

Cont'd...

Next Page

Link to Texas Secretary of State Home Page | link to Texas Register home page | link to Texas Administrative Code home page | link to Open Meetings home page