(a) After the public comment period or the conclusion of any
notice and comment hearing, the commission shall send notice by first-class
mail of the final action on the application to any person who commented during
the public comment period or at the hearing, and to the applicant.
(b) The notice must include the following:
(1) the response to any comments submitted during the public
comment period;
(2) identification of any change in the conditions of
the draft electric generating facility permit and the reasons for the change;
(3) a statement that any person affected by the decision
of the commission may petition for rehearing under the appropriate procedure
in Chapter 50 of this title (relating to Action on Applications and Other
Authorizations) and may seek judicial review under TCAA, §382.032 (relating
to Appeal of Commission Action).
|