RULE §24.233Contents of Certificate of Convenience and Necessity Applications

(a) Application. To obtain or amend a certificate of convenience and necessity (CCN), a person, public water or sewer utility, water supply or sewer service corporation, affected county as defined in §24.3(4) of this title (relating to Definitions of Terms), county, district, or municipality shall file an application for a new CCN or a CCN amendment. Applications must contain the following materials, unless otherwise specified in the application form:

  (1) the appropriate application form prescribed by the commission, completed as instructed and properly executed;

  (2) mapping documents as prescribed in §24.259 of this title (relating to Mapping Requirements for Certificate of Convenience and Necessity Applications);

  (3) information to demonstrate a need for service in the requested area, including:

    (A) a copy of each written request for service received, if any; and

    (B) a map showing the location of each request for service, if any;

  (4) if applicable, a statement that the requested area overlaps with the corporate boundaries of a district, municipality, or other public authority, including:

    (A) a list of the entities that overlap with the requested area; and

    (B) evidence to show that the applicant has received the necessary approvals including any consents, franchises, permits, or licenses to provide retail water or sewer utility service in the requested area from the applicable municipality, district, or other public authority that:

      (i) currently provides retail water or sewer utility service in the requested area;

      (ii) is authorized to provide retail water or sewer service by enabling statute or order; or

      (iii) has an ordinance in effect that allows it to provide retail water or sewer service in the requested area, if any.

  (5) an explanation from the applicant demonstrating that issuance of a new CCN or a CCN amendment is necessary for the service, accommodation, convenience, or safety of the public;

  (6) if the infrastructure is not already in place or if existing infrastructure needs repairs and improvements to provide continuous and adequate service to the requested area, a capital improvement plan, including a budget and an estimated timeline for construction of all facilities necessary to provide full service to the requested area, keyed to a map showing where such facilities will be located to provide service;

  (7) a description of the sources of funding for all facilities that will be constructed to serve the requested area, if any;

  (8) disclosure of all affiliated interests as defined by §24.3 of this title;

  (9) to the extent known, a description of current and projected land uses, including densities;

  (10) a current financial statement of the applicant;

  (11) according to the tax roll of the central appraisal district for each county in which the requested area is located, a list of the owners of each tract of land that is:

    (A) at least 25 acres; and

    (B) wholly or partially located within the requested area;

  (12) if dual certification is being requested, a copy of the executed agreement that allows for dual certification of the requested area. Where such an agreement is not practicable, a statement of why dual certification is in the public interest;

  (13) if an amendment is being requested with the consent of the existing CCN holder, a copy of the executed agreement to amend the existing certificated service area;

  (14) for an application for a new water CCN or a CCN amendment that will require the construction of a new public drinking water system or facilities to provide retail water utility service, a copy of:

    (A) the approval letter for the plans and specifications issued by the TCEQ for the public drinking water system or facilities. Proof that the applicant has submitted plans and specifications for the proposed drinking water system is sufficient for a determination of administrative completeness. The applicant shall notify the commission within ten days upon receipt of any TCEQ disapproval letter. If the applicant receives a TCEQ disapproval letter, the application for a new water CCN or a CCN amendment may be subject to dismissal without prejudice. Any approval letter for the proposed public drinking water system or facilities must be filed with the commission before the issuance of a new CCN or a CCN amendment. Failure to provide such approvals within a reasonable amount of time after the application is found administratively complete may result in dismissal of the application without prejudice. Plans and specifications are only required if the proposed change in the existing capacity is required by TCEQ rules;

    (B) other information that indicates the applicant is in compliance with §24.205 of this title (relating to Adequacy of Water Utility Service) for the system; or

    (C) a contract with a wholesale provider that meets the requirements in §24.205 of this title;

  (15) for an application for a new sewer CCN or CCN amendment that will require the construction of a new sewer system or new facilities to provide retail sewer utility service, a copy of:

    (A) a wastewater permit or proof that a wastewater permit application for the additional facility has been filed with the TCEQ. Proof that the applicant has submitted an application for a wastewater permit is sufficient for a determination of administrative completeness. The applicant shall notify the commission within ten days upon receipt of any TCEQ disapproval letter. If the applicant receives a TCEQ disapproval letter, the application for a new sewer CCN or CCN amendment may be subject to dismissal without prejudice. Any approval letter for the permit application must be filed with the commission before the issuance of a new CCN or a CCN amendment. Failure to provide such approvals within a reasonable amount of time after the application is found administratively complete may result in the dismissal of the application without prejudice. Plans and specifications are only required if the proposed change in the existing capacity is required by TCEQ rules.

    (B) other information that indicates that the applicant is in compliance with §24.207 of this title (relating to Adequacy of Sewer Service) for the facility; or

    (C) a contract with a wholesale provider that meets the requirements in §24.207 of this title; and

  (16) any other item or information required by the commission.

(b) If the requested area overlaps the boundaries of a district, and the district does not intervene in the docket by the intervention deadline after notice of the application is given, the commission shall determine that the district is consenting to the applicant's request to provide service in the requested area.

(c) Application within the municipal boundaries or extraterritorial jurisdiction of certain municipalities.

  (1) This subsection applies only to a municipality with a population of 500,000 or more.

  (2) Except as provided by paragraphs (3) - (7) of this subsection, the commission may not grant to a retail public utility a CCN for a requested area within the boundaries or extraterritorial jurisdiction of a municipality without the consent of the municipality. The municipality may not unreasonably withhold the consent. As a condition of the consent, a municipality may require that all water and sewer facilities be designed and constructed in accordance with the municipality's standards for facilities.

  (3) If a municipality has not consented under paragraph (2) of this subsection before the 180th day after the date the municipality receives the retail public utility's application, the commission shall grant the CCN without the consent of the municipality if the commission finds that the municipality:

    (A) does not have the ability to provide service; or

    (B) has failed to make a good faith effort to provide service on reasonable terms and conditions.

  (4) If a municipality has not consented under this subsection before the 180th day after the date a landowner or a retail public utility submits to the municipality a formal request for service according to the municipality's application requirements and standards for facilities on the same or substantially similar terms as provided by the retail public utility's application to the commission, including a capital improvement plan required by TWC §13.244(d)(3) or a subdivision plat, the commission may grant the new CCN or a CCN amendment without the consent of the municipality if:

    (A) the commission makes the findings required by paragraph (3) of this subsection;

    (B) the municipality has not entered into a binding commitment to serve the requested area before the 180th day after the date the formal request was made; and