<<Prev Rule

Texas Administrative Code

Next Rule>>
TITLE 16ECONOMIC REGULATION
PART 2PUBLIC UTILITY COMMISSION OF TEXAS
CHAPTER 25SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS
SUBCHAPTER ITRANSMISSION AND DISTRIBUTION
DIVISION 1OPEN-ACCESS COMPARABLE TRANSMISSION SERVICE FOR ELECTRIC UTILITIES IN THE ELECTRIC RELIABILITY COUNCIL OF TEXAS
RULE §25.192Transmission Rates for Export from ERCOT

(a) Tariffs. Each transmission service provider (TSP) shall file a tariff for transmission service to establish its rates and other terms and conditions and shall apply its tariffs and rates on a non-discriminatory basis. The tariff shall apply to all distribution service providers (DSPs) and any entity scheduling the export of power from the Electric Reliability Council of Texas (ERCOT) region. The tariff shall not apply to any entity engaging in wholesale storage as described by §25.501(m) of this title (relating to Wholesale Market Design for the Electric Reliability Council of Texas) (storage entity).

(b) Charges for transmission service delivered within ERCOT. DSPs, excluding storage entities, shall incur transmission service charges pursuant to the tariffs of the TSP.

  (1) A TSP's transmission rate shall be calculated as its commission-approved transmission cost of service divided by the average of ERCOT coincident peak demand for the months of June, July, August and September (4CP), excluding the portion of coincident peak demand attributable to wholesale storage load. A TSP's transmission rate shall remain in effect until the commission approves a new rate. The TSP's annual rate shall be converted to a monthly rate. The monthly transmission service charge to be paid by each DSP is the product of each TSP's monthly rate as specified in its tariff and the DSP's previous year's average of the 4CP demand that is coincident with the ERCOT 4CP.

  (2) Payments for transmission services shall be consistent with commission orders, approved tariffs, and §25.202 of this title (relating to Commercial Terms for Transmission Service).

(c) Transmission cost of service. The transmission cost of service for each TSP shall be based on the expenses in Federal Energy Regulatory Commission (FERC) expense accounts 560-573 (or accounts with similar contents or amounts functionalized to the transmission function) plus the depreciation, federal income tax, and other associated taxes, and the commission-allowed rate of return based on FERC plant accounts 350-359 (or accounts with similar contents or amounts functionalized to the transmission function), less accumulated depreciation and accumulated deferred federal income taxes, as applicable.

  (1) The following facilities are deemed to be transmission facilities:

    (A) power lines, substations, reactive devices, and associated facilities, operated at 60 kilovolts or above, including radial lines operated at or above 60 kilovolts, except the step-up transformers and a protective device associated with the interconnection from a generating station to the transmission network;

    (B) substation facilities on the high side of the transformer, in a substation where power is transformed from a voltage higher than 60 kilovolts to a voltage lower than 60 kilovolts;

    (C) the portion of the direct-current interconnections with areas outside of the ERCOT region (DC ties) that are owned by a TSP in the ERCOT region, including those portions of the DC tie that operate at a voltage lower than 60 kilovolts; and

    (D) capacitors and other reactive devices that are operated at a voltage below 60 kilovolts, if they are located in a distribution substation, the load at the substation has a power factor in excess of 0.95 as measured or calculated at the distribution voltage level without the reactive devices, and the reactive devices are controlled by an operator or automatically switched in response to transmission voltage.

    (E) As used in subparagraphs (A) - (D) of this paragraph, reactive devices do not include generating facilities.

  (2) For municipally owned utilities, river authorities, and electric cooperatives, the commission may permit the use of the cash flow method or other reasonable alternative methods of determining the annual transmission revenue requirement, including the return element of the revenue requirement, consistent with the rate actions of the rate-setting authority for a municipally owned utility.

  (3) For municipally owned utilities, river authorities, and electric cooperatives, the return may be determined based on the TSP's actual debt service and a reasonable coverage ratio. In determining a reasonable coverage ratio, the commission will consider the coverage ratios required in the TSP's bond indentures or ordinances and the most recent rate action of the rate setting authority for the TSP.

  (4) A municipally owned utility that is required to apply for a certificate of public convenience and necessity to construct, install, or extend a transmission facility within ERCOT pursuant to §25.101 of this title (relating to Certification Criteria) is entitled to recover, through the utility's wholesale transmission rate, reasonable payments made to a taxing entity in lieu of ad valorem taxes on that transmission facility, provided that:

    (A) The utility enters into a written agreement with the governing body of the taxing entity related to the payments;

    (B) The amount paid is the same as the amount the utility would have to pay to the taxing entity on that transmission facility if the facility were subject to ad valorem taxation;

    (C) The governing body of the taxing entity is not the governing body of the utility; and

    (D) The utility provides the commission with a copy of the written agreement and any other information that the commission considers necessary in relation to the agreement.

  (5) The commission may adopt rate-filing requirements that provide additional details concerning the costs that may be included in the transmission costs and how such costs should be reported in a proceeding to establish transmission rates.

(d) Billing units. No later than December 1 of each year, ERCOT shall determine and file with the commission the current year's average 4CP demand for each DSP, or the DSP's agent for transmission service billing purposes, as appropriate, excluding the portion of coincident peak demand attributable to wholesale storage load. This demand shall be used to bill transmission service for the next year. The ERCOT average 4CP demand shall be the sum of the coincident peak of all of the ERCOT DSPs, excluding the portion of coincident peak demand attributable to wholesale storage load, for the four intervals coincident with ERCOT system peak for the months of June, July, August, and September, divided by four. As used in this section, a DSP's average 4CP demand is determined from the total demand, coincident with the ERCOT 4CP, of all customers connected to a DSP, including load served at transmission voltage, but excluding the load of wholesale storage entities. The measurement of the coincident peak shall be in accordance with commission-approved ERCOT protocols.

(e) Transmission rates for exports from ERCOT. A transmission service charge for exports of power from ERCOT must be assessed to transmission service customers for transmission service within the boundaries of the ERCOT region, in accordance with this section and the ERCOT protocols.

  (1) A transmission service customer must be assessed a transmission service charge for the use of the ERCOT transmission system in exporting power from ERCOT based on scheduled exports and the rates established under subsections (c) and (d) of this section. The intervals must consist of one hour.

  (2) The hourly transmission rate for exports from ERCOT will be the TSP's annual rate established under subsections (c) and (d) of this section divided by 8760.

  (3) The entity scheduling the export of power over a DC tie is solely responsible to the TSP for payment of transmission service charges under this subsection.

  (4) Beginning with the January 2023 reporting month, ERCOT must file a public report with the commission stating the total amount of energy imported and the total amount of energy exported over each DC tie for the calendar month. The report must also include the total amount of energy exported from the ERCOT region during the reporting month and each of the preceding 11 calendar months, reported by scheduling entity. Each report must be filed within 45 days of the end of the reporting month.

(f) Transmission revenue. Revenue from the transmission of electric energy out of the ERCOT region over the DC ties that is recovered under subsection (e) of this section shall be credited to all transmission service customers as a reduction in the transmission cost of service for TSPs that receive the revenue.

(g) Revision of transmission rates. Each TSP in the ERCOT region shall periodically revise its transmission service rates to reflect changes in the cost of providing such services. Any request for a change in transmission rates shall comply with the filing requirements established by the commission under this section.

(h) Interim Update of Transmission rates.

Cont'd...

Next Page

Link to Texas Secretary of State Home Page | link to Texas Register home page | link to Texas Administrative Code home page | link to Open Meetings home page