(a) 10% Test (Competitive HTC Only). No later than July 1 of the year following the submission of the Carryover Allocation Agreement or as otherwise specified in the applicable year's Qualified Allocation Plan, documentation must be submitted to the Department verifying that the Development Owner has expended more than 10% of the Development Owner's reasonably expected basis, pursuant to §42(h)(1)(E)(i) and (ii) of the Code and Treasury Regulations, 26 CFR §1.42-6. The Development Owner must submit, in the form prescribed by the Department, documentation evidencing paragraphs (1) - (7) of this subsection, along with all information outlined in the Post Award Activities Manual. Satisfaction of the 10% Test will be contingent upon the submission of the items described in paragraphs (1) - (7) of this subsection as well as all other conditions placed upon the Application in the Commitment. Requests for an extension will be reviewed on a case by case basis as addressed in §10.405(c) of this subchapter and §11.2 of this title, as applicable, and a point deduction evaluation will be completed in accordance with Tex. Gov't Code §2306.6710(b)(2) and §11.9(f) of this title. Documentation to be submitted for the 10% Test includes:

  (1) An Independent Accountant's Report and Taxpayer's Basis Schedule form. The report must be prepared on the accounting firm's letterhead and addressed to the Development Owner or an Affiliate of the Development Owner. The Independent Accountant's Report and Taxpayers Basis Schedule form must be signed by the Development Owner. If, at the time the accountant is reviewing and preparing their report, the accountant has concluded that the taxpayer's reasonably expected basis is different from the amount reflected in the Carryover Allocation agreement, then the accountant's report should reflect the taxpayer's reasonably expected basis as of the time the report is being prepared;

  (2) Any conditions of the Commitment or Real Estate Analysis underwriting report due at the time of 10% Test submission;

  (3) Evidence that the Development Owner has purchased, transferred, leased, or otherwise has ownership of the Development Site and a current title policy. The Development Site must be identical to the Development Site that was submitted at the time of Application submission. For purposes of this paragraph, any changes to the Development Site acreage between Application and 10% Test must be addressed by written explanation or, as appropriate, in accordance with §10.405 of this subchapter (relating to Amendments and Extensions);

  (4) A current survey or plat of the Development Site, prepared and certified by a duly licensed Texas Registered Professional Land Surveyor. The survey or plat must clearly delineate the flood plain boundary lines and show all easements and encroachments;

  (5) For New Construction, Reconstruction, and Adaptive Reuse Developments, a certification from a Third Party civil engineer or architect stating that all necessary utilities will be available at the Development Site and that there are no easements, licenses, royalties, or other conditions on or affecting the Development that would materially or adversely impact the ability to acquire, develop, and operate as set forth in the Application. Copies of supporting documents may be required by the Department;

  (6) For the Development Owner and on-site or regional property manager, training certificate(s) from a Department approved "property owner and manager Fair Housing trainer" showing that a controlling Principal in the Development Owner structure and an on-site or regional property manager attended and passed at least five hours of Fair Housing training. For architects and engineers, training certificate(s) from a Department approved "architect and engineer Fair Housing trainer" showing that the lead architect or engineer responsible for certifying compliance with the Department's accessibility and construction standards has attended and passed at least five hours of Fair Housing training. Certifications required under this paragraph must not be older than three years from the date of submission of the 10% Test Documentation, and must verify that all parts or phases of the offered training have been completed; two certificates supplied for the same part or phase of an offered training will not be counted towards the five hour required minimum, even if they were attended on different dates; and

  (7) A Certification from the lender and syndicator identifying all known Guarantors. If identified Guarantors have changed from the Guarantors or Principals identified at the time of Application, a non-material amendment may be required in accordance with §10.405 of this subchapter (relating to Amendments and Extensions), and the new Guarantors or Principals must be reviewed in accordance with Chapter 1, Subchapter C of this title (relating to Previous Participation and Executive Award Review and Advisory Committee).

  (8) Evidence of submission of the CMTS Filing Agreement pursuant to §10.607(a) of this title (relating to Reporting Requirements).

(b) Construction Status Report (All Multifamily Developments). All multifamily Developments must submit a construction status report. Construction status reports shall be due by the tenth day of the month following each reporting quarter's end (January, April, July, and October) and continue on a quarterly basis until the entire Development is complete as evidenced by one of the following: Certificates of occupancy for each building, the Architect's Certificate(s) of Substantial Completion (AIA Document G704 or equivalent form) for the entire Development, the final Application and Certificate for Payment (AIA Document G702 and G703), or an equivalent form approved for submission by the construction lender and/or investor. For Competitive Housing Tax Credit Developments, the initial report is due by October 10th following the year of award (this includes Developments funded with HTC and TDHCA Multifamily Direct Loans), and for Developments awarded under the Department's Multifamily Direct Loan programs only, the initial report is due by the 90th calendar day after loan closing. For Tax Exempt Bond Developments, the initial construction status report must be submitted as part of the Post Bond Closing Documentation and is due by the 60th calendar day following closing on the bonds. A Construction Status Report not submitted by the due date will incur an extension fee in accordance with §11.901 of this title (relating to Fee Schedule). The initial report for all multifamily Developments shall consist of the items identified in paragraphs (1) - (6) of this subsection, unless stated otherwise. All subsequent reports shall contain items identified in paragraphs (4) - (6) of this paragraph and must include any changes or amendments to items in paragraphs (1) - (3) if applicable:

  (1) The executed partnership agreement with the investor or, for Developments receiving an award only from the Department's Direct Loan Program, other documents setting forth the legal structure and ownership. If identified Guarantors or Principals of a Guarantor entity were not already identified as a Principal of the Owner, Developer, or Guarantor at the time of Application, a non-material amendment must be requested in accordance with §10.405 of this subchapter, and the new Guarantors and all of its Principals, as applicable, must be reviewed in accordance with Chapter 1, Subchapter C of this title (relating to Previous Participation and Executive Award Review and Advisory Committee);

  (2) The executed construction contract for the General Contractor, prime subcontractor(s) and Affiliates or Related Party subcontractor(s);

  (3) The construction loan agreement. If the loan has not closed, the anticipated closing date must be provided and, upon closing, the agreement must be provided to the Department;

  (4) The most recent Application and Certificate for Payment (AIA Document G702 and G703) certified by the Architect of Record (or equivalent form approved for submission by the construction lender and/or investor) for the General Contractor, prime subcontractor(s) and Affiliates or Related Party subcontractor(s);

  (5) All Third Party construction inspection reports not previously submitted. If the lender and/or investor does not require third party construction inspection reports, the Development Owner must hire a third party inspector to perform these inspections on a quarterly basis and submit the reports to the Department. Third Party construction inspection reports must include, at a minimum, the date construction started (initial submission only), a discussion of site conditions as of the date of the site visit, current photographs of the construction site and exterior and interior of buildings, an estimated percentage of construction completion as of the date of the site visit, identification of construction delays and other relevant progress issues, if any, and the anticipated construction completion date; and

Cont'd...